Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 30 percent capacity cushion is best. Time Standard Demand Forecast Processing Lot Size Setup (hr/lot) Component Pessimistic Expected Optimistic (hr/unit) (units/lot) 16,000 11,000 16,000 16,000 12,000 23,000 27,000 17,000 A 0.05 1.0 50 в 0.30 4.6 80 0.05 8.3 100 35,000 a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up to the next whole number.) Сарacity Demand Forecast Requirement (M) Pessimistic 16000 machines Expected machines Optimistic machines

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter11: Simulation Models
Section11.4: Marketing Models
Problem 30P: Seas Beginning sells clothing by mail order. An important question is when to strike a customer from...
icon
Related questions
Question
Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates
on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained
three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 30 percent capacity cushion is best.
Time Standard
Demand Forecast
Setup
(hr/lot)
Lot Size
Processing
(hr/unit)
Component
Pessimistic
Expected
Optimistic
(units/lot)
A
0.05
1.0
50
16,000
16,000
27,000
В
0.30
4.6
80
11,000
12,000
17,000
C
0.05
8.3
100
16,000
23,000
35,000
a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up to the next whole number.)
Сарacity
Requirement (M)
Demand Forecast
Pessimistic
16000 machines
Expected
machines
Optimistic
machines
Transcribed Image Text:Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 30 percent capacity cushion is best. Time Standard Demand Forecast Setup (hr/lot) Lot Size Processing (hr/unit) Component Pessimistic Expected Optimistic (units/lot) A 0.05 1.0 50 16,000 16,000 27,000 В 0.30 4.6 80 11,000 12,000 17,000 C 0.05 8.3 100 16,000 23,000 35,000 a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up to the next whole number.) Сарacity Requirement (M) Demand Forecast Pessimistic 16000 machines Expected machines Optimistic machines
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,