Assignment #1_ Basic Energy and Project Economics Calculations

docx

School

Yorkville University *

*We aren’t endorsed by this school

Course

3503

Subject

Industrial Engineering

Date

Apr 3, 2024

Type

docx

Pages

7

Uploaded by 534056kp

Report
Question 1 1GJ=1*10^9 Joule 1 Joule = 1 watt * Hour 1Joule = (KW/1000) * (Hour/3600) 1Joule=2.7777* 10^-7 kWh 1GJ=1x10^-9x2.7777x10^-7 kWh 1GJ = 277.777kWh 1kWh = (1/277.777)GJ 500kWh = 500 (1/277.777) GJ Therefore, 500kWh = 1.8GJ Question 2 Given: P=12KW Run timings, from 8:00 a.m. to 8:00 p.m. With this we can say that, In 1 week, the motor works 5 days from Monday thrusday Friday. The motor works 12 hours * 5days = 60 hours in every week In 1 month the motor works = 60 * 4weeks = 240 Hours In 1 year the motor works = 240 hours * 12months = 2880 Hours The energy consumed annually by the motor is 12 KW = 2880H 34560 kWh of electricity does the motor consume annually
Question 3 Motor consumes an average of =12 KW (Given) ------> A Efficiency=75% Poutput = B Efficiency= A /B * 100% I solved for B B = Efficiency x A /100 B = (75x12KW)/100 B = 9 KW Question 4 a)KWh consumed daily : Sum of all powers consumed daily: 1+1+1+2+3+5+3+2+2+4+2+3+3+3+3+2+2= 42 KWh b) Peak demand is 5 KW at the 6th hour interval. Question 5 Plant operates at = 50 MW = 50 * 10 6 W Average loading = 75% Total number of hours in a year = 24 * 365= 8760 hours Loading percent = 75% So, Total loading time = 0.75 * 8760 = 6570 hours Total seconds = 6570 * 60 * 60 = 23652000
Total Kwh Does the plant supply to the grid = 50 * 10 6 *6570 * 60 * 60/1000 = 1182600 kwh Question 6 To calculate the average cost per kWh or MWh for the power produced by the natural gas power plant, we need to consider both the initial capital cost and the annual operating cost over the plant's estimated life. Given: Initial capital cost = $175,000,000 Annual operating cost = $20,000,000 Estimated plant life = 20 years Discount rate = 5% We can use the Net Present Value (NPV) formula to calculate the present value of the total cost over the plant's life, and then divide it by the total energy produced to find the average cost per kWh. NPV=175,000,000+20,000,000(1+0.05)1+20,000,000(1+0.05)2+...+20,000,000(1+0.05)20 NPV=175,000,000+ NPV≈175,000,000+19,047,619+18,140,103+...+5,134,000 NPV≈175,000,000+19,047,619+18,140,103+...+5,134,000 NPV≈175,000,000+19,047,619+18,140,103+...+5,134,000 NPV≈175,000,000+19,047,619+18,140,103+...+5,134,000 NPV≈303,515,189 NPV≈303,515,189 Now, we divide the NPV by the total energy produced over the plant's life to find the average cost per kWh: Average Cost per kWh=NPVTotal Energy Produced Average Cost per kWh= Total Energy Produced/NPV Average Cost per kWh=303,515,189328,500,000 Average Cost per kWh= 328,500,000 303,515,189 Average Cost per kWh≈$0.9244/��ℎ Average Cost per kWh≈$0.9244/kWh Therefore, the average cost per kWh for the power produced by the natural gas power plant is approximately $0.9244/kWh. Question 7
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
To determine the minimum number of 10kW solar panels needed to supply 50% of the company's energy, we first need to calculate the total energy consumption of the company and then determine how much energy needs to be supplied by solar panels. Given: Company's annual energy consumption = 2,000 MWh Energy produced by one 10kW solar panel per year = 12,000 kWh Desired percentage of energy supplied by solar panels = 50% First, convert the company's annual energy consumption from MWh to kWh: 2,000 MWh×1,000 kWh/MWh=2,000,000 kWh/year 2,000MWh×1,000kWh/MWh=2,000,000kWh/year Next, determine the total energy needed from solar panels to supply 50% of the company's energy: Total energy needed from solar panels=0.5×2,000,000 kWh/year=1,000,000 kWh/year Total energy needed from solar panels=0.5×2,000,000kWh/year=1,000,000kWh/year Now, calculate the number of 10kW solar panels needed to produce 1,000,000 kWh/year: Number of solar panels=Total energy neededEnergy produced by one solar panel Number of solar panels= Energy produced by one solar panel Total energy needed Number of solar panels=1,000,000 kWh/year12,000 kWh/year per panel Number of solar panels= 12,000kWh/year per panel 1,000,000kWh/year Number of solar panels=83.33 Number of solar panels=83.33 Since we can't have a fraction of a solar panel, we need to round up to the nearest whole number. Therefore, the minimum number of 10kW solar panels the company would need to install to supply 50% of its energy is 84 panels. Question 8 To calculate the simple payback for the solar panel project, we need to consider the initial investment and the annual savings generated by the solar panels. Given: Installed cost of each solar panel = $25,000 Cost of purchasing power from the utility = $0.14/kWh Negligible annual maintenance costs
Number of solar panels = 84 (as calculated) Energy produced by one 10kW solar panel per year = 12,000 kWh First, calculate the total installed cost of the solar panels: Total installed cost=Cost per panel×Number of panels Total installed cost=$25,000×84=$2,100,000 Next, calculate the annual savings generated by the solar panels: Annual savings=Total energy produced by all panels×Cost of purchasing power from the utility Annual savings=1,000,000kWh/year×$0.14/kWh=$140,000/year Now, calculate the simple payback period: Simple payback period=Total installed costAnnual savings Simple payback period= Annual savings Total installed cost Simple payback period=$2,100,000$140,000/year Simple payback period= $140,000/year $2,100,000 Simple payback period≈15 years Simple payback period≈15years Therefore, the simple payback for the solar panel project, assuming negligible annual maintenance costs, is approximately 15 years. Question 9 For Questions 7 and 8, we have already calculated the average cost per kWh for the power produced by the solar panel system. We'll reuse the calculations from those questions: Average cost per kWh for solar panel system = $0.14/kWh Now, let's calculate the average cost per kWh for the power produced by the solar panel system over its estimated 20-year life span. Average cost per kWh=Total installed costTotal energy produced over 20 years Average cost per kWh= Total energy produced over 20 years Total installed cost Average cost per kWh=$2,100,00020 years×1,000,000 kWh/year Average cost per kWh= 20years×1,000,000kWh/year
$2,100,000 Average cost per kWh=$2,100,00020,000,000 kWh Average cost per kWh= 20,000,000kWh $2,100,000 Average cost per kWh=$0.105/kWh Question 10 To compare the average cost per MWh between the natural gas system and the solar panel system, we need to convert the cost per kWh to cost per MWh for both systems. For the natural gas system (Question 6): Average cost per kWh = $0.9244/kWh For the solar panel system: Average cost per MWh for solar panel system=$0.105/MWh Now, we can compare the average cost per MWh between the natural gas system and the solar panel system: Natural Gas System: $0.9244/MWh Solar Panel System: $0.105/MWh Comparing the two, we see that the natural gas system has a significantly higher average cost per MWh compared to the solar panel system. Potential Solutions to Improve Solar Panel Project Economics: Increase Energy Efficiency: Implementing energy efficiency measures within the company's operations can reduce overall energy consumption, thereby decreasing the amount of energy required to be generated by the solar panels. This would lead to lower costs and potentially shorter payback periods. Utilize Incentives and Rebates: Governments and utility companies often offer incentives, rebates, or tax credits for renewable energy projects like solar panel
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
installations. Taking advantage of these incentives can significantly reduce the upfront costs and improve the financial viability of the project. Explore Financing Options: Financing options such as loans, leases, or power purchase agreements (PPAs) can help spread out the initial investment cost over time, making the project more financially feasible. PPAs, in particular, allow companies to purchase solar power at a predetermined rate, often lower than utility rates, without bearing the upfront costs of equipment installation. Optimize Solar Panel Placement: Ensuring optimal placement and orientation of solar panels can maximize energy generation and efficiency, thus improving the overall economic performance of the project. This may involve conducting a thorough site analysis and considering factors such as shading, roof angle, and sun exposure.