n marble block quarrying operation, hand rock drills, costing P70,000 each, is used. It has a drilling rate of 15 cm/nmin, produces 30 cubic meters of block per month and consumes 80 liters of diesel fuel for compressor drive, per rock drill per cubic meter produced utilizing 1 worker per drill. A modern equipment quarry bar mounted rock drill is being offered for P180,000 per unit and has a drilling rate of 65 cm/min that will produce 75 cubic meters of block per month, ut consumes135 litersof diesel fuel for the compressor drive per cubic meters of block produced, utilizing 2 workers per quarry bar drill. Considerdiesel fuel at P6.55per liter at quarries, worker earning P375 per day, 22 days per month, 12 years life of both drills with 13% salvage value, 3% annual tax rate, P300 per cubic meter monthly for other expenses and sold at P1,500per cubi meter. Would you recommend the purchase of the new equipment? What is the pay-out period of the better drill?

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question

In marble block quarrying operation, hand rock drills, costing P70,000 each, is used. It has a drilling rate of 15 cm/nmin, produces 30 cubic meters of block per month and consumes 80 liters of diesel fuel for compressor drive, per rock drill per cubic meter produced utilizing 1 worker per drill. A modern equipment quarry bar mounted rock drill is being offered for P180,000 per unit and has a drilling rate of 65 cm/min that will produce 75 cubic meters of block per month, ut consumes135 litersof diesel fuel for the compressor drive per cubic meters of block produced, utilizing 2 workers per quarry bar drill. Considerdiesel fuel at P6.55per liter at quarries, worker earning P375 per day, 22 days per month, 12 years life of both drills with 13% salvage value, 3% annual tax rate, P300 per cubic meter monthly for other expenses and sold at P1,500per cubi meter. Would you recommend the purchase of the new equipment? What is the pay-out period of the better drill?


PP for HAND DRILL: ___years ( 2 decimalplaces)
PP for MOUNTED DRILL: ____years (2 decimal places)
Hand drill or mounted drill:

Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Environmental Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education