The expected times and variances for the project activities are given below. What is the probability of completing the project in 24 periods? Variance ID Description Predecessor [(b - al/6? Pilot production Select channels of distrib. Develop mktg. program Test market 1 None 3 2 None 4 3 None 4 1 2 5 Patent 10 5 Full production Ad promotion Release 4 10 7 3 8 2,5,6,7 2 1 6744 O63
Q: A four-period moving average
A:
Q: Draw a network diagram of the project that shows which activities follow which other ones, and…
A:
Q: 2. PERT/CPM Activity Description Immediate Time Estimate Predecessors Weeks) A Develop product…
A:
Q: C2 (i)Assume that annual energy requirement of an industry is 20900 kWh ,we calculate that what will…
A: Given Annual energy requirement= 20900kWh Coefficient of performance = 0.4 Loss factor value =…
Q: Activity Immediate Predecessor(s) Te VAR Slack A - 5 0.444 0 B - 2 0.111 4 C - 3 0.444 6.5 D A…
A: Ackuily Pre deScor Achuty Predecessor Te Q _ S Q — 2 C - 3 c B 6S £…
Q: Use the information below to answer the questions that follow. Annual household fuelwood use in…
A: A measure of the energy contained in a fuel or food, derived from the heat released by a specified…
Q: Required information An asset owned by Photon Environmental was book depreciated by the Straight…
A: Depreciation per year is D=BV2-BV3 Here BV2 is the book value at year 2 and BV3 is the book value at…
Q: A project has the following activities; the activities and precedence relationships are given in…
A: Critical path of a network flow diagram is defined as the path obtained by connecting the all the…
Q: The total design and construction cost for a digester to handle a flow rate of0.5 million gallons…
A: To calculate the cost of digestor for a flow rate of 2.0 MG We have the following equation…
Q: Q 88. Variability between a small sample size is easy to spot in: (select the best option) Ops: A. O…
A: first we will see which charts are used for what and when. P-chart : It is generally used to…
Q: . The operations manager of a large production plant would like to estimate the mean amount of time…
A: According to terms and conditions of bartleby we can only provide 1st part 1st solution. Thank you !
Q: How would Simulated Annealing perform if the temperature, T, is always equal or very close to 0,…
A: Simulated annealing is a technique for resolving optimization problems that are both unconstrained…
Q: Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic…
A: Activity expected Time Variance J 10.5 1.361 K 8 L 6.5 M 3 0 N 5 1.77 O 7 P 7.5…
Q: Choose the correct value of contribution per unit for given data: Selling price-120 OMR & Variable C
A: Given data Selling price=120 OMR Variable Cost=35 OMR
Q: Question: Cost coefficients of fifteen generator units and their power limits are given in tables 1…
A:
Q: Considering the transportation costs of natural gas over land by pipeline, natural gas…
A: The oil is moved through the pipelines by pump stations along the pipeline. Natural gas (and…
Q: Q7. Which information is not related to local conditions. In house expertise C. Supplier Material…
A: Hi and thanks for the questions. Since you have asked multiple questions, we will solve the first…
Q: _____system uses measurements of disturbance variables to position the manipulated variable in such…
A: feedforward control is use to measure of disturbance variable
Q: Table 4 shows the job processing data which involves the jobs identification, processing time and…
A: GIVEN DATA FIVE JOB WITH PROCESSING TIME AND DUE DATE GIVEN WE HAVE TO ANLYSE IT
Q: Given three production runs of test data with five samples each, determine the control limits for…
A:
Q: The estimated times and immediate predecessors for the activities in a project at Howard Umrah's…
A:
Q: 20. An abstract says: "This paper develops a system dynamics model of Iceland's energy sector…
A: option c statistical design
Q: Tony’s Barbershop is run, owned, and operated by Anthony Jones, who has been cutting hairfor more…
A: a)The average time between arrivals was one every 50 minutes, which gives an arrival rate of Each…
Q: Deadline: Submit by May 24th, 2021 Description/ Content: Using the table below, find the following:…
A: Network diagram-
Q: 10. Selection community is one of steps for location selection that depends on: - (a) Political…
A:
Q: Blocking in experimental design is useful because it: A) keeps the experimenter from knowing which…
A: Given Data⇒Blocking in experimental designProblem definition⇒Problem says Blocking in experimental…
Q: 1.) A piece of production equipment is to be replaced immediately because it no longer meets quality…
A: Given Datafor equipment Acapital Investment =$20,000Annual cash flow=$12,000Useful life=8yearsMarket…
Q: () Draw the project network. (i) Find the expected duration and variance for each activity. (ii)…
A:
Q: A firm provides solution regarding forecast over a 6 month cycle. The following data is regarding…
A: Data given -
Q: Exp.(3): Find the variance and the standard deviation for the data in this frequency during…
A:
Q: O LeBron or MJ? X April 8, 2020 – B Lecture 13 – Flc x P CIVENG 2004 ( X CIVENG 2004 f (2) Facebook…
A: Hello. Since you have posted multiple questions and not specified which question needs to be solved,…
Q: 1. A registered Profession Engincer (P.Eng. or Ing.) specializing in Industrial Engineering may…
A: The most probable answers are given under:
Q: A company is planning to launch a new product. It currently has four possible new products under…
A:
Q: How can maching learning be incoraptred into Tesla? 2. Could Tesla benfit from automatic trading?…
A: Tesla's current AI solutions are based on unsupervised machine learning. Tesla is working on…
Q: Process control can be defined as the act of controlling a final control eement to change the…
A: Process control is an important part in maintaining the output of a system within a desired range by…
Q: The following data were measured over a three-month period (conditions of uncertainty of Procurement…
A:
Q: etween the EOQ model and the planned shortage or backorder model? If the manager adds constraints…
A: EOQ mode is Q = (2DCo/Ch)1/2 Backorder model is Q = (2DCo/Ch)1/2 *((Ch + Cb)/
Q: C2(1)Assume that annual energy requirement of an industry is 20900 kWh ,we calculate that what will…
A: Given Annual energy requirement= 20900kWh Coefficient of performance = 0.4 Loss factor value =…
Q: 4. Using below data for an army practice: A. Construct a project network B. Determine the length or…
A: Given, The army plan for attack. Objective - To construct a network diagram.
Q: QUESTION 5 LA local firm is planning its workforce and production levels over the next year. The…
A: Solution: Prepare the table as shown below: Month Number of Working days Demand Forecasting Units…
Q: i need the answer quickly
A:
Q: Match the following v Identify correctly Spatial arrangement and connection of different components…
A: Solution:
Q: In a PERT network expected time to finish an activity is 22 days. Variance of the activity is 9…
A:
Q: 7. 8. 9. In Juran's view, workers cause less than 20% of quality problems. Who causes the other 80%?…
A: Dear Students
Q: The network diagram for a project is shown in the accompanying figure, with three timeestimates for…
A: (a) Understand that in the question the optimistic time, most likely time and pessimistic time for…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- Consider the network described in the table below.Activity ImmediatePredecessor(s)Pessimistic Probable OptimisticJ -- 15 10 8K -- 9 8 7L J 10 6 5M J 3 3 3N K,M 9 5 1O K,M 10 7 4P L,N 10 8 3a. Calculate the expected duration of each activity.b. Calculate the expected duration and variance of the critical path.c. Calculate the probability that the project will be completed in fewer than 30 time units.Determine the blade length for a wind turbine that supplies an electrical power output of 1.95 MW and given the following parameters: Wind speed = 51 km/hr The gear, generator and electric efficiencies are 93%, 95% and 91% respectively. The power coefficient of the wind turbine is the maximum possible as given by the Lanchester-Betz limit. Assume the atmospheric air conditions are 1.01325 bar and 27 °CAssume that annual energy requirement of an industry is 20000 kWh . DETERMINE size of wind turbine that is required to be installed to meet the energy requirement . Following assumptions are taken into account for estimation Annual energy requirement - 20000 kWh Propeller type wind machine is used . Coefficient of performance -0.40 Wind speed at 15 meter height is 5 meter / sec ( if the turbine hub is placed at the height other than 15 meter , the wind speed should be estimated as shown in " vertical wind speed variation section Density of air - 1 kg / m Capacity factor -0.30
- 2.5-L bench scale bioreactor is used for the production of recombinant P64K protein from Neisseria meningitides. The dimensions for the bioreactor are Dt 12.9 cm, ratio Di/Dt = 1/3 and N = 700 rpm. With the scale up factor of 2.24, determine the impeller tip speed (m/s) for the pilot scale bioreactor based on constant impeller tip speed and constant power consumption per volume. Predict which scale up method might give a higher concentration of P64K, if the demand of dissolved oxygen plays an important role.CH, CQ and n are functions of CP. Draw the dimensionless performance curves of the turbine on a single graph by makingthe necessary scalings. (Fit the curve by using the excel program for drawing. Also give the values you used for plotting inthe table) ÖN=5A wind turbine has the maximum power output at the rated speed of 12 m/s and a rotor diameter of 82 meters. The cut-in and cut-out speeds for this type of wind turbine are 4 m/s and 23 m/s, respectively. The table below shows the annual wind data near a potential site for setting up a wind farm using this type of wind turbine and the power coefficient of the wind turbine at the specific wind speed. The air density is 1.22 kg/m3. (a). What is the maximum power output of this wind turbine, assuming Betz limit? (b). What is the average power output if the wind turbine is installed at this site?. (c). What is the capacity factor of the wind turbine at this site? (d). If a wind farm consisting of 100 such wind turbines is built at the site, how much energy does this wind farm generate in a year (in the unit of kWh)? (e). Is this a good site for using this particular type of wind turbine?
- Activity Immediate Predecessor(s) Te VAR Slack A - 5 0.444 0 B - 2 0.111 4 C - 3 0.444 6.5 D A 7.5 0.25 0 E B 6.5 0.694 4 F C 8 0.111 6.5 G D, E 5 0.111 0 What is the critical path for the project described by this table? A. C-F B. B-E-G C. A-D-G D. A-B-C Click to select your answer.11 Sunco Oil has refineries in Los Angeles and Chicago.The Los Angeles refinery can refine up to 2 million barrelsof oil per year, and the Chicago refinery up to 3 million.Once refined, oil is shipped to two distribution points:Houston and New York City. Sunco estimates that eachdistribution point can sell up to 5 million barrels per year.Because of differences in shipping and refining costs, theprofit earned (in dollars) per million barrels of oil shippeddepends on where the oil was refined and on the point ofdistribution (see Table 51). Sunco is considering expandingthe capacity of each refinery. Each million barrels of annualrefining capacity that is added will cost $120,000 for the LosAngeles refinery and $150,000 for the Chicago refinery. Uselinear programming to determine how Sunco can maximizeits profits less expansion costs over a ten-year period.The application rate of a certain chemical is recommended at 4 kg/ha. The calibration test of a 16-liter knapsack sprayer is as follows: Nozzle discharge = 1.2 liters/min, swath = 1.5 m and walking speed = 20 m/minDetermine the amount of chemical to mix with water per loading:a. 102 gms/load b. 160 gms/loadc. 200 gms/load d. 240 gms/load
- 5.15. A small-parts assembly line involves the use of solvents requiring a high level of ventilation. To achieve removal of these toxic gases, a mean velocity of 8 ft/s must be maintained across the cross-section of a 12 ft high by 30 ft wide room. The toxicants are subsequently removed in a wet scrubber or filter, which causes a pressure drop of 30 lb/ft². Using a Cordier analysis, select the design parameters for a fan that will provide the required flow and pressure rise, while oper ating at or near 90% total efficiency, and that minimizes the diameter of the fan. Give dimensions and speed of the fan and describe the type of fan chosen.Show step by step solution. Use Mpa unit Sn = 7PROPAGATION OF ERROR You are tasked to supervise the design of 0.5MW wind turbine to be constructed in a Wind Farm in Pililla, Rizal. Suppose the design criteria are as follows: The air density as surveyed after 2 year period averaged at 1.225 kg / cubic meter. The sweeping diameter of the rotor blades is 125m, and the anemometer reading in the area amounts to 4.2m/s on a 2 year period of survey. What is the theoretical power output of the turbine assuming 100% efficiency of operation? Your answer must be in kW and in two decimal places with correct signs. In the previous problem, if the diameter measurement is off by 0.1m and the anemometer reading is also fluctuating by 0.05m/s and if the error measurement for theoretical power output must be limited to 3%, WHY OR WHY NOT should you accept the design? * Show complete solution in paper.