M1_Activity_2
.docx
keyboard_arrow_up
School
Royal Melbourne Institute of Technology *
*We aren’t endorsed by this school
Course
C5256
Subject
Civil Engineering
Date
Jan 9, 2024
Type
docx
Pages
6
Uploaded by MinisterIceFly32
CPC40120/CPC50220 Module 1 – Assessment 2.8
Assessment Cover Sheet
The Cover Sheet must be completed before you start your assessment.
Student Surname
Student Given Name
Qualification
CPCC40120/CPC50220 CertIV/Diploma of Building and Construction (Building)
Module of Study
Module 1
Assessment Name
Activity 2.8 – Calculate Quantities
Trainer Name
Student Statement
Plagiarism is a form of cheating. It is taking and using someone else’s thoughts or writings and representing them as your own. Plagiarism is a serious act and may result in a participant’s exclusion from a Unit of Competency or a course. This in turn may require for students to pay to re-complete the module or course at a later date. The following list outlines some of the activities for which a participant can be accused of plagiarism:
1.
Presenting any work by another individual as one’s own unintentionally
2.
Handing in assessments markedly similar to or copied from another student
3.
Presenting the work of another individual or group as their own work.
4.
Handing up assessments without the adequate acknowledgement of sources used, including assessments taken totally or in part from the internet.
Many of the workbook activities are ‘open book’ yet should still be conducted under test conditions without consultation with other students. If you are unsure of any assessment requirements you should check with your Trainer / Assessor.
By submitting this assessment electronically you declare that all work for assessment tasks submitted for this assessment is your own with no part of any assessment being copied/plagiarised from another person’s work, except where authorised and listed / referenced.
© House of Learning Pty Ltd
M1 – Activity 2.8 - Answer Sheet – V1.0| 08.07.2021 | Page 1 of 6
CPC40120/CPC50220 Module 1 – Assessment 2.8
Scenario - Identify and produce estimated building
and construction costs in the workplace
This scenario covers Task 2.8 Calculate Quantities and Task 2.9 – Produce Cost Estimates
This assessment is a real-work project where you have responsibilities for producing estimated costs for labour, materials, overheads and on-costs on various residential and commercial construction projects within their scope of work as a trade contractor or builder. For Tasks 2.8 and 2.9, refer to Project Portfolio for project no. 20361 – Retail Complex
to determine the quantities of labour materials, plant and equipment for the building, and develop estimates for the construction of the building. The developer who is developing the project 20361 Retail Complex has asked you for a price for part of the project. They want a price for the ground floor Cafe and the first floor residential unit only
for the project. Grid at
Grid B-C, 18-20.
The inclusions and exclusions are detailed below.
Inclusions:
●
Structural block including to both levels of the structure and including along Grid 18
●
Wall framing for the ground floor of the café
●
Rear Entry door to the unit on the ground floor
●
Floor system between the ground floor and first floor
●
Stairs to the ground to first floor
●
Internal and external walls on the first floor.
●
Windows and doors on the first floor
●
Roof framing system on the first floor
●
Roof Covering system on the first floor
●
External finishes to the first floor
●
Internal Lining
●
Internal Fix
●
Internal Finishes
●
Electrical
●
Cabinetry
●
Waterproofing to the terrace
●
Tiling to the terrace
●
Handrails
Exclusions:
© House of Learning Pty Ltd
M1 – Activity 2.8 - Answer Sheet – V1.0| 08.07.2021 | Page 2 of 6
CPC40120/CPC50220 Module 1 – Assessment 2.8
●
Shop fitting to front elevation of the ground floor Café
●
Fit out to the ground floor café
●
Plumbing
●
The ground slab for the shop and Café.
●
North and south walls to shop 4 adjacent to the café.
The Quote List for Project no. 20361 contains a number of supplier prices that have been attained for the
project. These prices should be used in providing the estimate for the work.
You may refer to BAA Constructions Rates Schedules, or you may choose to research current prices for the various items.
The estimated time to complete the work quoted is 14 weeks from commencement to hand-over.
You can use the BAA Project Estimating Template (Excel Workbook) to collate the information and calculate the price or you can use any other electronic estimating system you would prefer to use.
The project will be allocated to a Supervisor who is a wage earning employee of the company. The supervisor has a company car and does not get a travel allowance. The supervisor works 48 hours per week and will have their time equally divided between four (4) projects including this project.
The project will also use a labourer who is also a wage earner but gets paid a travelling allowance as they
are not provided a vehicle.
You can use the hourly rate template to determine this rate. These overhead costs will need to be calculated and included the price.
What do I need to do?
© House of Learning Pty Ltd
M1 – Activity 2.8 - Answer Sheet – V1.0| 08.07.2021 | Page 3 of 6
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
3. (1) Define critical path, ES, EF, LS, LF, dummy activity and slack.
(2) Cables By Us is bringing a new product on line to be manufactured in their current facility in
existing space. The owners have identified 11 activities and their precedence relationships.
(a) Draw the network diagram of this project
(b) Calculate the project completion time
(c) Identify the critical path
日
OF 5
SONY
arrow_forward
ESSAY
Instruction: Answer the essay questions. Write your answers in a short bond paper (8.5
in. by 11 in.). Use the attached format in this module.
1. What are the different professional responsibilities of a Civil Engineer?
2. Why do we need to know the obligations and liabilities of both the Civil Engineer
and the Client?
3. When do the engineering services get suspended or terminated?
4. How should a dispute between the Civil Engineer and the Client be settled?
5. What are the typical services offered by Civil Engineers or civil engineering firms?
6. How is a Civil Engineer selected for a particular service or project?
7. What are the requirements for foreign civil engineers to practice their profession in
the Philippines?
arrow_forward
What are the practical constraint?
arrow_forward
One-page resume that can be used when you apply for your dream jobs after 3-4 years when you graduate in Civil Engineering.
arrow_forward
Quality Engineering question
A Production Engineer working in Company A wants to maintain a Standard Operation Procedure (SOP) for the mobile phone assembly line and also monitor status of production (traveler). Please advise him the necessary documentation to do it and help him regarding the type of information the document and records should contain.
Please answer in your own words. please don't use handwriting. Thank you
arrow_forward
Q2: Suppose a construction site is 35km away from the market area, Apply the knowledge of construction management which of the two theories I.e. “The just-in-time theory” or “The inventory buffer theory”, will you prefer for materials management and why?
Civil Engineering
Subject= Construction Management
Answer in word format
arrow_forward
Part 1: Take-home and Viva activity related to topics covered in LO1.
|You work as a mechanical software engineer in a mechanical company which provides modelling and
design services for different types of mechanical applications. Your main tasks are to analyze and assess
different designs and obtain optimal solutions prior to any prototyping or manufacturing step. Your
direct manager assigned you to work on specific tasks for different running projects.
Project 1:
Simply supported beams are usually used in structures due to their high stability and performance in resisting
shear stress and bending moment, they are applied in variety of applications such as steel-frame used for
advertisement cars' chassis and bridges. Your role in a structure design company is to analyze and design the
bridge based on simply supported beam theory. Your manager asked you to calculate the distribution of shear
force, bending moment and stress đue to bending for bridge modeled as simply supported beam…
arrow_forward
OSHA Subject ( give sample answer ) 5 lines
arrow_forward
Assume that you are a hotel receptionist, and you ask each of the following to fill out a guest information form. Write on the table below what you are going to say to each person as guest.
arrow_forward
Please give proctor test results and graph.
arrow_forward
See attached.
arrow_forward
Instructions: Write your solution and answer on a
paper. Put your name and
LBP/SBP/newsprint/yellow
section on the upper left part of the paper; your solutions
should be written from the upper to the lower part, and
from the left to the right side, of your paper. Enclosed your
answer in a box. Scan/take pictures of your solution papers
and compile them in one (1) file (pdf).
Determine the resultant of B and C if the resultant of A and
B is 100 kN directed along the z-axis.
arrow_forward
from book Construction Contracts Keith Collier 3rd
q1) a. Explain the statement: Documents for construction contracts are not always the same as contract documents.
b. In the light of your explanation, list all the classes of documents for contracts, identifying the contract documents.
q2) Explain the proper purpose and procedure for a “letter of intent” issued by an owner, and who should draft or give advice concerning it.
please don't slove as handwriting
arrow_forward
The introduction section of a proposal includes:
Select one:
o a. Report organization
b. All points mentioned
c. Statement of the problem
d. The background
arrow_forward
Scenario 1 – applies to the measurement task and the application of
measurement principles questions in CMA1
You are the consultant Quantity Surveyor (QS) working for a leading provider of sustainable design
and construction solutions and you have been assigned to work with an inexperienced client on a
large construction project. The traditionally procured project is currently at the Technical Design
Stage (RIBA 2020) and your manager has asked you to perform the following tasks.
The PDF drawings listed below are available on the VLE in Week 8: Assignment 1 preparation and
are included to develop measurement skills only.
• D10104 Ground floor plan 2024
• D10115 Section AA 2024.
Following traditional measurement conventions and using a Standard Method of Measurement
(SMM), take off quantities for selected superstructure items.
• External cavity wall: Do not Measure the Porch
o The external half brick outer skin
o Forming 100mm cavity and 50mm cavity insulation
o Block wall inner skin.
•…
arrow_forward
What is the project completion time?
a. 14 days
b. 12 days
c. 15 days
d. 13 days
When will fund raising activity end?
a. April 19
b. April 16
c. April 15
d. April 18
When will fund raising activity start?
a. April 15
b. April 13
c. April 14
d. April 18
arrow_forward
Directions: You are an architect in a construction company. You are tasked to build 3 circular water tanks
for a 3- start hotel. You have to design the specifications of the water tanks, specifically the diameters and
length of the tanks that could hold 10000 m2, 9000 m², and 8000 m²of water. You are required to write a
proposal to the company board in two weeks. The board would like to see the concept used; it's practically,
accuracy of computation and the organization of the report.
arrow_forward
Answer remaining part of the question
arrow_forward
1- Provide a brief response for each of the below case studies
2-State the code of fundamental canons of ethics, rules of practice and professional obligation.
3-write a brief conclusion for each case
CASE 1
Engineer A is a recently hired software engineer recruited from college by HyTechCo, a global software company. As part of his first assignment, Engineer A’s supervisor, Engineer B, requests that he write software to provide security for e-mailed documents within HyTechCo. After completing the project, Engineer A learns on an IT industry news Web site about an individual with another company who had made similar software available to overseas clients and was being investigated by the government because of U.S. laws that require that such software not be sent overseas because of national security concerns. Engineer A learns that the software he developed for HyTechCo has been sent overseas by HyTechCo’s IT department for use by HyTechCo’s offices abroad. Engineer A informs Engineer…
arrow_forward
0% plagiarism write it own your own words.
Please rejecting this question it is not an essay.
Question: briefly describe the construction sector in Oman.
arrow_forward
Answer Problem 2. Follow the same instructions above.
arrow_forward
I just want the name of the source that contains a question identical to this question sent
arrow_forward
Assume that you are a hotel receptionist, and you ask each of the following to fill out a guest information
form. Write on the table below what you are going to say to each person as guest.
GUESTS
1. an angry old man
2. a socialite woman
3. a Chinese national who does
not understand English
language
4. a person with hearing
disability
5. a no-read-no-write lady
WHAT ARE YOU GOING TO SAY?
2. Discuss the importance of nonverbal communication in the communication
process. When does it become a disadvantage among people from different
cultures?
3. In a workplace, do we have to adapt the culture of people from different
cultures in order to become an effective communicator? Explain your answer.
arrow_forward
Pls. Answer it completely
arrow_forward
Question 48
schedule is a schedule in which the resources for a project are assigned to activities so the activities can be closely monitored.
O resource-loaded
O time-loaded
A
look-ahead
O preliminary
amazon
Bcer
F12
Scr Lk
Artêtdéf
PrtSclimpréc
SysRg/Syst.
F4
F5
F6
F7
F8
F9
F10
F11
Bre
VA
arrow_forward
What are the major ITER buildings?
Select one:
A.Tokamak Building
B.Radio Frequency Building
C.Assembly Building
D.All of the above
arrow_forward
Task
A. High Level Analysis
B. Selection of Hardware Platform
C. Installation and Commissioning of hardware
D. Detailed Analysis of core modules
E. Detailed Analysis of supporting Modules
Programming of core modules
F.
G. Programming of supporting Modules
H. Quality Assurance of core modules
1. Quality Assurance of supporting Modules
J. Core module training
K. Development and QA of accounting Report
L. Development and QA of Management reporting
M. Development of Management Information System
N. Detailed Training
Duration Times are in days
5 days work per week (Saturdays and Sundays are day-off)
Create a Gantt Chart starting November 28, 2022.
Duration Prerequisite
1
1
2
2
2
2
3
1
1
1
1
1
1
1
A
B
A
D
D
E
F
G
C, H
E
E
L
I, J, K, M
arrow_forward
One-page resume that can be apply jobs for civil engineering after 3-4 years when you graduate in Civil Engineering
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Related Questions
- 3. (1) Define critical path, ES, EF, LS, LF, dummy activity and slack. (2) Cables By Us is bringing a new product on line to be manufactured in their current facility in existing space. The owners have identified 11 activities and their precedence relationships. (a) Draw the network diagram of this project (b) Calculate the project completion time (c) Identify the critical path 日 OF 5 SONYarrow_forwardESSAY Instruction: Answer the essay questions. Write your answers in a short bond paper (8.5 in. by 11 in.). Use the attached format in this module. 1. What are the different professional responsibilities of a Civil Engineer? 2. Why do we need to know the obligations and liabilities of both the Civil Engineer and the Client? 3. When do the engineering services get suspended or terminated? 4. How should a dispute between the Civil Engineer and the Client be settled? 5. What are the typical services offered by Civil Engineers or civil engineering firms? 6. How is a Civil Engineer selected for a particular service or project? 7. What are the requirements for foreign civil engineers to practice their profession in the Philippines?arrow_forwardWhat are the practical constraint?arrow_forward
- One-page resume that can be used when you apply for your dream jobs after 3-4 years when you graduate in Civil Engineering.arrow_forwardQuality Engineering question A Production Engineer working in Company A wants to maintain a Standard Operation Procedure (SOP) for the mobile phone assembly line and also monitor status of production (traveler). Please advise him the necessary documentation to do it and help him regarding the type of information the document and records should contain. Please answer in your own words. please don't use handwriting. Thank youarrow_forwardQ2: Suppose a construction site is 35km away from the market area, Apply the knowledge of construction management which of the two theories I.e. “The just-in-time theory” or “The inventory buffer theory”, will you prefer for materials management and why? Civil Engineering Subject= Construction Management Answer in word formatarrow_forward
- Part 1: Take-home and Viva activity related to topics covered in LO1. |You work as a mechanical software engineer in a mechanical company which provides modelling and design services for different types of mechanical applications. Your main tasks are to analyze and assess different designs and obtain optimal solutions prior to any prototyping or manufacturing step. Your direct manager assigned you to work on specific tasks for different running projects. Project 1: Simply supported beams are usually used in structures due to their high stability and performance in resisting shear stress and bending moment, they are applied in variety of applications such as steel-frame used for advertisement cars' chassis and bridges. Your role in a structure design company is to analyze and design the bridge based on simply supported beam theory. Your manager asked you to calculate the distribution of shear force, bending moment and stress đue to bending for bridge modeled as simply supported beam…arrow_forwardOSHA Subject ( give sample answer ) 5 linesarrow_forwardAssume that you are a hotel receptionist, and you ask each of the following to fill out a guest information form. Write on the table below what you are going to say to each person as guest.arrow_forward
- Please give proctor test results and graph.arrow_forwardSee attached.arrow_forwardInstructions: Write your solution and answer on a paper. Put your name and LBP/SBP/newsprint/yellow section on the upper left part of the paper; your solutions should be written from the upper to the lower part, and from the left to the right side, of your paper. Enclosed your answer in a box. Scan/take pictures of your solution papers and compile them in one (1) file (pdf). Determine the resultant of B and C if the resultant of A and B is 100 kN directed along the z-axis.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Structural Analysis (10th Edition)Civil EngineeringISBN:9780134610672Author:Russell C. HibbelerPublisher:PEARSONPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning
- Fundamentals of Structural AnalysisCivil EngineeringISBN:9780073398006Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel LanningPublisher:McGraw-Hill EducationTraffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning