C15
docx
School
College of Southern Nevada *
*We aren’t endorsed by this school
Course
201
Subject
Accounting
Date
Jan 9, 2024
Type
docx
Pages
5
Uploaded by totytheproducer
C15 – Blake County – GASB 87
Problem/Solution
Task 1
Blake County had the following agreements in 20X9.
You have been asked to advise on the
accounting treatment for each of these agreements.
Indicate whether each of these is (1) a
short-term lease, (2) a lease, (3) a financed purchase, (4) a sale of an asset, or (5) none of the
above.
1.
Blake County obtains the right to use equipment that has a market rental rate of
$24,000 per year for five years for $1 per year. – None of the above
2.
Blake County enters into a 6-month lease on July 1, 20X0, that includes an option to
extend the lease an additional 6 months. – Short-term lease
3.
Blake County entered into a 12-month lease with an option to renew the lease for 12
months at a time up to 29 times. – Lease
4.
Blake County enters into a multiyear contract that conveys the exclusive right to use
a building on weekends.
Other parties use the building on the other days. – Lease
5.
Blake County enters into a 20-year contract on a building that transfers ownership
to Blake County at the end of the contract period. – Financed purchase
6.
Blake County enters into a 20-year contract on a building that transfers ownership
to Blake County at the end of the contract period.
The contract contains an option
that allows Blake County to terminate the lease at the end of each year.
It is likely
that Blake County will exercise the option. – Lease
1
C15 – Blake County – GASB 87
Problem/Solution
Rationale
:
1.
GASB Statement 87 specifies that a lease is defined as a contract that conveys
control of the right to use another entity’s nonfinancial asset as specified in the
contract for a period of time in an exchange or exchange-like transaction.
Blake
County’s right to use the equipment for $1 does not meet the description of an
exchange or exchange-like transaction.
2.
GASB Statement 87 states that a short-term lease is a lease that has a maximum
term of 12 months or less, including any options to extend.
3.
GASB Statement 87 states that a short-term lease is a lease that has a maximum
term of 12 months or less, including any options to extend.
Therefore, this is a lease.
4.
The contract conveys control of the right to use the building and therefore is a lease.
Under GASB Statement 87, the lease definition does not require uninterrupted
control of the right to use the facility.
5.
A contract that transfers ownership of the underlying asset to the lessee at the end of
the contract should be reported as a financed purchase by the lessee.
6.
Because Blake County has the option to terminate the lease and it is reasonably
likely that Blake County will exercise the option, the contract is a lease and not a
financed purchase.
2
C15 – Blake County – GASB 87
Problem/Solution
Task 2
Blake City enters into a lease contract to obtain equipment.
The lease begins January 1,
20X1, and is for noncancelable period of 36 months.
The city has an option to extend the
lease for an additional 24 months.
The city is doubtful that it will exercise the option to
extend the lease.
At the end of the lease term (either 36 or 60 months, depending on
whether the option to extend is exercised), the lease may be continued on a month-to-month
basis for up to 12 months, which either the city or the lessor can cancel.
The monthly base
rent is $2,000 per month, due on the first of each month, and includes 250 machine-hours
per month.
There is $10 fee for each machine-hour over 250.
In addition, the lease
contract requires $100 per month payment for routine repairs and maintenance.
The lease
contract states an interest rate of 5%.
A separate contract for delivery and installation fee
of $1,391 is due with the first lease payment.
The city chooses to amortize the lease
equipment on a straight-line basis.
Months
Present value interest factors $1 annuity due monthly basis using 5% annual rate
24
22.8889
36
33.5047
37
34.3657
38
35.2231
39
36.0770
40
36.9273
41
37.7740
42
38.6173
43
39.4571
44
40.2933
45
41.1261
46
41.9555
47
42.7814
48
43.6039
49
44.4230
50
45.2386
3
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
C15 – Blake County – GASB 87
Problem/Solution
Months
Present value interest factors $1 annuity due monthly basis using 5% annual rate
51
46.0509
52
46.8598
53
47.6654
54
48.4676
55
49.2665
56
50.0621
57
50.8544
58
51.6433
59
52.4290
60
53.2115
61
53.9907
62
54.7667
63
55.5394
64
56.3090
65
57.0753
66
57.8385
67
58.5985
68
59.3554
69
60.1091
70
60.8597
71
61.6071
72
62.3515
4
C15 – Blake County – GASB 87
Problem/Solution
1.
What is the lease term? – 36 months
2.
What is initial lease liability amount? - $67,009
3.
What is the initial value of the lease asset? $68,400
4.
What is the amount of monthly amortization expense?
Enter the amount in whole
dollars without a $ or comma. – 1,900
Rationale
:
1.
The initial lease term in the noncancelable 36-month period.
The 24-month option
to extend is excluded because the lessee is unsure that the option will be exercised.
The month-to-month period is excluded because either party can cancel it.
2.
The lease liability is the present value of an annuity due 5% annual interest, 36
monthly payments, $2,000 payments = $67,009.
The potential variable usage fees
based on future use are excluded.
The repair and maintenance service fees are also
excluded.
3.
The initial value of the lease asset is the initial lease liability amount of $67,009 plus
delivery and installation charge of $1,391 = $68,400.
4.
The amortization expense is the initial lease asset amount of $68,400 allocated on a
straight-line basis over 36 months [$68,400/36 = $1,900].
5
Related Documents
Related Questions
Required information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Problem 6-10 (Algo) Part 3
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Balance Sheet (Partial)
Current assets:
Current liabilities:
2024
$ 2,156,000
5,544,000
2,130,000
1,865,000
3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the
contract.
Note: Do not round intermediate calculations.
2024
2025
2026
$ 3,388,000 $ 2,371,600
2,156,000
0
3,414,000
3,300,000
2025
4,456,000…
arrow_forward
Solve both questions
Do not give answer in image formate
arrow_forward
Q.3.
arrow_forward
Please do not give solution in image format thanku
arrow_forward
Please do not give solution in image format thanku
arrow_forward
Required information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Costs incurred during the year
Estimated costs to complete as of year-end
Revenue
Gross profit (loss)
$
$
Problem 6-10 (Algo) Part 5
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs
incurred and costs to complete information.
Answer is complete but not entirely correct.
2024
2024
$ 2,016,000
5,184,000
2,180,000
1,890,000…
arrow_forward
Please help me
arrow_forward
Required information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Costs incurred during the year
Estimated costs to complete as of year-end
Revenue
Gross profit (loss)
$
$
Problem 6-10 (Algo) Part 5
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs
incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest
whole dollar…
arrow_forward
Required information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Balance Sheet (Partial)
Current assets:
Accounts receivable
Construction in progress
Less: Billings
Costs and profit in excess of billings
Current liabilities:
Construction in progress
Problem 6-10 (Algo) Part 3
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the
contract. (Do not round intermediate calculations.)
X Answer is…
arrow_forward
Required information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Balance Sheet (Partial)
Current assets:
2022
2021
$2,044,000
5,256,000 2,628,000
$2,628,000
2,170,000
2,502,000
1,885,000
2,600,000
Current liabilities:
Problem 6-10 (Algo) Part 3
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the
contract. (Do not round intermediate calculations.)
2021
0
2023
$2,890,800
2022
0
5,328,000…
arrow_forward
Required information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Problem 6-10 (Algo) Part 1
Westgate recognizes revenue over time according to percentage of completion.
Revenue
Gross profit (loss)
2021
$2,044,000
5,256,000
2,170,000 2,502,000
1,885,000
2,600,000
2021
2022
2023
2022
$2,628,000 $2,890,800
2,628,000
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate
calculations. Loss amounts should be indicated with a minus sign.)
2023
0
5,328,000
5,515,000
arrow_forward
Required information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Problem 6-10 (Algo) Part 1
Westgate recognizes revenue over time according to percentage of completion.
Revenue
Gross profit (loss)
2021
$2,044,000
5,256,000
2,170,000
1,885,000
X Answer is complete but not entirely correct.
2022
3,600,000 $
$
$
2021
2,800,000 $
756,000 $ 972,000
2022
$2,628,000
2,628,000
2,502,000
2,600,000
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate
calculations.…
arrow_forward
Required Information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following Information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
2025
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
2024
2026
$ 2,490,000
5,810,000
2,030,000
$ 3,984,000
$ 2,008,600
1,826,000
в
4,444,000
3,900,000
3,526,000
4,285,000
1,815,000
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10 (Algo) Part 4
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs
Incurred and costs to complete Information.
Note: Do not round Intermediate calculations and round your final…
arrow_forward
of 5
Required information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10 (Algo) Part 1
Revenue
Gross profit (loss)
$
$
2022
2021
$2,044,000 $2,628,000
5,256,000 2,628,000
2,170,000 2,502,000
1,885,000
2,600,000
Answer is not complete.
2022
2,200,000 $
1,868,000 X
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate
calculations. Loss amounts should be indicated with a…
arrow_forward
Hardev
arrow_forward
Rahul
arrow_forward
Required Information
Problem 6-10 (Static) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Costs incurred during the year
Estimated costs to complete as of year-end
Revenue
Gross profit (loss)
2024
$ 2,400,000
5,600,000
2,000,000
1,800,000
2024
2025
Problem 6-10 (Static) Part 5
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs
incurred and costs to complete information.
2026
2025
$ 3,600,000
2,000,000
Note: Do…
arrow_forward
Give me correct answer with explanation.v
arrow_forward
Vinubhai
arrow_forward
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Problem 6-10 (Algo) Part 5
Westgate recognizes revenue over time according to percentage of completion.
Costs incurred during the year
Estimated costs to complete as of year-end
Revenue
Gross profit (loss)
$
$
2024
$ 2,610,000
6,390,000
2,100,000
1,850,000
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs
incurred and costs to complete information.
X Answer is complete but not entirely correct.
2026
3,939,962
(110,038)…
arrow_forward
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
2024
$ 2,610,000
6,390,000
2,100,000
2025
2026
$ 3,162,000
$ 2,230,800
2,028,000
0
3,672,000
1,850,000
3,000,000
4,228,000
5,150,000
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10 (Algo) Part 5
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs
incurred and costs to complete information.
Note: Do not round intermediate calculations and round your final answers to the nearest…
arrow_forward
!
Required information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara
County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
2024
2025
$
2026
$
Cost incurred during the year
Estimated costs to complete as of
year-end
Billings during the year
Cash collections during the year
2,016,000 2,808,000 2,613,600
5,184,000 2,376,000
0
2,180,000 2,644,000 5,176,000
1,890,000 2,500,000 5,610,000
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10 (Algo) Part 5
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the
following costs incurred and costs to complete information.
Note: Do not round intermediate calculations and round your final…
arrow_forward
help please answer in text form with proper workings and explanation for each and every part and steps with concept and introduction no AI no copy paste remember answer must be in proper format with all working
arrow_forward
help please answer in text form with proper workings and explanation for each and every part and steps with concept and introduction no AI no copy paste remember answer must be in proper format with all working
arrow_forward
!
Required information
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
2024
$ 2,156,000
5,544,000
2,130,000
1,865,000
Problem 6-10 (Algo) Part 2
2025
$ 3,388,000
2,156,000
3,414,000
3,300,000
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
2026
$ 2,371, 600
4,456,000
4,835,000
2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs
incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit…
arrow_forward
Please do not give solution in image format ?.
arrow_forward
Sh12
arrow_forward
5
arrow_forward
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Costs incurred during the year
Estimated costs to complete as of year-end
Revenue
Gross profit (loss)
2021
2022
$2,044,000 $2,628,000
5,256,000
2,628,000
2,170,000
2,502,000
1,885,000
2,600,000
Problem 6-10 (Algo) Part 5
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs
incurred and costs to complete information. (Do not round intermediate…
arrow_forward
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Balance Sheet (Partial)
Current assets:
Accounts receivable
Construction in progress
Problem 6-10 (Algo) Part 3
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the
contract. (Do not round intermediate calculations.)
Less: Billings
Costs and profit in excess of billings
Current liabilities:
Construction in progress
Answer is complete but not entirely…
arrow_forward
Do not give answer in image formet and hand writing
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you


Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,

Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON

Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Related Questions
- Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Problem 6-10 (Algo) Part 3 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Current liabilities: 2024 $ 2,156,000 5,544,000 2,130,000 1,865,000 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Note: Do not round intermediate calculations. 2024 2025 2026 $ 3,388,000 $ 2,371,600 2,156,000 0 3,414,000 3,300,000 2025 4,456,000…arrow_forwardSolve both questions Do not give answer in image formatearrow_forwardQ.3.arrow_forward
- Please do not give solution in image format thankuarrow_forwardPlease do not give solution in image format thankuarrow_forwardRequired information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) $ $ Problem 6-10 (Algo) Part 5 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. Answer is complete but not entirely correct. 2024 2024 $ 2,016,000 5,184,000 2,180,000 1,890,000…arrow_forward
- Please help mearrow_forwardRequired information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) $ $ Problem 6-10 (Algo) Part 5 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar…arrow_forwardRequired information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Accounts receivable Construction in progress Less: Billings Costs and profit in excess of billings Current liabilities: Construction in progress Problem 6-10 (Algo) Part 3 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) X Answer is…arrow_forward
- Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: 2022 2021 $2,044,000 5,256,000 2,628,000 $2,628,000 2,170,000 2,502,000 1,885,000 2,600,000 Current liabilities: Problem 6-10 (Algo) Part 3 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) 2021 0 2023 $2,890,800 2022 0 5,328,000…arrow_forwardRequired information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Problem 6-10 (Algo) Part 1 Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) 2021 $2,044,000 5,256,000 2,170,000 2,502,000 1,885,000 2,600,000 2021 2022 2023 2022 $2,628,000 $2,890,800 2,628,000 Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.) 2023 0 5,328,000 5,515,000arrow_forwardRequired information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Problem 6-10 (Algo) Part 1 Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) 2021 $2,044,000 5,256,000 2,170,000 1,885,000 X Answer is complete but not entirely correct. 2022 3,600,000 $ $ $ 2021 2,800,000 $ 756,000 $ 972,000 2022 $2,628,000 2,628,000 2,502,000 2,600,000 Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations.…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education


Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,

Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON

Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education