A pharmaceutical company fills a drug which is in a powder form into a bottle. It has an automated process consisting of a filling machine and a sealing unit. After filling the bottle, it is automatically sealed with a metallic cap. To monitor the quality of the process, samples of size 5 are drawn periodically from the process and the quantity filled is measured. The table below has data on 12 such observations. Sample 1 2 3 4 5 1 9.21 8.87 8.71 9.08 9.34 2 9.06 8.97 9.13 8.46 8.85 3 9.35 8.95 9.20 9.03 8.44 4 9.21 8.71 9.05 9.35 8.87 5 9.01 9.17 9.21 9.05 9.53 6 8.74 8.35 8.50 9.06 8.89 7 9.21 9.05 9.00 8.78 9.23 8 9.15 9.20 9.23 9.15 9.06 9 8.98 8.81 8.90 9.13 9.05 10 9.03 9.10 9.26 9.44 8.48 11 9.49 9.05 9.12 8.88 8.93 12 8.95 9.10 9.02 9.04 8.96 (a) Establish the upper and lower control limits for the X bar chart and the R Chart (b) Construct a control chart and investigate if the process is in control Values for setting the control charts are A2 = 0.577, D3 = 0, D4 = 2.114

Glencoe Algebra 1, Student Edition, 9780079039897, 0079039898, 2018
18th Edition
ISBN:9780079039897
Author:Carter
Publisher:Carter
Chapter10: Statistics
Section10.1: Measures Of Center
Problem 9PPS
icon
Related questions
Topic Video
Question

A pharmaceutical company fills a drug which is in a powder form into a bottle. It has an automated
process consisting of a filling machine and a sealing unit. After filling the bottle, it is automatically
sealed with a metallic cap. To monitor the quality of the process, samples of size 5 are drawn
periodically from the process and the quantity filled is measured. The table below has data on 12
such observations.
Sample 1 2 3 4 5
1 9.21 8.87 8.71 9.08 9.34
2 9.06 8.97 9.13 8.46 8.85
3 9.35 8.95 9.20 9.03 8.44
4 9.21 8.71 9.05 9.35 8.87
5 9.01 9.17 9.21 9.05 9.53
6 8.74 8.35 8.50 9.06 8.89
7 9.21 9.05 9.00 8.78 9.23
8 9.15 9.20 9.23 9.15 9.06
9 8.98 8.81 8.90 9.13 9.05
10 9.03 9.10 9.26 9.44 8.48
11 9.49 9.05 9.12 8.88 8.93
12 8.95 9.10 9.02 9.04 8.96
(a) Establish the upper and lower control limits for the X bar chart and the R Chart
(b) Construct a control chart and investigate if the process is in control
Values for setting the control charts are A2 = 0.577, D3 = 0, D4 = 2.114

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 7 images

Blurred answer
Knowledge Booster
Hypothesis Tests and Confidence Intervals for Means
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, statistics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Glencoe Algebra 1, Student Edition, 9780079039897…
Glencoe Algebra 1, Student Edition, 9780079039897…
Algebra
ISBN:
9780079039897
Author:
Carter
Publisher:
McGraw Hill