BUSM 5130
Assignment #3
Solve the following problem for this assignment. Please complete the required information on the front-page template that I have posted on Moodle and include it in
your assignment. Save your Excel file with your name and ID number as the file name. Upload your solution in Moodle. This assignment is due at the beginning of the class next week
.
1.
Open the Restaurant file on Moodle and answer the following questions:
a.
What is the mean, median and mode for Meal cost at Metro Area
Mean
40.36
Median
40
Mode
25
b.
Construct frequency distribution, relative frequency, percent frequency, cumulative frequency, cumulative relative frequency and cumulative percent frequency for this data.
Meal Cost
Frequency
relative frequency
percent frequency
10-19
1
0.02
2
19-29
13
0.26
26
30-39
11
0.22
22
40-49
10
0.2
20
50-59
11
0.22
22
60-69
4
0.08
8
Grand Total
50
1
100
Meal Cost Cumulative frequency
Cumulative relative frequency Cumulative percent frequency
<=19
1
0.02
2
<=29
14
0.28
28
<=39
25
0.5
50
<=49
35
0.7
70
<=59
46
0.92
92
<=69
50
1
100
c.
Chart your data in part b (use the right chart for the right tables, as you see fit).
10-19
19-29
30-39
40-49
50-59
60-69
0
2
4
6
8
10
12
14
Histogram of the Meal Cost at Metro Area Meal Cost Frequency
10-19
14%
19-29
23%
30-39
19%
40-49
18%
50-59
19%
60-69
7%
Percent frequency of Cost at Metro Area
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
A manufacturer is designing a product layout for a new product productionIt plans to use a production line for 8 hours per day in order to meet forecasted demand of 70 units per day. The product requires 7 tasks in total. These tasks are namelyABC, D, E, F, and Grespectively. Task A does not have any predecessor to startTo start Task B.it requires Task A to be completedStarting tasks needs, the task B to be completed. Also, starting task Dneeded task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed task Fto be completed. The processing times for tasks, ABC, D. E. and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8 and 4.7 minutes respectively. What should be the cycle time in minutes? a 4.7 b. None is the correct answer Oc 7.5 d6.86 e.
arrow_forward
About Assignment Short-Term Scheduling The following table shows the contribution of benefits provided by 5 employees A, B, C, and D in handling 5 types of work
I, II, III, IV, and V.
Work
Employee
A
B
C
D
I
10
12
10
8
II
14
10
9
15
III
8
8
7
9
IV
13
15
8
16
V
10
13
14
11
Determine the maximum contribution that can be obtained using the Assignment Models
arrow_forward
Florida Southwestern State College has decided to implement a new registration system that will allow students to register online as well as in person. As an IT manager, you decide to set up a JAD session to help define the requirements for a new system. The FSW organization is fairly typical, with an administrative staff that includes a registrar, student support and service team, a business office, an IT group, and a number of academic departments. Using this information, you start work on a plan to carry out the JAD session. Who would you invite to the session, and why? What would be your agenda for the session, and what would take place at each stage of the session?
arrow_forward
Asap please
arrow_forward
Don’t solve it In excel please .
arrow_forward
Use Mathematics CAPS curriculum
arrow_forward
Design a SWOT analysis for a IT help desk center. This help desk has 3 tiers:
Tier 1: Lower level, can help with small issues on a computer (logging in, website issues).
Tier 2: Physical repairs, can help with troubleshooting hardware problems or any problem Tier 1 could not solve. Will replace broken components.
Tier 3: Administration, this tier has all the bosses that see over Tier 2 and Tier 1. They will help with Tier 2 if needed, mostly used in disaster scenarios.
arrow_forward
Used : Call center optimization as project , please give Citation if possible
are required to identify and select a project that you have worked on, whether as a project manager or project team member. If you have not worked on a project before or you are unable to select a suitable project based on your work experiences, you should select a project that you know about and have sufficient access to the project’s information. Remember, the project that you select (the case) should have already been completed/finished, implemented, or executed. If you decide to select a project outside of your work experiences, there are several completed projects in your local community, your country, the region, or internationally that you may be able to use as a case for this assignment. There are no restrictions on the type of project that you select or decide to work with, however please be deliberate in your selection or when choosing a project to work with. You should avoid selecting a project…
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 80 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one: a. None is the correct answer b. 5 C. 6 d. 3 e. 1
arrow_forward
A nursing home must schedule nurses in a manner that balances providing adequate patient care while keeping costs down. From historical records, administrators can project the minimum number of nurses to have on hand during each day/time slot. This data is shown below.
Shift
Time Slot
Minimum number of nurses needed
1
12 am-4
10
2
4 am-8
6
3
8 am-12
8
4
12 pm-4
12
5
4 pm-8
10
6
8 pm-12
14
Nurses must start work at the beginning of one of the four-hour shifts (starting as early as 12 am midnight or as late as 8pm evening) and work for eight hours. Nurses who begin working at 8 pm will work until 4 am the next morning.
Formulate and solve the nurse-scheduling problem so as to minimize excess stagging while satisfying minimum staffing requrements.
What is the value of total excess staffing?
arrow_forward
Solve this assignment problem in Excel to find the lowest cost solution and answer the following questions:
1.Which employee is assigned to job 1?
Employee C (or) Employee B (or) Employee A
2. Which employee is assigned to job 2?
Employee C (or) Employee B (or) Employee A
3.Which employee is assigned to job 3?
Employee C (or) Employee B (or) Employee A
4.What is the minimum cost to complete all three jobs?
arrow_forward
Use the “A1_Excel_Template” Excel file to solve the questions below.
Submit two files for this assignment:
The completed word file (use this file to compile your solutions) with your answers including Excel screenshots.
The Excel file with your answers.
Specific Instructions:
The “A1_Excel_Template” file contains the data sets on separate worksheets (tabs) labeled as “ Problem 1_DHL”, “Problem 2_Patients”, and so on. Use these datasets to complete problems below.
Save the solved problems in A1_Excel_Template as A1_Last Name. For Instance,
Use this word file to compile your answers. You need to take a screenshot of your Excel answers ( e.g., frequency table, bar chart, pie chart, .. etc.) and paste it under appropriate question in this word file.
Save the A1_ word file as A1_Last Name. For Instance, A1_Kochan.
Submit the excel file and this word file that contain your answers.
arrow_forward
Assignment problems are LPP problems where a project/work is assigned to a specific machine or to an individual. It is a one-to-one pairing.
Mr. Pat, the manager of MTVM Machine Shop plans to assign his four projects to the following contractors, TV Engineering, JPAT Enterprise, HP Construction and VH Materials Engineering. Construct a problem and solve the Objective is minimizing the cost of the project.
Note: The labelling of the table should be like this.
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in
order to meet forecasted demand of 180 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F,
and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C
needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task
C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The
processing times for tasks, A, B, C, D, E, F, and G are 2.4, 2.2, 0.9, 1.0, 1.2, 1.8, are 1.5 minutes respectively. Applying the most
remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What will be the idle time
for the LAST Workstation?
a.
0.57
b.
1.17
С.
0.47
d.…
arrow_forward
Instructions:
Do this on a clean sheet of paper (preferably bond paper).
Construct a complete Linear Programming Model.
Show a complete, legible, and well-organized solution.
Upload in Canvas an image or pdf file of your work through this page.
3. In order to produce 1000 tons of non-oxidizing steel for engine valves, at least the following units of manganese, chromium and molybdenum, will be needed weekly: 10 units of manganese, 12 units of chromium, and 14 units of molybdenum (1. unit is 10 pounds). These metals are obtainable from dealers in nonferrous metals, who, to attract markets make them available in cases of three sizes, S, M and L. One S case costs $9 and contains 2 units of manganese, 2 units of chromium and 1 unit of molybdenum. One M case costs $12 and contains 2 units of manganese, 3 units of chromium, and 1 unit of molybdenum. One L case costs $15 and contains 1 unit of manganese, 1 unit of chromium and 5 units of molybdenum. How many cases of each kind should be…
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8
hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These
tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it
requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting taskD needed task
B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of
both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C,
D, E, F, and G are 2.3, 2.1,0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for
balancing the assembly line, with ties broken according to longest task time first. What will be the idle time for the
LAST Workstation?
O a. 1.7
O b. None is the…
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in
order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F,
and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C
needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task
C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The
processing times for tasks, A, B, C, D, E, F, and G are 2.4, 2.2,0.9, 1.0, 1.2, 1.8, are 1.5 minutes respectively. How many minimum
numbers of workstations are needed? Round-up to the nearest integer
а. 8
b. 4
С. 6
O d. 5
O e. None is the correct answer
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are:
a. B,C and D
b. C…
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line
for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in
total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to
start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed.
Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C.
Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task
F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7
minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken
according to longest task time first, the tasks that will be assigned to the SECOND workstation are
Select one:
Oa. B and…
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line
for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in
total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to
start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed.
Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C.
Whereas starting task F needs the completion of both the tasks D andE. Finally, starting task G needed, task
F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7
minutes respectively. How many minimum numbers of workstations are needed?
Select one:
O a. 6
Ob. 2
Oc.4
O d. None is the correct answer
O e. 8
Next page
Immp to
arrow_forward
A manufacturer is designing a product layout
for a new product production. It plans to use
a production line for 8 hours per day in order
to meet forecasted demand of 100 units per
day. The product requires 7 tasks in total.
These tasks are namely, A, B, C, D, E, F, and
G respectively. Task A does not have any
predecessor to start. To start Task B, it
requires Task A to be completed. Starting
tasks C needs, the task B to be completed.
Also, starting task D needed task B to be
completed. Task E can only start upon
completion of Task C. Whereas starting task
F needs the completion of both the tasks D
and E. Finally, starting task G needed, task F
to be completed. The processing times for
tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9,
1.0, 1.2, 1.8, are 4.7 minutes respectively.
What should be the (calculated) cycle time in
minutes?
а.
4.5
O b. None is the correct answer
С.
0.9
d. 4.8
е.
4.4
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in
order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F,
and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C
needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task
C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The
processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, and 4.7 minutes respectively. How many minimum
numbers of workstations are needed?
O a. 6
O b. None is the correct answer
O c. 8
O d. 2
O e.
4
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet
forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does
not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also,
starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of
both the tasks Dand E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9,
1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to
longest task time first, the tasks that will be assigned to the FIRST workstation are
O a. A, B, and C
Ob.
None…
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order
to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G
respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the
task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C Whereas
starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing
times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of
workstations are needed?
Select one:
O a.2
O b. None is the correct answer
O c.6
O d. 8
O e. 4
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day
in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C,
D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed.
Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start
upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G
needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7
:minutes respectively. What should be the (calculated) cycle time in minutes? Select one
0.9
.b
4.5
.C
None is the correct answer
4.4
.e
4.8
The correct answer is: 4.8
O O O O
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day
in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C,
D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed.
Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start
upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G
needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7
minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to
:longest task time first, the tasks that will be assigned to the FOURTH workstation are Select one
.a
G only…
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order
to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G
respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the
task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas
starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing
times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for
balancing the assembly line, with ties broken according to longest task tíme first. What will be the idle time for the FOURTH Workstation?
Select one:
O a 20
O 6.0.1…
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line
for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in
total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to
start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed.
Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C.
Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task
F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7
minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken
according to longest task time first. What is the idleness in percentage?
Select one:
O a. 81.82
Ob. 20.83
O c. None is…
arrow_forward
A manufacturer is designing a product layout
for a new product production. It plans to use
a production line for 8 hours per day in order
to meet forecasted demand of 100 units per
day. The product requires 7 tasks in total.
These tasks are namely, A, B, C, D, E, F, and
G respectively. Task A does not have any
predecessor to start. To start Task B, it
requires Task A to be completed. Starting
tasks C needs, the task B to be completed.
Also, starting task D needed task B to be
completed. Task E can only start upon
completion of Task C. Whereas starting task
F needs the completion of both the tasks D
and E. Finally, starting task G needed, task F
to be completed. The processing times for
tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9,
1.0, 1.2, 1.8, are 4.7 minutes respectively.
Applying the most following tasks rule for
balancing the assembly line, with ties broken
according to longest task time first. What is
the efficiency in percentage?
а.
None is the correct answer
b. 20.83
С.…
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day
in order to meet forecasted demand of 70 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C,
D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed.
Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start
upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G
needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7
minutes respectively. How many minimum numbers of workstations are needed? Select one
.a
3
b
2.
.C
4.
.d
.e
None is the correct answer
The correct an
answer is 3
arrow_forward
A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet
forecasted demand of 70 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A
does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also,
starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of
both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9,
1.0, 1.2, 1.8, and 4.7 minutes respectively. What should be the cycle time in minutes?
O a. 7.5
O b. 4.4
c.
None is the correct answer
O d. 6.86
O e. 4.7
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
BUSN 11 Introduction to Business Student Edition
Business
ISBN:9781337407137
Author:Kelly
Publisher:Cengage Learning
Essentials of Business Communication (MindTap Cou...
Business
ISBN:9781337386494
Author:Mary Ellen Guffey, Dana Loewy
Publisher:Cengage Learning
Accounting Information Systems (14th Edition)
Business
ISBN:9780134474021
Author:Marshall B. Romney, Paul J. Steinbart
Publisher:PEARSON
International Business: Competing in the Global M...
Business
ISBN:9781259929441
Author:Charles W. L. Hill Dr, G. Tomas M. Hult
Publisher:McGraw-Hill Education
Related Questions
- A manufacturer is designing a product layout for a new product productionIt plans to use a production line for 8 hours per day in order to meet forecasted demand of 70 units per day. The product requires 7 tasks in total. These tasks are namelyABC, D, E, F, and Grespectively. Task A does not have any predecessor to startTo start Task B.it requires Task A to be completedStarting tasks needs, the task B to be completed. Also, starting task Dneeded task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed task Fto be completed. The processing times for tasks, ABC, D. E. and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8 and 4.7 minutes respectively. What should be the cycle time in minutes? a 4.7 b. None is the correct answer Oc 7.5 d6.86 e.arrow_forwardAbout Assignment Short-Term Scheduling The following table shows the contribution of benefits provided by 5 employees A, B, C, and D in handling 5 types of work I, II, III, IV, and V. Work Employee A B C D I 10 12 10 8 II 14 10 9 15 III 8 8 7 9 IV 13 15 8 16 V 10 13 14 11 Determine the maximum contribution that can be obtained using the Assignment Modelsarrow_forwardFlorida Southwestern State College has decided to implement a new registration system that will allow students to register online as well as in person. As an IT manager, you decide to set up a JAD session to help define the requirements for a new system. The FSW organization is fairly typical, with an administrative staff that includes a registrar, student support and service team, a business office, an IT group, and a number of academic departments. Using this information, you start work on a plan to carry out the JAD session. Who would you invite to the session, and why? What would be your agenda for the session, and what would take place at each stage of the session?arrow_forward
- Design a SWOT analysis for a IT help desk center. This help desk has 3 tiers: Tier 1: Lower level, can help with small issues on a computer (logging in, website issues). Tier 2: Physical repairs, can help with troubleshooting hardware problems or any problem Tier 1 could not solve. Will replace broken components. Tier 3: Administration, this tier has all the bosses that see over Tier 2 and Tier 1. They will help with Tier 2 if needed, mostly used in disaster scenarios.arrow_forwardUsed : Call center optimization as project , please give Citation if possible are required to identify and select a project that you have worked on, whether as a project manager or project team member. If you have not worked on a project before or you are unable to select a suitable project based on your work experiences, you should select a project that you know about and have sufficient access to the project’s information. Remember, the project that you select (the case) should have already been completed/finished, implemented, or executed. If you decide to select a project outside of your work experiences, there are several completed projects in your local community, your country, the region, or internationally that you may be able to use as a case for this assignment. There are no restrictions on the type of project that you select or decide to work with, however please be deliberate in your selection or when choosing a project to work with. You should avoid selecting a project…arrow_forwardA manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 80 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one: a. None is the correct answer b. 5 C. 6 d. 3 e. 1arrow_forward
- A nursing home must schedule nurses in a manner that balances providing adequate patient care while keeping costs down. From historical records, administrators can project the minimum number of nurses to have on hand during each day/time slot. This data is shown below. Shift Time Slot Minimum number of nurses needed 1 12 am-4 10 2 4 am-8 6 3 8 am-12 8 4 12 pm-4 12 5 4 pm-8 10 6 8 pm-12 14 Nurses must start work at the beginning of one of the four-hour shifts (starting as early as 12 am midnight or as late as 8pm evening) and work for eight hours. Nurses who begin working at 8 pm will work until 4 am the next morning. Formulate and solve the nurse-scheduling problem so as to minimize excess stagging while satisfying minimum staffing requrements. What is the value of total excess staffing?arrow_forwardSolve this assignment problem in Excel to find the lowest cost solution and answer the following questions: 1.Which employee is assigned to job 1? Employee C (or) Employee B (or) Employee A 2. Which employee is assigned to job 2? Employee C (or) Employee B (or) Employee A 3.Which employee is assigned to job 3? Employee C (or) Employee B (or) Employee A 4.What is the minimum cost to complete all three jobs?arrow_forwardUse the “A1_Excel_Template” Excel file to solve the questions below. Submit two files for this assignment: The completed word file (use this file to compile your solutions) with your answers including Excel screenshots. The Excel file with your answers. Specific Instructions: The “A1_Excel_Template” file contains the data sets on separate worksheets (tabs) labeled as “ Problem 1_DHL”, “Problem 2_Patients”, and so on. Use these datasets to complete problems below. Save the solved problems in A1_Excel_Template as A1_Last Name. For Instance, Use this word file to compile your answers. You need to take a screenshot of your Excel answers ( e.g., frequency table, bar chart, pie chart, .. etc.) and paste it under appropriate question in this word file. Save the A1_ word file as A1_Last Name. For Instance, A1_Kochan. Submit the excel file and this word file that contain your answers.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- BUSN 11 Introduction to Business Student EditionBusinessISBN:9781337407137Author:KellyPublisher:Cengage LearningEssentials of Business Communication (MindTap Cou...BusinessISBN:9781337386494Author:Mary Ellen Guffey, Dana LoewyPublisher:Cengage LearningAccounting Information Systems (14th Edition)BusinessISBN:9780134474021Author:Marshall B. Romney, Paul J. SteinbartPublisher:PEARSON
- International Business: Competing in the Global M...BusinessISBN:9781259929441Author:Charles W. L. Hill Dr, G. Tomas M. HultPublisher:McGraw-Hill Education
BUSN 11 Introduction to Business Student Edition
Business
ISBN:9781337407137
Author:Kelly
Publisher:Cengage Learning
Essentials of Business Communication (MindTap Cou...
Business
ISBN:9781337386494
Author:Mary Ellen Guffey, Dana Loewy
Publisher:Cengage Learning
Accounting Information Systems (14th Edition)
Business
ISBN:9780134474021
Author:Marshall B. Romney, Paul J. Steinbart
Publisher:PEARSON
International Business: Competing in the Global M...
Business
ISBN:9781259929441
Author:Charles W. L. Hill Dr, G. Tomas M. Hult
Publisher:McGraw-Hill Education