H.W 2: Construct the PERT Net work for the data shown below and determine the expected. Finish date, R Probability of finishing the works in 25 months.
Q: PM.52 HCA (Hospital Corporations of America) has obtained 5 new hospitals in a recent acquisition.…
A: Possible path Duration Maximum Critical ABDGIJK 1+5+6+14+12+2+5 = 45 No No ABEHJK 1+5+7+12+2+5…
Q: : The advanced energy technology (AET), was given the responsibility of executing the transfer of a…
A: Note: - As we can answer only up to three subparts we will answer the first three subparts here.…
Q: 1. The activities involved in the construction of a certain project are given in Table 1. One…
A: Given the following activity data:
Q: I need help with chapter 17, problem 2 (17.2) Question is A-D
A: a)Arrange the activities into two logical sequences:
Q: make the project start date 3 Jan 2022 Level the following multi-project operation. Work package…
A: Given data is
Q: 2. Tom Schriber, a director of personnel of Management Resources, Inc., is in the process of…
A: Given data is
Q: Below is information about a project to implement a new manufacturing cell to assemble personal…
A: Given Information:
Q: 2. The R & D Department is planning to bid on a large project for the development of a new…
A: “Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: 7. 6. 1. Based upon the following diagram and activity durations, write down the Critical Path. 2.…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: Q:2 Draw AOA and AON network diagrams and gantt chart for the project, calculate TE for each…
A: Below is the solution:-
Q: 2. Colonial State College is considering building a new multipurpose athletic complex on campus. The…
A: A project network (also known as a project activity network) is a graphical depiction of the…
Q: Write practical application of "Knowledge Areas in Project Management" on Metro Bus Islamabad…
A: In any company, project completion plays a key role in the success of the organization. Project…
Q: (Question 23) As a process analyst – you are requested to – Map the above project(refer to case…
A: While all organizations, irrespective of size, have processes that can be an endless supply, many of…
Q: Activity Time estimate (days) Succeeding Activity A 4 D A E F 11 C G H D,E,F 7 G
A: Network Diagram :
Q: EQUIRED: a. The PERT Network, identifying the critical path and including slack times.
A: We are only allowed to do one question at a time. Please post rest questions again to get answer.
Q: A. Instruction: 1. Construct both AOA diagram for the following data. a) b) Identify the paths and…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: 1.Forecast Completion •What is the Estimate at Completion? •New bottom up estimate is 575,000…
A: As the project progresses, the original budget may no longer be realistic because of the changed…
Q: Using a suitable example each, describe what the following project planning process activities…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Scope control for improvement project?
A: It defines project scope as the work that should be done to convey an item with the predefined…
Q: 9. At a local university, the Student Commission on Programming and Entertainment (SCOPE) is…
A: Note: - Since the exact that has to be answered is not specified, we will answer the first…
Q: Activity Immediate predecessor(S) Normal Time Normal Cost($) Crash Time (Weeks) A none 10 16000 8 B…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(1, 2,…
Q: Activity Times (days) Activity Cost ($) Immediate Activity Predecessor 100 None 150 None 125 А D 175…
A: given,
Q: From the following data of information prepare the (a) Net- work diagram; (b) The Early Start (ES)…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: TASK PRECEDENCE ΤΙME (MINUT) A Tan leather 30 B Dye leather A 15 C Shape case B 10 D Mold hinges and…
A: Given data will be as follows: Work Element Precedence Time (min) A Tan leather - 30 B Dye…
Q: Construct a network diagram using AON notation
A: GIVEN
Q: Taskl: Main Task - Solve below two problems: (Group F) Problem 1: Given the following network with…
A: Critical Path Method (CPM): For Forward Pass-Early Start (ES)= Maximum (or Highest) EF value from…
Q: You are the manager of a project to improve a billing processat your firm. Table 7.7 contains the…
A: Critical Path In project management, the longest distance between the start and the end, including…
Q: Activity A B C E F G H Preceded By ** A B,C D E BC F.G Expected Time Direct Cost Regular Crash…
A:
Q: Q.1. Draw AOA diagram and find the critical path. Q.2. What will be the project duration?
A: AOA diagram
Q: List of WBS for project of construction?
A: Work breakdown structure or WBS refers to a technique of project management for completing any…
Q: The activities described by the following table aregiven for the Howard Corporation in Kansas:…
A: Solution a) The AON PERT diagram is shown below
Q: PM.58 Tech Solutions XYZ makes accessory products for tablet computers. Below are all the activities…
A: Forward Pass:Early Start (ES)= Maximum (or Highest) EF value from immediate Predecessor(s)Early…
Q: Instruction: a. Construct AON diagram for the following data. b. Identify critical path. c. Conduct…
A: This question is related to the topic-Project Management and this topic falls under the Operations…
Q: Two
A: The formula for EF = Max (EF of all immediate predecessors)Since C is preceded by A and B we find…
Q: 2. Tom Schriber, a director of personnel of Management Resources, Inc., is in the process of…
A: A Project Evaluation and Review Technique (PERT) is a device that projects the board uses to deal…
Q: t a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: Task ID Duration Dependency A 3 B 14 C.F A 2
A: Activity Immediate Predecessors Duration A - 3 B A 4 C B 3 D C,F 5 E A 6 F E 2
Q: 5. As part of a major plant renovation project, the industrial engineering department has been asked…
A: We’ll answer the first question since the exact one wasn’t specified. Please submit a new question…
Q: At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing…
A: The critical path is A-C-E-G Duration 32
Q: Immediate Activity Description Time (days) Predecessors Excavate Lay Foundation Begin Initial…
A:
Q: 22. Given the following network, compute the early, late, and slack iime lor cáčh activity. Clearly…
A: Find the network diagram below: So the Critical path is A--D--E--F--G Duration is 20 days
Q: 2. Tom Schriber, a director of personnel of Management Resources, Inc., is in the process of…
A: Time variance is a distinction between the standard hours and genuine hours appointed to a task. The…
Q: Activity Resources Duration (days) Precedence activity A Sub-con 10 Direct labour, Material Supplier…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: Consider a project having the following seven activities: Normal Normal Crash Crash Maximum Time…
A: A network diagram is a visual representation of a project which helps to identify the project…
Q: 7. The project information for the custom order project of the Air Control Company is presented…
A: Activity and Slack TimeThe AON project network is a project network with activities being…
Step by step
Solved in 2 steps with 9 images
- You are the manager of a project to improve a billing processat your firm. Table 7.7 contains the data you will need toconduct a cost analysis of the project. Indirect costs are $1,600per week, and penalty costs are $1,200 per week after week 12.a. What is the minimum-cost schedule for this project?b. What is the difference in total project costs between the ear-liest completion time of the project using “normal” timesand the minimum-cost schedule you derived in part (a)?2. a) The activity shown in Table Q2 (a) are processes carried out in a mechatronic company. Based on the table provided, (i) Determine the Critical Path and Project Duration to complete the process. ii. Activity F cannot start immediately after activity C. The delay is expected to be 7 days. Determine by stating the possible problem, Critical Path and Project Duration to complete the process.3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: a) DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team. b) Find the critical path. c) What is the project completion time? • • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede: ACTIVITY DURATION (WEEKS) PRECEDES A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 — ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A — 2 B — 5 C — 1 D B…
- Activity Predecessor Activities Normal Crashed Duration (Days) Cost ($) Duration Cost ($) KA - 5 2000 3 5600 LB - 7 3000 4 7800 MC A 10 4000 7 6100 ND AB 11 5000 8 8000 PE B 6 2400 4 3600 RF C 8 3000 6 5100 QG C,D,E 4 4200 1 3000 SH E,G 5 5500 3 2500 What is the ES for Activity G and and LS for activity F?1.16 Given an auditing project with the following activities, please refer to the first pic find:(a) The probability of completing the critical path in 12 weeks (or less), as the client desires. (b) The probability of completing the critical path in 13 weeks (or less). c) The probability of completing the critical path in 16 weeks (or less), the client’s drop-dead date.(d) The number of weeks required to assure a 92.5 percent chance of completing the critical path, as guaranteed by the auditing firm.6. Which of the following is a graphical network model that depicts a project’s tasks and the relationships between those tasks? a. PERT chart b. WBS c. Gantt chart d. Line chart
- Imagine that you are a project manager for a construction company. You must create a WBS for the Site Preparation phase of this project. Here is a list of tasks. Task Title Predecessors Duration A Contract Approval -- 5 B Site Survey A 5 C Permit Application A 4 D Grading B,C 5 E Sewer Lines B 7 F Base Paving D 3 G City Approval C,F 6 H Final Paving E,G 8Consider a project to produce custom door moldingsfor GMC Acadia cross-over vehicles, described inTable 7.4. a. If you start the project immediately, when will it be finished?b. You are interested in completing your project as soon aspossible. You have only one option. Suppose you couldassign Employee A, currently assigned to activity G, tohelp Employee B, currently assigned to activity F. Eachweek that Employee A helps Employee B will result inactivity G increasing its time by one week and activity Freducing its time by one week. How many weeks shouldEmployee A work on activity F?G 1 A project management team is conducting the activity sequencing for a new project. The team has determined that Task A takes 3 days. Task B is dependent on Task A finishing and has a duration of 1 day. Task C takes 4 days. Task D is dependent on Task C starting and has a duration of 7 days. Task E is dependent on both Task C and Task D finishing and has a duration of 2 days. Task F is dependent on both Task E and Task B finishing and has a duration of 4 days. What is the critical path and duration of the project?
- Rich Cole Control Devices, Inc., producescustom-built relay devices for auto makers. The most recentproject undertaken by Cole requires 14 different activities.Cole’s managers would like to determine the total projectcompletion time (in days) and those activities that lie alongthe critical path. The appropriate data are shown in the fol-lowing table.a) What is the probability of being done in 53 days?b) What date results in a 99% probability of completion?a) What is the completion time of the project? b) Draw the resource loading graph. c) Try to level the resource loading as possible.PERT/CPM HOMEWORK (MOD 10) In the table below, you will see activities and times associated with each activity. Review the PowerPoint slides in Module 10 , before you start this assignment. Task Preceding Tasks to (optimistic) tm (most likely) tp (pessimistic) A NONE 2 3 10 B NONE 2 3 4 C A 1 2 3 D A 4 6 14 E B 4 5 12 F C 3 4 5 G D,E 1 1 7 1.) Draw the network using the table above. Make sure all 4 values (ES, EF, LS, LF) are listed on the network. 2.) What is the slack for each activity? What is the critical path? Show ALL of your work! 3.) Find the expected project completion time. What is the project variance? 4.) What is the probability that it would be in more than 14 days? Show ALL of your work. *The circle diagram picture is just an example of how it should look it is not apart of the problem in the chart