Suppose that a task in a project has the following time​ estimates:   to=optimistic completion time=10 weeks tm=most likely completion time=17 weeks tp=pessimistic completion time=19 weeks   Compute the expected task variance.   The task expected task variance is _____ weeks. ​(Enter your response rounded to two decimal​ places.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
Suppose that a task in a project has the following time​ estimates:
 
to=optimistic completion time=10 weeks
tm=most likely completion time=17 weeks
tp=pessimistic completion time=19 weeks
 
Compute the expected task variance.
 
The task expected task variance is _____ weeks. ​(Enter your response rounded to two decimal​ places.)
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,