On January 1, 2021, Ka Leody Inc. entered into a long-term construction contract with fixed contract price of P 5,000,000. Ka Leody billed its client as follows: 30% during 2021, 40% during 2022 and the remainder at the end of project completion. The following data were provided by the cost accountant of the Ka Leody Inc: 2020 2021 2022 Cumulative cost incurred as of the end of the year P 2,200,000 P 3,600,000 P 4,800,000 Estimated remaining cost to complete at the end of the year P 3,300,000 P 900,000 0 What is the revenue to be recognized on December 31, 2021 under percentage of completion method ?

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 19RE
icon
Related questions
Question
On January 1, 2021, Ka Leody Inc. entered into a long-term construction contract with fixed contract price of P 5,000,000. Ka Leody billed its client as follows:
30% during 2021, 40% during 2022 and the remainder at the end of project completion. The following data were provided by the cost accountant of the Ka
Leody Inc:
2020
2021
2022
Cumulative cost incurred as of the end of the year
P 2,200,000 P 3,600,000 P 4,800,000
Estimated remaining cost to complete at the end of the
year
P 3,300,000 P 900,000
What is the revenue to be recognized on December 31, 2021 under percentage of completion method ?
Transcribed Image Text:On January 1, 2021, Ka Leody Inc. entered into a long-term construction contract with fixed contract price of P 5,000,000. Ka Leody billed its client as follows: 30% during 2021, 40% during 2022 and the remainder at the end of project completion. The following data were provided by the cost accountant of the Ka Leody Inc: 2020 2021 2022 Cumulative cost incurred as of the end of the year P 2,200,000 P 3,600,000 P 4,800,000 Estimated remaining cost to complete at the end of the year P 3,300,000 P 900,000 What is the revenue to be recognized on December 31, 2021 under percentage of completion method ?
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
Individual Income Taxes
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Financial Accounting Intro Concepts Meth/Uses
Financial Accounting Intro Concepts Meth/Uses
Finance
ISBN:
9781285595047
Author:
Weil
Publisher:
Cengage