During a month, a machine runs for 600 hours. The machine was under breakdown for 60 hours. There was industrial unrest resulting in idle time of 60 hours. Assume 30 days months of 24 hours a day work. The maintenance workers are paid incentive as per the following details. Breakdown%.    Incentive <5%.                      100 5-10%.                     50 7-11%.                        0 (i) What is the incentive amount actually paid in the month? (ii) What is the overall productivity?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter9: Decision Making Under Uncertainty
Section: Chapter Questions
Problem 30P
icon
Related questions
icon
Concept explainers
Topic Video
Question

Problem :

During a month, a machine runs for 600 hours. The machine was under breakdown for 60 hours. There was industrial unrest resulting in idle time of 60 hours. Assume 30 days months of 24 hours a day work. The maintenance workers are paid incentive as per the following details.

Breakdown%.    Incentive

<5%.                      100

5-10%.                     50

7-11%.                        0

(i) What is the incentive amount actually paid in the month?

(ii) What is the overall productivity?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,