Madison Manufacturing is considering a new machine that costs $350,000 and would reduce pre-tax manufacturing costs by $110,000 annually. Madison would use the 3-year MACRS method to depreciate the machine, and management thinks the machine would have a value of $33,000 at the end of its 5-year operating life. The applicable depreciation rates are 33.33%, 44.45%, 14.81%, and 7.41%. Working capital would increase by $35,000 initially, but it would be recovered at the end of the project's 5-year life. Madison's marginal tax rate is 25%, and a 14% cost of capital is appropriate for the project. a. Calculate the project's NPV, IRR, MIRR, and payback. Do not round intermediate calculations. Round the monetary value to the nearest dollar and percentage values and payback to two decimal places. Negative values, if any, should be indicated by a minus sign. NPV: $ IRR: MIRR: Payback: years b. Assume management is unsure about the $110,000 cost savings - this figure could deviate by as much as plus or minus 20%. Do not round intermediate calculations. Round your answers to the nearest dollar. Negative values, if any, should be indicated by a minus sign. Calculate the NPV if cost savings value deviate by plus 20%. $ % Calculate the NPV if cost savings value deviate by minus 20%. $ c. Suppose the CFO wants you to do a scenario analysis with different values for the cost savings, the machine's salvage value, and the working capital (WC) requirement. She asks you to use the following probabilities and values in the scenario analysis: Scenario Probability Cost Savings Salvage Value WC Worst case Base case Best case 0.35 0.35 $ 88,000 110,000 132,000 $40,000 35,000 0.30 30,000 $28,000 33,000 38,000 Calculate the project's expected NPV, its standard deviation, and its coefficient of variation. Do not round intermediate calculations. Round the monetary values to the nearest dollar and a coefficient of variation to two decimal places. Negative values, if any, should be indicated by a minus sign. The project's expected NPV: $ Standard deviation: $ Coefficient of variation:
Madison Manufacturing is considering a new machine that costs $350,000 and would reduce pre-tax manufacturing costs by $110,000 annually. Madison would use the 3-year MACRS method to depreciate the machine, and management thinks the machine would have a value of $33,000 at the end of its 5-year operating life. The applicable depreciation rates are 33.33%, 44.45%, 14.81%, and 7.41%. Working capital would increase by $35,000 initially, but it would be recovered at the end of the project's 5-year life. Madison's marginal tax rate is 25%, and a 14% cost of capital is appropriate for the project. a. Calculate the project's NPV, IRR, MIRR, and payback. Do not round intermediate calculations. Round the monetary value to the nearest dollar and percentage values and payback to two decimal places. Negative values, if any, should be indicated by a minus sign. NPV: $ IRR: MIRR: Payback: years b. Assume management is unsure about the $110,000 cost savings - this figure could deviate by as much as plus or minus 20%. Do not round intermediate calculations. Round your answers to the nearest dollar. Negative values, if any, should be indicated by a minus sign. Calculate the NPV if cost savings value deviate by plus 20%. $ % Calculate the NPV if cost savings value deviate by minus 20%. $ c. Suppose the CFO wants you to do a scenario analysis with different values for the cost savings, the machine's salvage value, and the working capital (WC) requirement. She asks you to use the following probabilities and values in the scenario analysis: Scenario Probability Cost Savings Salvage Value WC Worst case Base case Best case 0.35 0.35 $ 88,000 110,000 132,000 $40,000 35,000 0.30 30,000 $28,000 33,000 38,000 Calculate the project's expected NPV, its standard deviation, and its coefficient of variation. Do not round intermediate calculations. Round the monetary values to the nearest dollar and a coefficient of variation to two decimal places. Negative values, if any, should be indicated by a minus sign. The project's expected NPV: $ Standard deviation: $ Coefficient of variation:
Financial Management: Theory & Practice
16th Edition
ISBN:9781337909730
Author:Brigham
Publisher:Brigham
Chapter11: Cash Flow Estimation And Risk Analysis
Section: Chapter Questions
Problem 1P: Talbot Industries is considering launching a new product. The new manufacturing equipment will cost...
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
Recommended textbooks for you
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Fundamentals Of Financial Management, Concise Edi…
Finance
ISBN:
9781337902571
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Fundamentals Of Financial Management, Concise Edi…
Finance
ISBN:
9781337902571
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning