6006
.pdf
keyboard_arrow_up
School
Fanshawe College *
*We aren’t endorsed by this school
Course
6003
Subject
Industrial Engineering
Date
Dec 6, 2023
Type
Pages
15
Uploaded by UltraDolphin3479
Question
29
0
I
0.
625
points
•
The relationship
of
the
owner
/engineer's resident
project
representative
or
inspector
to
the
contractor
should
be
which
of
the
following:
A
firm
but
amiable and cordial
member
of
the
construction
team.
A technical policeman
to
insist
upon
rigid adherence
to
all orders and
project
documents
provisions.
• A
firm
adversary
of
the
contractor
to
assure
that
there
will
be
no
attempt
to
"g
et
by"
with
something.
Quite
friendly;
meet
socially occasionally.
Question
30
An
existing soils
report
should
be
included
as
part
of
the
contract
documents.
True
False
Que
stion
31
0
I
0.
625
points
0
I
0.625
points
For a
public
works
project, changes may
not
be
made
to
any
of
the
documents
during
which
of
the
fo
llowing
phases?
After
bid
opening,
but
before
award
of
the
contract.
•
Before
opening
of
bids,
but
after
advertising
for
bids.
After
bid
opening,
but
before
signing
of
the
agreement
After
award
of
the
contract
,
but
before
signing
the
agreement.
Question
32
0.625
I
0.
625
points
•
Question
14
0.625
I
0.625
points
If a discrepancy
is
discovered which makes literal i
nterpretation
of
the
plans and specifications impossible,
the
owner
/engineer's
resident
project
representative
or
inspector should:
tell the
contractor
to
"cut-to-fit"
and "beat-to-shape" until
everything
fits
OK.
•
telephone
the
project
manager
or
engineer responsible
for
the
plans and specifications
for
instructions
before
proceeding
with
the
work.
work
out
a solution
to
the
problem
by
yourself
that
will
allow
a field adaptation
of
the
design
error
or
omission.
make a deal
with
the
contractor
for
a
trade-off
in exchange
for
cor
r
ecting
the
work.
Question
15
0.625
I
0.625
points
It
is
permissible
for
the
owner's
representative
to
issue instructions
or
orders
to
a subcontractor as long
as
they
are directed
to
a
management representative
of
that
subcontracto
r.
True
•
Fa
lse
Question
16
0.625
I
0.625
points
Under
the
partnering concept, all differences are intended
to
be resolved
at
the
lowest
management level - preferably
at
the
project
site.
• True
False
Question
17
0.625
I
0.625
points
•
Question
1
0.
625
I
0.
625
points
-
If
requested
by
the contractor,
the
Resident Project Representative
or
inspector may
offer
suggestions
as
to
how
to
do
the
work.
True
•
False
Que
stion
2
Photographs should be taken
on
the
project
site:
occasionally
during
construction.
only
when
a problem occurs
•
regularly, showing all principal features, problems, and progress made
to
date.
not
at
all
Que
s
tion
3
A Change
Order
can be issued any
time
after
execution
of
the
Agreement.
• Tr
ue
False
Qu
e
stion
4
0.625
I
0.
625
point
s
0.
625
I
0.
625
points
0.
625
I
0.625
points
On all construction
work
where
the
owner
/ engineer has assigned an inspector
or
resident
project
representative
to
inspect
the
work,
the
inspector
or
resident
project
representative should
do
which
of
the
following:
•
Inspect t
he
work
during
construction and
notify
the
contractor
of
any
non-conforming
items
of
work
as
soon as
they
are
Question 1
Describe time-limited and resource-limited planning.
- The process
of
developing a plan
that
must
be completed
within
a specific
time
frame is referred
to
as
time-limited
planning. This
type
of
planning is commonly used
in
project management,
where
deadlines are critical
to
project
Answer: success. - The process
of
creating a plan
that
must
be completed
with
a
limited
amount
of
resources,
on
the
other
hand, is referred
to
as
resource-limited planning. This
type
of
planning is
frequently
used
when
there are budget
constraints
or
a
limited
number
of
people available to complete
the
project.
Question
2
The appropriate sequence
for
developing a
construction
plan is
0
I
1 point
)(
(Instructor
Marked)
1
/
1
point
compute and chart
the
duration
of
all WBS activities. develop
the
network
diagram. develop
the
WBS.
put
the
WBS
activities
in
sequence
✓
•
develop
the
WBS,
put
the
WBS activities
in
sequence. compute and
chart
the
duration
of
all WBS activities, develop
the
network
diagram
develop
the
WBS,
compute
and chart
the
duration
of
all WBS activities,
put
the
WBS activities in sequence, develop
the
network
Question
31
0
I
0.625
points
For a public
works
project, changes may
not
be made
to
any
of
the
documents during
which
of
the
following
phases?
After
bid opening,
but
before
award
of
the
contract.
•
B
efore
opening
of
bids,
but
after
advertising
for
bids.
After
bid opening,
but
before
signing
of
t
he
agreement.
After
award
of
the
contract,
but
before
signing
the
agreement.
Question
32
0.625
I
0.625
points
An
inspector should always
try
to
get
the
contractor
to
give
the
owner
the
highest
quality
materials and workmanship, regardless
of
what
the
specifications call for.
Tr
ue
False
Question
22
0.
625
I
0.
625
points
An
inspector's
diary
may
be in loose-leaf
form
as
long
as
the pages are numbered.
True
•
False
Question
23
0.
625
I
0.
625
points
It
is possible,
under
contracts
involving
separate inspections
by
other
agencies having
jurisdiction
,
to
maintain
the
one-to-one
relationship
with
the
contractor.
•
True
False
Question
24
Carefully
documented
project
records should
be
kept
in
the
form
of:
daily
construction
progress
reports
only.
a
monthly
summary report,
but
no
other
documentation
is necessary.
bar
charts and S-curves only.
•
dai
ly
construction
progress
reports
and
daily
diaries.
Question
25
The Supplementary General
Conditions
can
be
used
to
modify
the
Agreement
Form.
0.
625
I
0.
625
points
0.
625
I
0.625
points
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help