Earned Value Analysis

.docx

School

Centennial College *

*We aren’t endorsed by this school

Course

701002

Subject

Business

Date

Apr 3, 2024

Type

docx

Pages

5

Uploaded by GrandFogWombat39

Report
Earned Value Analysis Section 002 Margi Trivedi (4915 / mtrive24@my.centennialcollege.ca ) Centennial College PMGT 702: Project Scheduling Management Anthony Jagdeo March 27 , 2024
PART-1 In month 9, the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. EV = Earned Value ($2,100) PV = Planned Value ($2,400) AC = Actual Cost ($2,000) Calculate SV: SV = $2,100 (EV) - $2,400 (PV) SV = -$300 The negative value (-$300) indicates the project is behind schedule by $300 in month 9. Calculate CV: CV = $2,100 (EV) - $2,000 (AC) CV = $100  The positive value$100 indicates that in the 9th month, the project was $100 under budget . On day 51, a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51? Earned Value (EV):  $600 Actual Cost (AC):  $650 Planned Cost (PC):  $560 1. Schedule Variance (SV): SV = EV - PC SV = $600 - $560 SV = $40 The positive SV of $40 indicates the project is   ahead of schedule   by $40 on day 51.   2. Cost Variance (CV): CV = EV - AC CV = $600 - $650 CV = -$50 The negative CV of -$50 indicates the project is   over budget   by $50 on day 51. 3. Cost Performance Index (CPI): CPI = EV / AC CPI = $600 / $650 CPI = 0.92 A CPI of 0.92 is less than 1, which suggests the project is spending more than planned to achieve the completed work.
Given the following project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8. From the data you have collected and computed for periods 4 and 8, what information are you prepared to tell the customer about the status of the project at the end of period 8? End of Period 4 Task Actual % complete EV AC PV CV SV A Finished 400 300 400 100 0 B 50% 1200 1000 800 200 400 C 33% 500 500 600 0 -100 D 0% 0 0 0 0 0 E 0% 0 0 0 0 0 Cumulative Total 2100 1800 1800 300 300 End of Period 8 Task Actual % complete EV AC PV CV SV A Finished 400 300 400 100 0 B Finished 2400 2200 2400 200 0 C Finished 1500 1500 1500 0 0 D 25% 400 300 0 100 400 E 33% 300 300 300 0 0 F 0% 0 0 0 0 0 Cumulative Total 5000 4600 4600 400 400
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help