CMGT 3320 - Principles of Construction Management
Homework #1 - Project Delivery System – Chapter 1
10 points
Save this file on your computer as CMGT 3320.HW#1.Your Last Name, answer the questions in RED under each question (be sure to note the page of the text where the info was found), and SEND the file to the digital drop box. Do not forget to send the file, if you just add it, I do not get it.
1.
What are the three principal concerns of a Resident Project Representative or an inspector with respect to his or her project during the construction phase?
The main focus is to get what was paid for, construction is done according to drawings, plans, specs, and all contract documents
2.
Ideally, a Resident Project Representative or an inspector should be under the direct management control of whom? CQC Representative
3.
Who should have the authority to make design changes in the field during construction?
Construction administration
4.
What type of organizational structure is best suited to fast-track construction?
Design build contract
5.
Under a CM contract, the CM firm’s responsibilities normally begin at which phase of construction? Preform contract administration and inspection. Some firms will assist with begging the conceptual phase, and continuing through the design phase before entering the construction phase.
6.
What type of relationships is intended to be established under a Partnering agreement? One-to-one
7.
What are the five steps necessary to set up a Partnering workshop?
Creation of a partnering character
development of an issue-resolution process
development of a joint evaluation process
discussion of individual roles and concerns
presentation of a facilitated workshop
8.
What is the 5 step process of initiating a project?
Advertise for bids
Open bids
Award contract
Sign agreement or “contract”
Issue notice to proceed