For the fllowing schedule, draw the node network, perform the C. tions, mark the critical path, and complete the table. Activity Duration IPA ES EF LS LF TF FF A 2 в 7 A 10 A D 5 A 4
Q: H.W For the following activities, draw the network diagram and by using forward and backward pass,…
A: Given data is
Q: 1. Draw the network. Determine the critical path. See Module 4 Problem 4 worksheet.
A: Hello thank you for the question. As per guidelines, we would provide only one answer at a time.…
Q: (a) Construct the AON network for the project. (b) Determine all paths that run from the start to…
A: Activity-on-node is a project management term that leads to a precedence diagramming method that…
Q: a. Choose the correct project network diagram below. A. OB. More info Activity Duration (days)…
A: The project network is the diagram that shows the order of completion of project network activities…
Q: Draw the activity-on-node (AON) project networkassociated with the following activities for Carl…
A: Project scheduling is a tool used by organizations and managers in project planning and…
Q: Consider the following information for a project to add a drive-through window at Crestview Bank.a.…
A:
Q: ACTIVITY PREDECESSORS DURATION (DAYS) A 3 B A 4 A D B 5 1 F D,E F,G 4 3 You are required to a) Draw…
A:
Q: Consider the following information for a project to add a drive-through window at Crestview Bank. a.…
A: b. The critical path is B-E-G-H. c. Slack for the activities A and D are 8 each.
Q: Fill the table below using the Activity-on-Arrow (A-o-A) network given and answer the questions.…
A:
Q: truct a network diagram and determine ES, EF slack times of all activities. mine the expected…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: b) - Draw the Activity-on-Node (AON) diagram using the following representation for every node:…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: D) Using the precedence table given, construct the precedence matrix and draw an activity-on-node…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Develop an "activity on Node" network diagram for this project and answer the following questions…
A: Project duration is the total time taken to complete the project successfully measurable in days or…
Q: For the following network, figure out the total floats and the critical path assuming interruptible…
A: Find the Given details below: Given details: Activity Duration A 4 B 3 C 8 D 7 E 6…
Q: Using the data in the following table: a) Draw the network diagram b) List the network paths, the…
A: Given data is
Q: What are the objectives of construction management?
A: NOTE: We are allowed to do one question only at a time. Please post the rest questions individually…
Q: 1) Find out the CP by drawing the Network diagram (need to show ES, Duration.EF, LS, LF, Slack) 2)…
A: Below is the solution:-
Q: Activity Time (Weeks) Immediate Predecessor(s) A 10 - B 8 - C 9 A D 7 A E 6 B F 12 B G 5 D,E H 4 D,E…
A:
Q: The following information concerns a project to raise moneyfor the Kids Against Crime…
A:
Q: 5. For the following problem, draw a network Activity A B C D E F G H IJ Immediate B А,В A,B B D,E,F…
A: Activity Immediate Predecessors A - B - C B D A,B E A,B F B G D,E,F H D,E I E,F…
Q: What is the critical path of the network?
A:
Q: Consider the following information for a project to add a drive-through window at Crestview Bank.…
A:
Q: Problem #2 A contractor has six jobs awaiting processing at a workstation that is also a bottleneck…
A: Total no. of jobs = 6 Current day = 7 Flow time (Current) = Flow time (Previous) + Duration…
Q: QI/ The following table shows the activities of a construction project, sequences and estimated…
A:
Q: For the project detailed in the table below: a) Draw the Activity on Node (AON) network diagram…
A: Activity Immediate Predecessors Duration A - 4 B - 6 C A,B 7 D B 8 E B 5 F C 5 G D 7…
Q: For the following schedule, draw the node network, perform the CPM calculations, mark the critical…
A: Given data is
Q: Construct a CPM network based on activity on node method with the details given below and find the…
A: Given information, Activity Immediate Predecessor Duration A 1 B A 4 C A 2 D A 2 E…
Q: The following table contains information related to the major activities of a research project. Use…
A:
Q: Draw and analyze a project network diagram to answer the following questions: What is the most that…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: REQUIRED: a. Prepare the PERT Network for the US Tea project b. What is the critical path and its…
A: The answer is as below:
Q: 2. An advertising project manager developed the network diagram shown in Figure below for a new…
A: Formula used- Early Start (ES) = Max EF of its predecessor Early Finish (EF) =ES +Duration Late…
Q: The critical path for the network activities shown below is with duration Immediate Activity…
A:
Q: 03 Proceed to solve the following problem by Critical Path Method. Name of Activity A Immediate…
A: Critical Path Method (CPM) is a task plan demonstrating strategy. Mr. Morgan R. Walker and James E.…
Q: The table below shows a schedule. Activity Duration Predecessor Cost of crashing Max. days it can be…
A: Draw Network Diagram :
Q: b) - Draw the Activity-on-Node (AON) diagram using the following representation for every node:…
A: Activity-on-node is a project management term that directs to a precedence diagramming technique…
Q: QI: Given the information below, draw the network (AOA) and find the probability of finishing the…
A: Let the task names for each activity from A, B,....n. Given data is
Q: The following information is available about a project toorganize an event to honor the mayor of…
A: Given data
Q: Make a clear and neat sketch of the network specified belowusing precedence notation. On the…
A: Activity Duration EST EFT LST LFT TF(LFT-EFT) A 2 0 2 0 2 0 B 4 2 6 2 6 0 C 7 2 9 5 12 3 D 3…
Q: You are required to draw the Critical Path Method (CPI) and complete all the necessary calculations…
A: The critical path is found by drawing the network diagram and assessing all the possible paths and…
Q: For each of the following network diagrams, determine both the critical path and the expected proj-…
A: The network diagrams for critical path can be constructed in two ways: Arrow to Node - AON Arrow to…
Q: Draw the activity-on-node (AON) project network associated with the following activities for Carl…
A: The network diagram is as below:-
Q: 6. For the following schedule, draw the node network, perform the CPM calcula- tions, mark the…
A:
Q: From the following schedule, draw the precedence network, perform the CPM calculations, mark the…
A: Here, Network Diagram is produced using forward path method and backward path method, in forward…
Q: Describe how expected activity times and variances can be computed in a PERT network.
A: The United States Defence was the first to develop and apply the PERT estimation technique (Program…
Q: A D A A B,C D H D,E F H,G You are required to a) Draw the network diagram b) Calculate ES, EF, LS,…
A: The answer is as below:
Q: a. Use the Table 1 above to develop a network diagram. b. Calculate the Early Start (ES), Early…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Read the following set of activities carefully. The precedence of all activities is finish to start.…
A: The program evaluation and review technique (PERT) is a statistical device utilized in undertaking…
Q: Below is the first set of activities (Phase I) in constructing a new house, the respective time…
A: Find the Given details below: Activity Description Predecessor Duration (Weeks) A Clear site -…
Q: To complete the problem the following is necessary. 1) project network diagram (AON), 2) table that…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
For the following
P;ease use the format provided in the screenshots.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images
- please correct and not handwritten, also explain the concept and formulas pls ill like.Tufte's argument that the space shuttle Challenger disaster was a direct result of the poorly displayed information. This example of the possible consequences of poor data display is certainly extreme. But similarly, poor data displays are an everyday occurrence in many organizations in the world and lead to mistakes; missed opportunities; and the loss of time, money, and sometimes, life or limb. the development of new ways of visualizing information is an active and exciting area of current research. However, to properly and effectively apply these new methods, one must first develop an awareness of where and how information is currently being displayed badly. Find an example of a poor information display that is currently in use in a business organization. This can be a chart that doesn't include all the information needed to draw a correct conclusion from the data presented, one that hides the important information behind a clutter of irrelevant data, one that forces incorrect…Links for reference are shown below https://hpu.blackboard.com/bbcswebdav/pid-2170562-dt-content-rid-18923038_1/xid-18923038_1 https://hpu.blackboard.com/bbcswebdav/pid-2170562-dt-content-rid-18923038_1/xid-18923038_1
- Afer executing our data through PostgreSQL we will get: Select one: a. Output b. Information c. Metadata d. InstructionsAhmed was an Arizona University student and spent 20 hours each week working at the university library. He liked the library because it was quiet and he could study some of the time. One interesting aspect of the library was the access to incredible databases, some of which were only for the professors. As a student worker he was privy to all the database codes, and soon discovered large amounts of materials for almost every class on campus. Bill, one of Ahmed’s fellow library student workers, was constantly talking about doing weird stunts and antics to put on YouTube. He was a nice person to be around but sometimes he was a little overbearing. One evening when Ahmed started work, Bill was talking about the many ways to download pirated music, movies, and books from the library’s system. “It is very easy and untraceable. I just route my requests to a professor’s IP address, then send it to several other faculty IP addresses so it is difficult to trace. I then go to one of the…Q3. What threats should Managing Director of Amul india Sodhi consider the most pressing? What opportunities present themselves as most achievable. (Word limit up to 150 words)
- Louis Estrada is Regional Manager at Commander Electronics in Atlanta, Georgia. He received an e-mail from Joseph Grimes, a frustrated restaurant owner who is demanding a steep price match for all his trouble with two new 4K Ultra HD televisions that both malfunctioned (see Activity 6.12). He had bought a Samsung QLED Q90R 65" 4K UHD TV (QN65Q90RAFXZA) at Commander Electronics for $2,597.99 plus tax. After installing it, he found, much to his chagrin, that the TV set failed the very next day. Wanting a new TV as soon as possible, he drove 30 minutes to the same Commander Electronics store to exchange the faulty model for another Samsung QLED Q90R 65" 4K UHD TV. A few days later, this TV also conked out. Again Joseph had to return the TV set, but this time he insisted on exchanging it for a different brand, a comparable LG 65" 4K UHD HDR Smart OLED TV (OLED65C8PUA) or a larger Sony 75" 4K Ultra HD Smart LED TV (XBR75X940E) that also fit Joseph’s criteria. However, at almost $3,000 both…TRUE OR FALSE 1. Tracing helps address completeness issues while vouching address existence issues. 2. Observation is limited to the point in time at which the observation took place. 3. The cost or difficulty involved in obtaining evidence is not itself a valid basis for omitting an audit procedure. 4. Minutes of meetings of board of directors are considered corroborating information. 5. If lower detection risk is determined, the auditor may expand the extent of substantive procedures to ensure the reliability of the audit evidence.4 Reporting financial information imposes costs and obviously these costs should be justified by the __________________of reporting that information. a. Quality b. Benefits c. Availability d. Timeliness
- ***paste results onto Excel and upload it. 1. The information provided below relates to sales in a dine-in restaurant in Salisbury Maryland: Months Sales (in $1000) Mar-19 46.5 Apr-19 49.6 May-19 49.8 Jun-19 61.9 Jul-19 65.5 Aug-19 64 Sep-19 70.3 Oct-19 59.8 Nov-19 60 Dec-19 70.8 Jan-20 51.9 Feb-20 59.6 Due to Coronavirus outbreak, Restaurants were ordered to shut down during March and April of 2020. The restaurant manager is trying to determine the amount of sales lost while it was shut down during March and April because of the outbreak. a. Use exponential smoothing, with α =.2, to develop a forecast for March and April. (Hint: Use the forecast for March 2020 as the actual sales in March 2020 in developing the forecast for April 2020.) b. Comment on the use of exponential smoothing for forecasts more than one period into the future. c. Use trend projection to forecast sales for March and April 2020. d. The restaurant had purchased as insurance…1. Dated documents should be maintained in a file cabinet and can be arranged: A. Alphabetically B. Chronologically C. By subject D. All of these E. None of these 2. In business: A. Being unorganized and stressed is acceptable B. Redoing a project a second time is acceptable C. Time is money D. All of these E. None of these 3. Negative stress commonly results in: A. Fatigue and diminished or increased appetite B. Anger, depression, and/or distrust C. Both Fatigue and diminished or increased appetite and Anger, depression, and/or distrust D. None of theseBased on her review of the stores, Zoe concluded that one of the first matters she had to attend to involved developing job descriptions for her store managers. As Zoetells it, her lessons regarding job descriptions in her basic management and HR management courses were insufficient to fully convince her of the pivotal role job descriptions actually play in the smooth functioning of an enterprise. Many times during her first few weeks on the job, Zoe found herself asking one of her store managers why he was violating what she knew to be recommended company policies and procedures. Repeatedly, the answers were either “Because I didn’t know it was my job” or “Because I didn’t know that was the way we were supposed to do it.” Zoeknew that a job description along with a set of standards and procedures that specified what was to be done and how to do it, would go a long way toward alleviating this problem. In general, the store manager is responsible for directing all store activities in…