Problem 13-3 (Algo) The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item End L C uxanoz Lead Time 3 3 Amount on Hand 0 Additional units 9 13 18 33 26 6 Direct Components L(2), C(1), x(3) B(2), J(3) G(2), B(2) H(4), B(2) Click here for the Excel Data File a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.)

Accounting Information Systems
11th Edition
ISBN:9781337552127
Author:Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Publisher:Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Chapter15: Integrated Production Processes (ipps)
Section: Chapter Questions
Problem 4P
icon
Related questions
Question

Jj.28.

 

Problem 13-3 (Algo)
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.
Item
End
L
C
K
B
3
G
H
Lead Time
3
3
4
4
2
Amount
on Hand
0
9
13
18
33
Additional units
26
6
0
The latest wook
Direct Components
L(2), C(1), X(3)
Click here for the Excel Data File
a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an
MRP plan.)
B(2), J(3)
G(2), B(2)
H(4), B(2)
b. An order for the end item is scheduled to be shipped at the start of week 16. What is the latest week that the order can be started
and still be ready to ship on time? (Hint You don't need to develop an MRP plan.)
Transcribed Image Text:Problem 13-3 (Algo) The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item End L C K B 3 G H Lead Time 3 3 4 4 2 Amount on Hand 0 9 13 18 33 Additional units 26 6 0 The latest wook Direct Components L(2), C(1), X(3) Click here for the Excel Data File a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) B(2), J(3) G(2), B(2) H(4), B(2) b. An order for the end item is scheduled to be shipped at the start of week 16. What is the latest week that the order can be started and still be ready to ship on time? (Hint You don't need to develop an MRP plan.)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Knowledge Booster
Quality control
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Accounting Information Systems
Accounting Information Systems
Finance
ISBN:
9781337552127
Author:
Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Publisher:
Cengage Learning
Pkg Acc Infor Systems MS VISIO CD
Pkg Acc Infor Systems MS VISIO CD
Finance
ISBN:
9781133935940
Author:
Ulric J. Gelinas
Publisher:
CENGAGE L
Survey of Accounting (Accounting I)
Survey of Accounting (Accounting I)
Accounting
ISBN:
9781305961883
Author:
Carl Warren
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning