D079 Task 1- Taylor Mays (final)
.docx
keyboard_arrow_up
School
Western Governors University *
*We aren’t endorsed by this school
Course
D079
Subject
Business
Date
Jun 27, 2024
Type
docx
Pages
3
Uploaded by BailiffDiscovery15585
D079 Business Environment Applications II
Task 1: Project Management
Taylor Mays
Student ID #: 010431129
A1a.
To begin the project, we must create a plan, determine the necessary steps, and select the people who will be involved and dedicated to the endeavor. The plan is to establish a catering business for customers who live up to 25 miles from the market. This is being launched in honor of the market's approaching 10th anniversary. Additionally, local vendors that sell organic food that is sourced locally are sought after by the local customer base. The catering business must be operational within 30 days to meet this standard.
A1b.
Stakeholder 1: Customers have a significant role in this. They must be within 25 miles of the market to be eligible for the delivery service. If you're in that zone, the objective is to deliver in one
hour. Customers can only receive this service if they are within this area.
Stakeholder 2: The suppliers are yet another crucial group. According to the supplier, the lettuce required for the catering plan's lunch salads won't be available. We may have an ethical conundrum when using non-organic lettuce if they cannot deliver the organic produce. The company would benefit only if we used fresh, organic ingredients. Suppliers risk not getting paid if they cannot deliver the organic lettuce, and our objectives may not be met.
Stakeholder 3:
Employees, or the caterers, are also essential. They have just two weeks to determine how much each lunch will cost, review what needs to be done before the business launches and determine how catering will affect in-store operations. These changes impact employees because they must rapidly obtain accurate information, which is difficult given the frequent changes.
A1c.
The project appears feasible considering the scope, cost, and time variables.
Customers
within 25 miles of the store can order catering once a week, with lunch orders delivered within an hour. We will initially have to spend more money on the budget because we must purchase catering supplies, but we can use some funds from the company's retail division. Given that we already have some employees and products ready to go, a 30-day launch seems realistic.
A2a.
First milestone:
Within the first week, hire new employees. To meet the 60-minute delivery target, we will need more delivery drivers. Additionally, staffing specialists will need to connect with suppliers or identify new ones to guarantee we have the food products we require in time for the launch.
Second Milestone
: Have a research and development team collect information about the neighborhood in the second week to estimate the number of possible customers. This will
guarantee seamless business operations and help to streamline logistics.
Third Milestone:
Request an analysis of all final costs from the finance department the third week before launch. This will guarantee that we have enough couriers to handle the deliveries and that all goals are met on schedule.
A2b.
Specific (S):
To stay within the $7000 budget, reduce lunch expenses by $700.
Measurable (M):
Lower meal expenses by 10% or more.
Achievable (A):
To assist suppliers in meeting demand, consider reducing the portion sizes of the free lunches.
Relevant (R):
Determine which expenses can be reduced to stick to the $7000 budget.
Time-bound (T):
Fulfill the $7000 budget in 30 days or less.
A2c.
Risk 1
: Since we only have one delivery vehicle, one of the most significant risks to the success of this project is the possibility of late or delayed deliveries. Customers may not receive their food on time if we receive several orders that must all be delivered in an hour due to delays caused by traffic or unforeseen orders.
Risk 2
: Another risk is working with more suppliers to meet our demand. We risk running out of the products needed for the launch if we need more suppliers, which could
damage our reputation and image.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule.
Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.
Q
Activity
A
B
C
D
E
The cost of shortening of project is $
F
G
H
I
Normal Time
(weeks)
5
7
7
7
1
3
5
4
2
Crash Time
(weeks)
4
4
Activity
A
B
C
D
E
6
4
6
1
3
4
2
2
Cost to Crash
($ per week)
. (Enter your response as a whole number.)
300
50
300
250
200
200
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.)
Time according to
schedule (weeks)
Time according to
schedule (weeks)
Immediate Predecessor(s)
Activity
F
G
H
I
None
None
A
A
B
3~~
C, D
D, E
F
G
arrow_forward
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?
Normal
Cost
$800
$200
$600
$750
$1,200
Normal
Crash
Activity Time (days) Time (days)
4
3
8
6
The total cost of crashing the project by 4 days is $
ABCDE
487
355
(Enter your response as a whole number.)
Total Cost
with Crashing Immediate Predecessor(s)
$1,500
$1,650
By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.)
Each Activity Should be
Reduced BY
(days)
Activity
A
B
C
D
E
$1,100
$600
$650
A
C
arrow_forward
scenarios of a project activities (tables given below) and their required times to be completed in
addition to their predecessors for developing a Website' :
Activity
Description
Duration (days)
Preceding Activities
A
Determine user needs
8
Review s/w and languages
Purchase software
10
Design format and style
10
E
Write programs
A
F
Review outcome product with user
12
G
Make revisions
4
C
H
Select server site
E
I
Install on server
14
D, F
Test
G, H, I
3. Highlight the total time to complete the project (days)
4. Calculate the late finishing time (backwards calculations)
arrow_forward
Project Scope Management
Khan, (2006) (see below) states that, "Managing the scope of a project is the most important function of a project manager ... Effective scope management of a project also ensures the success of key completion areas, including time, cost, and quality.
Project scope management can be further subdivided into its components which include: project initiation, scope planning, scope definition, scope verification, and scope change control."
Based on your Integrated Project:
Select two of the subdivisions above and discuss the primary issues that could arise from the process.
Your response should begin with a definition of the selected subdivision before detailing the selected process
arrow_forward
The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule.
Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.
Normal Time
Crash Time
Activity
(weeks)
(weeks)
Cost to Crash
($ per week)
Immediate Predecessor(s)
A
5
4
200
B
9
8
300
None
None
C
4
2
200
A
4
2
250
A
E
3
3
B
F
3
3
C, D
G
3
1
150
D, E
6
4
350
F
G
7
4
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.)
Activity
A
Time according to
schedule (weeks)
Activity
Time according to
schedule (weeks)
F
G
B
C
D
E
arrow_forward
7
arrow_forward
1. A project has been defined to contain the following list of activities along with their required times for completion.
What would happen if activity 6 were revised to take 6 weeks instead of 1 week?
2. Construct a Gantt chart for the project defined in Problem 1.
arrow_forward
List two outputs for each of the Project Risk Management processes (note that the Implement Risk Responses process is not discussed in this chapter)
arrow_forward
Students shall, with a point of view of him/herself as project manager (PM), submit a Project Management Plan (PMP) for the given engineering project below: - “Procurement & Installation of Emergency Generator at Fire station” Students are allowed to propose their own project, given that the projects shall have enough scale to address the element described below:- a. Student should produce a project definition statement regarding the proposed project. b. Student should propose a suitable project team to carry out the project. Student should in the PMP describe the duties and power of different team memebrs in the project. c. The PMP shall include a risk management plan, which student shall identify, analyse and proposed mitigations measures for smooth delivery of the project deliverables. The risk manamgenet plan shall include a risk register d. The PMP shall include a quality management plan, which student shall propose a method statement to control the quality of the delivery of…
arrow_forward
What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days?
NORMAL
CRASH
TIME (DAYS) TIME (DAYS)
9
7
7
6
5
4
6
4
9
6
ACTIVITY
Design (A)
Wiring (B)
Chip install (C)
Software (D)
Testing (E)
The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $
NORMAL
COST
200
800
600
1,100
1,200
CRASH
COST
300
875
675
1,300
1,875
IMMEDIATE PREDECESSOR(S)
(enter your response as a whole number).
A, B
C
arrow_forward
What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days?
ACTIVITY
Design (A)
Wiring (B)
Chip install (C)
Software (D)
Testing (E)
NORMAL
CRASH
TIME (DAYS) TIME (DAYS)
8
7
7
6
6
6
9
6
NORMAL
COST
400
1,100
700
900
1,200
CRASH
COST
550
1,300
800
1,250
1,950
IMMEDIATE PREDECESSOR(S)
The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $
whole number).
A, B
C
(enter your response as a
arrow_forward
The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs
and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs
Activity
A
B
С
D
E
F
G
H
Normal Time
(weeks)
5
9
4
4
3
3
Activity
A
B
с
D
Crash Time
(weeks)
4
8
2
2
3
3
00000
6
Cost to Crash
(5 per week)
250
350
881 18889
G
250
300
200
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers)
Time according to
schedule (weeks)
400
Activity
F
Immediate Predecessor(s)
None
None
A
A
B
C.D
D, E
F
G
Time according to
schedule (weeks)
arrow_forward
Top administrators in a hospital have approved a project to improve the efficiency of pharmaceutical services department by the end of the fiscal year to satisfy new state regulations for the coming year. However, they are concerned about four potential threats (1) the cost to implement the changes may be excessive (2) the pharmacists may resist changes (3) the project may run much longer than expected and not be ready for coming fiscal year, (4) The changes might reduce the quality of drug care in the hospital. The likelihood and negative impact of each threat have been solicited from the managers and are as follows, based on a seven-point scale where seven is the most likely and most negative impact.
Threat
Probability
Impact
1
5
3
2
6
5
3
3
4
4
4
7
Construct a risk matrix and identify what you would consider to be critical, monitor and ignore threats. Explain your reasoning.
arrow_forward
You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need to
conduct a cost analysis of the project. Indirect costs are $1,800 per week, and penalty costs are $800 per week after week 12.
Activity
A
BCDEF
Immediate
Predecessor(s)
-
A
B
B, C
Normal Time (weeks) Crash Time (weeks)
4
1
3
1
3
6
6
5
1
6
7
Normal Cost Crash Cost
($)
($)
5,000
8,500
7,500
9,500
4,000
4,000
6,500
12,500
3,500
7,000
4,000
7,000
a. What is the minimum-cost schedule for this project?
The minimum-cost schedule is weeks. (Enter your response as an integer.)
b. What is the difference in total project costs between the earliest completion time of the project using "normal" times and the
minimum-cost schedule you derived in part (a)?
The minimum-cost schedule costs $ less than using the "normal" times. (Enter your response as an integer.)
arrow_forward
1.You are the new Chief Design Officer (CDO) of a start-up, DTUI Inc. The project is to design a system for selling pottery. The aim is to develop an interface that meets the needs of both the potters and the customers. Describe in detail a design methodology of four stages to facilitate the proper design of such a system. Write your answer in the form of a management plan for this project. For each stage, indicate the number of weeks that should be allocated.
Hint: Note the four phases of the design process: • Requirements analysis • Preliminary (conceptual) and detailed design • Build and implementation • Evaluation
For questions 2–4, refer to the following scenario: The State of Maryland is developing a web-voting interface. For selecting the candidates, one design (RB) is a set of radio buttons and another is (CB) a combo-box (drops down when selecting the scroll arrow icon), both using standard fonts at 10-point size.
2. Compare these two designs when there are four candidates…
arrow_forward
The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project
three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible.
Identify activities to crash while minimizing the additional crash costs. .
Normal Time
Crash Time
Cost to Crash
Immediate
Activity
(weeks)
(weeks)
Predecessor(s)
(S per week)
300
A
4
None
None
B
4
50
C
6.
300
250
A
E
1
B.
C.D
D, E
4
200
H.
4
2
200
2.
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole
numbers.)
777
arrow_forward
Subject: Construction Quality Management
In planning projects, it is essential that planners bring out critical project characteristics so that the project manager may direct the work toward completion. Discuss the criteria for project managers that encompasses four areas which must be considered during planning and the plan must include the provisions to support these actions.
arrow_forward
Widgetco is making a prototype of a new product. The productconsists of two subassemblies. Before building either subassembly, the firm must purchaseraw materials and train workers. Before the subassemblies can be combined, subassembly2 must be inspected. The following table describes the project:Activity Description Requires Duration (Days)A Train workers 6B Purchase materials 9C Make subassembly 1 A,B 8D Make subassembly 2 A,B 7E Inspect subassembly 2 D 10F Combine subassemblies C, E 12G Subassembly 2 safety report E 6How quickly can Widgetco complete this project?(a) Define decision variables.(b) Write a suitable LP problem formulation.
arrow_forward
help me with a,b,c
arrow_forward
Identify the critical path for the following three scenarios of a project activities (tables given
below) and their required times to be completed in addition to their predecessors for developing
a Website':
Activity
Description
Duration (weeks)
Preceding Activities
A
Determine user needs
3
Review s/w and languages
1
C
Purchase software
4
D
Design format and style
4
B
E
Write programs
A
F
Review outcome product with user
C
G
Make revisions
1
D, F
H
Select server site
3
E
I
Install on server and test
6.
G
J
3
Н, I
1. Draw the path.
2. Calculate the early finishing time (forwards calculations)
3. Highlight the total time to complete the project (weeks)
4. Calculate the late finishing time (backwards calculations)
5. Calculate the slack time of the non-critical path activities
6. Identify the critical path (highlight critical path activities)
arrow_forward
Please create SWOT Analysis
Note: details in the photo attached
arrow_forward
I'm unable to answer the following question?
What is the total cost of crashing the project from its current duration down to 13 weeks?
arrow_forward
The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project
threethree
weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.
Activity
Normal Time
(weekweeks)
Crash Time
(weekweeks)
Cost to Crash
($ per
weekweek)
Immediate Predecessor(s)
A
55
44
300300
None
B
77
44
5050
None
C
77
66
300300
A
D
77
66
250250
A
E
11
11
long dash—
B
F
33
33
long dash—
C, D
G
55
44
200200
D, E
H
44
22
200200
F
I
22
22
long dash—
G
Part 2
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as…
arrow_forward
An electrical engineer wants to finish his new device production project within 47 days to meet his contract deadline. Explain what he should do to meet his plan . The project information is listed below. Please ignore the indirect cost.
arrow_forward
Identify the critical path for the following three scenarios of a project activities (tables given
below) and their required times to be completed in addition to their predecessors for developing
a 'Website':
Activity
Description
Duration (weeks)
Preceding Activities
A
Determine user needs
3
B
Review s/w and languages
1
Purchase software
4
Design format and style
В
E
Write programs
2
A
F
Review outcome product with user
5
G
Make revisions
1
D, F
H
Select server site
3
E
I
Install on server and test
6
J
3
H, I
5. Calculate the slack time of the non-critical path activities
6. Identify the critical path (highlight critical path activities)
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
BUSN 11 Introduction to Business Student Edition
Business
ISBN:9781337407137
Author:Kelly
Publisher:Cengage Learning
Essentials of Business Communication (MindTap Cou...
Business
ISBN:9781337386494
Author:Mary Ellen Guffey, Dana Loewy
Publisher:Cengage Learning
Accounting Information Systems (14th Edition)
Business
ISBN:9780134474021
Author:Marshall B. Romney, Paul J. Steinbart
Publisher:PEARSON
International Business: Competing in the Global M...
Business
ISBN:9781259929441
Author:Charles W. L. Hill Dr, G. Tomas M. Hult
Publisher:McGraw-Hill Education
Related Questions
- The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Q Activity A B C D E The cost of shortening of project is $ F G H I Normal Time (weeks) 5 7 7 7 1 3 5 4 2 Crash Time (weeks) 4 4 Activity A B C D E 6 4 6 1 3 4 2 2 Cost to Crash ($ per week) . (Enter your response as a whole number.) 300 50 300 250 200 200 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Time according to schedule (weeks) Time according to schedule (weeks) Immediate Predecessor(s) Activity F G H I None None A A B 3~~ C, D D, E F Garrow_forwardWhat is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Cost $800 $200 $600 $750 $1,200 Normal Crash Activity Time (days) Time (days) 4 3 8 6 The total cost of crashing the project by 4 days is $ ABCDE 487 355 (Enter your response as a whole number.) Total Cost with Crashing Immediate Predecessor(s) $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $600 $650 A Carrow_forwardscenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a Website' : Activity Description Duration (days) Preceding Activities A Determine user needs 8 Review s/w and languages Purchase software 10 Design format and style 10 E Write programs A F Review outcome product with user 12 G Make revisions 4 C H Select server site E I Install on server 14 D, F Test G, H, I 3. Highlight the total time to complete the project (days) 4. Calculate the late finishing time (backwards calculations)arrow_forward
- Project Scope Management Khan, (2006) (see below) states that, "Managing the scope of a project is the most important function of a project manager ... Effective scope management of a project also ensures the success of key completion areas, including time, cost, and quality. Project scope management can be further subdivided into its components which include: project initiation, scope planning, scope definition, scope verification, and scope change control." Based on your Integrated Project: Select two of the subdivisions above and discuss the primary issues that could arise from the process. Your response should begin with a definition of the selected subdivision before detailing the selected processarrow_forwardThe table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Normal Time Crash Time Activity (weeks) (weeks) Cost to Crash ($ per week) Immediate Predecessor(s) A 5 4 200 B 9 8 300 None None C 4 2 200 A 4 2 250 A E 3 3 B F 3 3 C, D G 3 1 150 D, E 6 4 350 F G 7 4 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Activity A Time according to schedule (weeks) Activity Time according to schedule (weeks) F G B C D Earrow_forward7arrow_forward
- 1. A project has been defined to contain the following list of activities along with their required times for completion. What would happen if activity 6 were revised to take 6 weeks instead of 1 week? 2. Construct a Gantt chart for the project defined in Problem 1.arrow_forwardList two outputs for each of the Project Risk Management processes (note that the Implement Risk Responses process is not discussed in this chapter)arrow_forwardStudents shall, with a point of view of him/herself as project manager (PM), submit a Project Management Plan (PMP) for the given engineering project below: - “Procurement & Installation of Emergency Generator at Fire station” Students are allowed to propose their own project, given that the projects shall have enough scale to address the element described below:- a. Student should produce a project definition statement regarding the proposed project. b. Student should propose a suitable project team to carry out the project. Student should in the PMP describe the duties and power of different team memebrs in the project. c. The PMP shall include a risk management plan, which student shall identify, analyse and proposed mitigations measures for smooth delivery of the project deliverables. The risk manamgenet plan shall include a risk register d. The PMP shall include a quality management plan, which student shall propose a method statement to control the quality of the delivery of…arrow_forward
- What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) 9 7 7 6 5 4 6 4 9 6 ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ NORMAL COST 200 800 600 1,100 1,200 CRASH COST 300 875 675 1,300 1,875 IMMEDIATE PREDECESSOR(S) (enter your response as a whole number). A, B Carrow_forwardWhat is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) NORMAL CRASH TIME (DAYS) TIME (DAYS) 8 7 7 6 6 6 9 6 NORMAL COST 400 1,100 700 900 1,200 CRASH COST 550 1,300 800 1,250 1,950 IMMEDIATE PREDECESSOR(S) The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $ whole number). A, B C (enter your response as aarrow_forwardThe table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs Activity A B С D E F G H Normal Time (weeks) 5 9 4 4 3 3 Activity A B с D Crash Time (weeks) 4 8 2 2 3 3 00000 6 Cost to Crash (5 per week) 250 350 881 18889 G 250 300 200 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers) Time according to schedule (weeks) 400 Activity F Immediate Predecessor(s) None None A A B C.D D, E F G Time according to schedule (weeks)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- BUSN 11 Introduction to Business Student EditionBusinessISBN:9781337407137Author:KellyPublisher:Cengage LearningEssentials of Business Communication (MindTap Cou...BusinessISBN:9781337386494Author:Mary Ellen Guffey, Dana LoewyPublisher:Cengage LearningAccounting Information Systems (14th Edition)BusinessISBN:9780134474021Author:Marshall B. Romney, Paul J. SteinbartPublisher:PEARSON
- International Business: Competing in the Global M...BusinessISBN:9781259929441Author:Charles W. L. Hill Dr, G. Tomas M. HultPublisher:McGraw-Hill Education
BUSN 11 Introduction to Business Student Edition
Business
ISBN:9781337407137
Author:Kelly
Publisher:Cengage Learning
Essentials of Business Communication (MindTap Cou...
Business
ISBN:9781337386494
Author:Mary Ellen Guffey, Dana Loewy
Publisher:Cengage Learning
Accounting Information Systems (14th Edition)
Business
ISBN:9780134474021
Author:Marshall B. Romney, Paul J. Steinbart
Publisher:PEARSON
International Business: Competing in the Global M...
Business
ISBN:9781259929441
Author:Charles W. L. Hill Dr, G. Tomas M. Hult
Publisher:McGraw-Hill Education