project management unit 1 test one

.pdf

School

Post University *

*We aren’t endorsed by this school

Course

213.30

Subject

Information Systems

Date

Dec 6, 2023

Type

pdf

Pages

18

Uploaded by BailiffArt10644

Report
1 21/23 that's 91% This Milestone has been retaken. 21 questions were answered correctly . 2 questions were answered incorrectly . Which of the following correctly describes the documentation of project risks? Low risks usually do not signifanctly impact a project. Medium risks must be watched closely by the project manager. High risks can become project killers if not mitigated. Most risks are closely monitored by the project sponsor. UNIT 1 — MILESTONE 1 21/23
CONCEPT Identifying Project Risks 2 CONCEPT Determining Project Outcomes Report an issue with this question Mila managed a project to develop a website for a restaurant. Which description below is an assumption, as opposed to a requirement? Report an issue with this question The restaurant owner needs the head chef to include a professional bio. The restaurant owner wants customers to make reservations via telephone. The restaurant owner wants a professional photographer to take pictures of his signature dishes. The restaurant owner thought customers would prefer using a website over a mobile app.
3 CONCEPT Project Manager Roles & Responsibilities 4 Which of the following is NOT true regarding the role of a project manager? Report an issue with this question Which of the following is included in a business case for a project? A project manager manages the expectations of all project stakeholders. A project manager must have expertise relevant to the assigned project. A project manager communicates both good and bad news to stakeholders. A project manager understands the need to maintain confidentiality.
CONCEPT Defining Project Rationale 5 Report an issue with this question Sean made sure the staff at a dry-cleaning business was trained to use some new, potentially hazardous equipment. He also had them sign off that they were aware of all the posted warning signs and had them read the safety manual. Which of the following is the probability of injuries occurring while using the equipment and the related impact on the employees? Onboarding instructions Risks Benefits Requirements Medium risk and high negative impact Low risk and high negative impact
CONCEPT Identifying Project Risks 6 CONCEPT Gathering Stakeholder Expectations: The Process Report an issue with this question What is the first step a project manager will take when defining the project scope? Medium risk and low negative impact High risk and high negative impact Design interview questions to ask the stakeholders Discuss the benefits of the project with stakeholders Convince stakeholders to support the project Identify stakeholders
7 CONCEPT Writing SMART Goals 8 Report an issue with this question Which of the following SMART goal components ensures the goal is focused and well-defined? Report an issue with this question Which of the following is an example of a change in time for the project Will managed to develop a film documentary on alligators in the Florida Everglades? Measurable Realistic Specific Action-oriented Will found errors in the research document created by his team.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help