Items
#
Items
Correct Answer
Your Answer
Result
1
All of the following are acronyms for ...ge control board except for which one?
C
C
Correct
2
You are a project manager for Star Lig...of the following tools and techniques?
C
C
Correct
3
You are holding a regularly scheduled ...ding status meetings except which one?
A
A
Correct
4
Understanding the Control Procurements process tools
Incorrect
5
You are a project manager for Star Lig...e following is true regarding the CCB?
C
C
Correct
6
Understanding the Monitor Communications process inputs
Correct
7
You are working on a project and disco...the following actions should you take?
C
C
Correct
8
Understanding Change Control concerns
Incorrect
9
All of the following are activities of...anagement system except for which one?
A
A
Correct
10
Which system centrally manages approve...s or the project management processes?
D
B
Incorrect
11
All of the following are tools and tec...mmunications process except which one?
A
A
Correct
12
You are a project manager for Bluebird...all of the following except which one?
B
B
Correct