very time table suggests two things; Plurality of activity and an expanse of time. Putting these two things together, Prepare a weekly LECTURE time table from Monday to Friday for a level 100 Bachelor of Information Technology students of GCTU.
Q: Activity Duration Number of men 1-2 3 5 2-4 2 3 2-3 3 7 3-4 0 0 3-5 3 2 4-5 7 2…
A:
Q: ing? What is the importance of linear programming? What is simplex method? What is the purpose of…
A: linear programming
Q: Find one of the critical paths CP from the choices below. A-1-3-6-8-9 B-1-2-4-6-9 C-1-2-4-6-7-9…
A: The network diagram is the graphic representation of the project. The project involves the…
Q: The following table shows activities with duration, dependency, dependency type, and the number of…
A: Network diagram:
Q: Define each of these terms, and indicate how each is determined.a. Expected activity time
A: Expected Activity time is calculated for anticipating the approximate time in which any activity…
Q: e) Draw manually the appropriate network diagram (using PDM) and then find (and also provide as a…
A: Below is the solution:-
Q: The idea of the maze as a layout is to a. confuse. b. disorient. c. distract. d.…
A: A maze is a path or assortment of ways, generally from an entrance to a goal. The word is employed…
Q: The activities described by the following table are given for the Howard Corporation in Kansas Time…
A: This question is related to the topic Project Management and This topic falls under Operations…
Q: Explain resource loading and resource leveling. Why would you level resources in a project?
A: Project management is nothing but the utilization of particular skills, methods, or techniques, and…
Q: For the following network, figure out the total floats and the critical path assuming interruptible…
A: Find the Given details below: Given details: Activity Duration A 4 B 3 C 8 D 7 E 6…
Q: Should she talk with the other team members from marketing individually about Drew? Why or why not?
A: The team leader is an individual who is responsible to motivate and guide the team members to…
Q: What is slack, and how is it computed?
A: The slack (also known as float) is referred to as the time by which a task can be delayed without…
Q: Given the following activity network: Ki A1 Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3…
A: Given data The activity A1 takes 5 weeks The activity A2 takes 8 weeks The activity A3 takes 2…
Q: Dr. Ell has been given a budget of $10,000 to organize a conference at her university in 3 months'…
A: This question is related to the project management subject and It falls under the…
Q: Which method for determining activity time estimates,deterministic or probabilistic, do you perceive…
A: Two organization arranging procedures are PERT and CPM. PERTutilizations probabilistic time gauges.…
Q: For output to equal projected demand, what is the minimum number of workstations needed?
A: Given, Projected demand=2160 license plates each day. Each day time consumption=6 hours.
Q: Should Laura talk with Drew’s manager about the situation now? Why or why not? If not, should she…
A: Not- As per the guidlelines of bartleby, only first three parts have been answered. For getting…
Q: Write Current situation and Problem/Opportunity statement, analysis of options and recommendations…
A: For a new student lounge or setting area, I believe that there is a vast opportunity as the students…
Q: One
A: Determine the early start of Activity C:It is given that the early start of A is 6 and B is 5.…
Q: Develop the network for planning and construction of the new hospital at Arnold Palmer.
A: A project schedule network diagram shows the sequential and analytical connection between tasks in a…
Q: Based on project information on kitchen space renovation as prepared below, in the time estimates .…
A: Given- Activity Predecessor Optimistic (O) Most likely (4M) Pessimistic (P) A - 9 10 11 B - 8…
Q: Classify each of the following as nominal, ordinal, interval, or ratio data and explain. a. the…
A:
Q: E G 5) 2. 4 days 9 days A-5/ days C-2 days F8 days H-7 days B-3 days D 3 4. 6. 5 days 6 days
A: What is Early Start & Late Finish? In any activity network diagram, there will be multiple…
Q: Given the following data below, draw the AON diagram and fill out the table below: Answer the…
A: 1.
Q: Q1/ Answer the following:- (1) The project management triangle are represent (2) The phase of tender…
A: Administrators utilize the management's triangle's task to dissect or comprehend the challenges that…
Q: The table below contains information about an environmental clean-up project in the township of…
A: Identify the activity that has no predecessors. These activities will be the initial activities. The…
Q: The table gives the total cost schedule for oil changes at the local Jiffy Lube. What is Jiffy…
A: Given-
Q: Given the following information, compute the required items: Florida Power & Light is attempting…
A: Activity on Node (AON) diagram for the project is shown below showing the precedence relationships.
Q: Hiw Y Design the network represents the following activities and then finds the critical Path?…
A: Given data is
Q: If we used AW analysis instead of PW analysis to select a project, it will give us a different…
A: Annual worth analyses are quite identical to present worth analysis, except that all expenditures…
Q: What are three choices that may be used in a project depending on the layout of a decision tree?…
A: INTRODUCTION: Decision-making is a critical skill for managers in organizations. The ability to make…
Q: You have been appointed to co-ordinate a project to re-locate your organization’s operations (this…
A: Work Breakdown structure used to develop the scope of the project that manages the task. The…
Q: A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800.…
A: The concept used here is earned value management.
Q: b) - Draw the Activity-on-Node (AON) diagram using the following representation for every node:…
A: Activity-on-node is a project management term that directs to a precedence diagramming technique…
Q: QI: Given the information below, draw the network (AOA) and find the probability of finishing the…
A: Let the task names for each activity from A, B,....n. Given data is
Q: A student has been put in charge of a new garden design. The new design will involve five different…
A: The calculations of ES, EF, LS, LF and slack is given by:EF = ES + activity timeFor the last…
Q: For each of the following network diagrams, determine both the critical path and the expected proj-…
A: The network diagrams for critical path can be constructed in two ways: Arrow to Node - AON Arrow to…
Q: Laura Brooks has been asked to be the team leader for a cross-functional project that is designed to…
A: As per the facts of the case, Laura is concerned about Drew's inactive participation in the team…
Q: Explain with aid of practical examples the following: 1. Scope creep 2. WBS 3. Scope statement
A: Project scope can be defined as that part of the project planning that involves the determination…
Q: What would you advise Laura to do at this stage? Should Laura wait until she sees how Drew performs…
A: Note as per the guidelines of Bartleby, only the first three parts of the question have been…
Q: Define each of these terms, and indicate how each is determined.a. Expected activity time.
A: For calculating the expected activity time, the parameters required are the following: Optimistic…
Q: Refer to the table given to answer the following question: 1. Which PERT diagram best represents the…
A: Given data is
Q: Should Laura wait until she sees how Drew performs working independently before she does anything?
A: From the above case study the question has been answered as follows:
Q: A student club plans on holding a campus-wide event at the end of the semester. The activities that…
A: Given that: Duration Immediate Activity (weeks) Predecessor A 2 -- B 3 A C 1 A D 3…
Q: What would you advise Laura to do at this stage?
A: Communication is the process in which information interchanges between two or more than two people.…
Q: For the activity times and network model below, What is the expected completion time? ________ What…
A: Here is the network diagram with activity & time duration :
Q: On June 12, 2013, the Delta Corporation was awarded a $160,000 contract for testing a product. The…
A: The three imperatives project chiefs work inside are budget, scope, and schedule. Schedule (or time)…
Every time table suggests two things; Plurality of activity and an expanse of time. Putting these two things together, Prepare a weekly LECTURE time table from Monday to Friday for a level 100 Bachelor of Information Technology students of GCTU.
Step by step
Solved in 2 steps with 1 images
- Operations Management PLEASE SHOW AND EXPLAIN ALL STEPS & CALCULATIONS- THANK YOU! ABC Construction has developed the following set of activities for its budgeting process. Activity Predecessor Normal Activity Time (Days) Resulting Activity Time if Activity is Crashed (Days) Total Cost to complete activity in Normal Time Total Cost to complete activity in Crash Time A -- 4 2 $200 $600 B A 6 3 $300 $1200 C A 4 1 $300 $900 D B, C 3 2 $500 $550 E D 4 1 $500 $1700 a) Using the Normal Times, what is the critical path and project completion time for the budgeting process? Also, what is the cost to complete the project based on the Normal Times? b) If we want to reduce the project completion time to the minimum possible time by crashing all activities as needed, what is the new project completion time and what is the new total project cost? c) Modify the problem as follows. There is now an indirect cost of $75 per day, which is in addition to the cost identified above.…It has just been completed by a university (or collegesenior )'s management team to implement university-wide computing systems that will support all core business processes, such as a student management information system, payroll and finance systems, and resource management (including a class scheduling system), over a five-year period. This increase in the usage of computer systems has coincided with an increase in the collection of transactional data regarding university business operations, and top management is aware of the potential value of the information contained within this data. As a matter of fact, the university's senior management has set a long-term objective of providing key decision-makers across the institution with business intelligence (BI) tools that would enable them to monitor key performance indicators (KPI) on their desktops. Senior management, on the other hand, recognizes that numerous milestones must be achieved before this objective can be achieved. It is…Since Jack believes that Work Center 3 is his bottleneck, hehas asked you to do the following:(a) Calculate the percentage of planned output needed tocomplete the planned inputs (planned input 1 backlog/planned output) at Work Center 3.(b) Calculate the percentage of planned input that actuallyhappened (actual input 1 backlog/planned input 1backlog).(c) Calculate the percentage of available output that wasactually accomplished (actual output/planned output) atWork Center 3.(d) Given your results, do you believe that Jack is correct inassuming that Work Center 3 is his bottleneck? Justifyyour answer.
- Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks: Task Performance Time (mins) Task Must Follow Task Listed Below A 4 − B 6 − C 6 A, B D 5 C E 7 D F 6 E G 7 E H 7 F, G This exercise only contains parts b, c, d, e, f, and g. The cycle time for the production of a chair = 9.69. minutes (round your response to two decimal places). The theoretical minimum number of workstations=5 (round your response up to the next whole number). d) The assignment of tasks to workstations should be: (Hint:…Is there a connection between the planning and scheduling of activities and the supply chain's capacity to remain viable? Is it possible for the organization to make use of both?Claire’s Catering is providing food for a major social event next Saturday. Because Claire’s does not have enough employees to fully staff the event, the manager should implement talent management to recruit enough workers for the event. True or False
- The XYZ company produces all type of office furniture. The “Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long office hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks; Task Time (min) Immediate predecessor A 4 - B 7 - C 6 A, B D 5 C E 6 D F 7 E G 8 E I 6 F, G a) Draw a precedence diagram of this operation b) What is the cycle time for this operation? c) What is the theoretical minimum number of workstations? d) Assign tasks to the workstations e) What is the idle time per cycle? f) What is the efficiency of the assembly line?You were just hired as the head strength coach at a NAIA school. You are the first strength coach the University has ever hired. Knowing that you have 500 student athletes across 22 different teams, how do you manage programming, load, and needs based workouts across all sports? Write a needs outline for 3 different sports: one in season, one off season, and one pre season.Mo. The I Love Operations Management (ILOM) Conference, a major international conference, is staffed by student volunteers. One of the tasks of the student volunteers is to register conference attendees. The registration process involves confirming that fees have been paid, retrieving a conference package specific to that person (filed under their last name), and passing on relevant information about the conference. In 2023, conference registration will be handled by a group of 10 student volunteers who work in five pairs to register the attendees (i.e., each pair will together register one attendee at a time). Attendees line up in a common line to be served by the next available pair of volunteers. Attendees arrive at an average rate of 139 per hour (assume Poisson arrival distribution) and the service time is, on average, two minutes (following a negative exponential distribution). What is the average time needed to register (includes waiting and registering), in minutes (round…
- What type of process—project, job shop, flow shop, and continuous flow—would most likely be used to produce the following? Explain your reasoning. Personal computers - Weddings- Paper-Continuous Paper Books- Tax preparation - What type of process – project, job shop, flow shop, and continuous flow – would most likely be used to produce the following? Gasoline- Air-conditioners - Specialized machine tools- Ships- Producing many flavors of ice cream-The following table details the tasks required forIndiana-based Frank Pianki Industries to manufacture a fullyportable industrial vacuum cleaner. The times in the table are inminutes. Demand forecasts indicate a need to operate with a cycletime of 10 minutes.ACTIVITY ACTIVITY DESCRIPTION IMMEDIATEPREDECESSORS TIMEA Attach wheels to tub — 5B Attach motor to lid — 1.5C Attach battery pack B 3D Attach safety cutoff C 4E Attach fi lters B 3F Attach lid to tub A, E 2G Assemble attachments — 3H Function test D, F, G 3.5I Final inspection H 2J Packing I 2a) Draw the appropriate precedence diagram for this productionline.b) Assign tasks to workstations and determine how much idletime is present each cycle.c) Discuss how this balance could be improved to 100%.d) What is the theoretical minimum number of workstations?A manufacturer needs to produce 300 coffee pots per 8 hour day. The discrete tasks required to produce a coffee pot have been identified, timed in seconds, and ordered as indicated in the table.Based on your takt time, what is the theoretical minimum number of workstations? Task Time Predecessors A 75 -- B 25 A C 40 A D 20 B, C E 50 C F 70 E G 45 D H 25 G I 15 G J 40 F, H, I