Telestar International On November 15, 1998, the Department of Energy Resources awarded Telestar a $475,000 contract for the developing and testing of two waste treatment plants. Telestar had spent the better part of the last two years developing waste treatment technology under its own R&D activities. This new contract would give Telestar the opportunity to “break into a new field”, that of waste treatment. The contract was negotiated at a firm-fixed price. Any cost overruns would have to be incurred by Telstar. The original bid was priced out at $847,000. Telestar’s management, however, wanted to win this one. The decision was made that Telstar would “buy in” at $475,000 so that they could at least get their foot into the new marketplace. The original estimate of $847,000 was very “rough” because Telestar did not have any good man-hour standards, in the area of waste treatment, on which to base their manhour projections. Corporate management was willing to spend up to $400,000 of their funds in order to compensate the bid of $475,000. By February 15, 1999, costs were increasing to such a point where overrun would be occurring well ahead of schedule. Anticipated cots to completion were now $943,000. The project manager decided to stop all activities in certain functional departments, one of which was structural analysis. The manager of the structural analysis department strongly opposed the closing out of the work order prior to the testing of the first plant’s high-pressure pneumatic and electrical systems. Structures manager: “You are running a risk if you close out this work order. How will you know if the hardware can withstand the stresses that will be imposed during the test? After all, the test is scheduled for next month and I can probably finish the analysis by then.” Project manager: “I understand your concern, but I cannot risk a cost overrun. My boss expects me to do the work within cost. The plant design is similar to one that we have tested before, without any structural problems being detected. On this basis I consider your analysis unnecessary.” Structures manager: “Just because two plants are similar does not mean that they will be identical in performance. There can be major structural deficiencies.” Project manager: “I guess the risk is mine.” Structures manager: “Yes, but I get concerned when a failure can reflect on the integrity of my department. You know, we are performing on schedule and within the time and money budgeted. You are setting a bad example by cutting off our budget without any real justification.” Project manager: “I understand your concern, but we must pull out all the stops when overrun costs are inevitable.” Structures manager: “There is no question in my mind that this analysis should be completed. However, I am not going to complete it on my overhead budget. I will reassign my people tomorrow. Incidentally, you had better be careful; my people are not very happy to work for a project that can be canceled immediately. I may have trouble getting volunteers next time.” Project manager: “Well, I am sure you will be able to adequately handle any future work. I will report to my boss that I have issued a work stoppage order to your department.” During the next month’s test, the plant exploded. Post analysis indicated that the failure was due to a structural deficiency. QUESTIONS 1. Who was at fault? 2. Should the structures manager have been dedicated enough to continue the work on his own? 3. Can a functional manager, who considers his organization as strictly support, still be dedicated to project success?

Understanding Business
12th Edition
ISBN:9781259929434
Author:William Nickels
Publisher:William Nickels
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
icon
Related questions
Question

Telestar International On November 15, 1998, the Department of Energy Resources awarded Telestar a $475,000 contract for the developing and testing of two waste treatment plants. Telestar had spent the better part of the last two years developing waste treatment technology under its own R&D activities. This new contract would give Telestar the opportunity to “break into a new field”, that of waste treatment. The contract was negotiated at a firm-fixed price. Any cost overruns would have to be incurred by Telstar. The original bid was priced out at $847,000. Telestar’s management, however, wanted to win this one. The decision was made that Telstar would “buy in” at $475,000 so that they could at least get their foot into the new marketplace. The original estimate of $847,000 was very “rough” because Telestar did not have any good man-hour standards, in the area of waste treatment, on which to base their manhour projections. Corporate management was willing to spend up to $400,000 of their funds in order to compensate the bid of $475,000. By February 15, 1999, costs were increasing to such a point where overrun would be occurring well ahead of schedule. Anticipated cots to completion were now $943,000. The project manager decided to stop all activities in certain functional departments, one of which was structural analysis. The manager of the structural analysis department strongly opposed the closing out of the work order prior to the testing of the first plant’s high-pressure pneumatic and electrical systems. Structures manager: “You are running a risk if you close out this work order. How will you know if the hardware can withstand the stresses that will be imposed during the test? After all, the test is scheduled for next month and I can probably finish the analysis by then.” Project manager: “I understand your concern, but I cannot risk a cost overrun. My boss expects me to do the work within cost. The plant design is similar to one that we have tested before, without any structural problems being detected. On this basis I consider your analysis unnecessary.” Structures manager: “Just because two plants are similar does not mean that they will be identical in performance. There can be major structural deficiencies.” Project manager: “I guess the risk is mine.” Structures manager: “Yes, but I get concerned when a failure can reflect on the integrity of my department. You know, we are performing on schedule and within the

time and money budgeted. You are setting a bad example by cutting off our budget without any real justification.” Project manager: “I understand your concern, but we must pull out all the stops when overrun costs are inevitable.” Structures manager: “There is no question in my mind that this analysis should be completed. However, I am not going to complete it on my overhead budget. I will reassign my people tomorrow. Incidentally, you had better be careful; my people are not very happy to work for a project that can be canceled immediately. I may have trouble getting volunteers next time.” Project manager: “Well, I am sure you will be able to adequately handle any future work. I will report to my boss that I have issued a work stoppage order to your department.” During the next month’s test, the plant exploded. Post analysis indicated that the failure was due to a structural deficiency.

QUESTIONS 1. Who was at fault? 2. Should the structures manager have been dedicated enough to continue the work on his own? 3. Can a functional manager, who considers his organization as strictly support, still be dedicated to project success? 4. What type of communication techniques could the project manager have used to improve the situation? 5. Based on the brief case study, do you think this project manager was a good leader? Why or why not?

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Introduction to Forecasting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Understanding Business
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Management Information Systems: Managing The Digi…
Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON
Business Essentials (12th Edition) (What's New in…
Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON
Fundamentals of Management (10th Edition)
Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON