1. Compute the most probable or mean time, t. Indicate your answers in the table above. 2. Construct the Network Diagram. Determine the Early Start and Early Finish of each of the activities. Determine the total duration of the project.
Q: The following table provides the information necessary to construct a project network diagram and…
A: Project crashing is a process which reduces the total duration using additional costs. Here, we can…
Q: scenarios of a project activities (tables given below) and their required times to be completed in…
A: In this question is about the critical path where we have to make a network diagram and have to show…
Q: Construct a network diagram for this project?
A: Find the Duration Calculation below:
Q: 1- Data for small project are given, determine the following 1- ES for Activity C. E. G. J 2- E.F…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Below is the first set of activities (Phase I) in constructing a new house, the respective time…
A:
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A: a. The network diagram for the project is:
Q: The Figure 1 below shows the activities on the nodes, while the table shows the normal time, crash…
A: There are two separate paths. The duration of the paths is: Start–A–B–F–End = 18 days…
Q: a. Construct the network. b. How long will it take to finish the project? c.. What is the critical…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: a. Draw the CPM Network b. What is the critical path c. What will the scheduled (earliest…
A: In the question, we have Activity Table data, this table data includes activity ID, Immediate…
Q: a. Draw the project network diagram. b. What completion date would you recommend?
A: Below is the solution:-
Q: Activity Description Preceded bDy Time (WKS) Feasibility Study Estimate production volumes Market…
A: i) the AOA format, the possible path activities would look like:
Q: a) Create an activity network diagram that shows the sequential logic the project tasks. b) Identify…
A: The critical path method (CPM) is a method for determining schedule flexibility and identifying…
Q: • Q1: Determine the critical path, the critical activities and the project completion time.…
A: A project network diagram is the visual representation of the project activities and their durations…
Q: a. Determine the expected activity completion times, te. b. Identify the critical path. c. What's…
A: The first four subparts (a), (b), (c), and (d) are answered below.
Q: Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern…
A: From the network diagram, The possible paths and their duration are: A-D-G-H = 3+3+1+3 = 10B-E-F =…
Q: Q:2 Draw AOA and AON network diagrams and gantt chart for the project, calculate TE for each…
A: Below is the solution:-
Q: 3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde…
A: 3.8) Given Activity Immediate Predecessor(s) Time(Days) A ______ 2 B ______ 5 C ______ 1…
Q: Consider the following data for a project to install a new server at the Northland Pines High…
A: a.
Q: 1. Construct the activity-on-node network. 2. Identify the critical path. 3. Compute the duration of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: The following information has been gathered for a project to install a new machine lathe at Diamond…
A: a.
Q: Ql: For activities shown in table below, find the new time of project after updating, if the project…
A:
Q: Consider the following data for a project to reorganize the office space at Platinum Financial…
A: a. The network diagram is as follows:
Q: [6 marks] Carefully draw an AON network diagram for the project, and perform both the forward and…
A: THE ANSWER IS AS BELOW:
Q: Consider the following data for a project to install a newserver at the Northland Pines High School:…
A: The critical path method, or critical path analysis, refers to an algorithm which is used for…
Q: a. Determine the expected time (t,) for each activity. 5. Identify the critical path(s) c. What is…
A: Answer is as below:
Q: a)Construct AON diagram for the following data. b) Identify path, path duration and critical path c)…
A: Below is the solution:-
Q: Using Microsoft Project, set up the network and determine the critical path for Phase 1 of the…
A: Given that, Activity Description Duration (days) 1 Building Road to the site 6 2 Materials…
Q: a) Construct a Gantt chart using MS Project 2016 b) Assuming the default 5-day workweek, calculate…
A: This question is related to the topic of Project Management and this topic falls under the…
Q: . CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL…
A: Activity-on-node is a therm related to project management. It directs to a precedence diagramming…
Q: oger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: The project network is the diagrammatic form in which project activities and their durations are…
Q: Consider the following data for a project to reorganize the office space at Platinum Financial…
A:
Q: Build a PERT Analysis for a 3-month project with 6 activities (A to F) and 5 nodes
A: The PERT Method (or Program Evaluation and Review Approach) is a standard network analysis…
Q: The following information has been gathered for a project to install a new machine lathe at Diamond…
A: a.
Q: a. Draw a network diagram and determine the expected project completion time b. What is the…
A: Below is the solution:-
Q: a) Develop a network diagram for the project. Identify the critical path. b) If the company would…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Draw the Network Diagram and determine the Critical Path and duration of the project (in days).…
A: Given data is
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: A. (5 points) Draw AON diagram of the project, including activity durations. B. (4 points) Based on…
A:
Q: Q3: Draw the network diagram and determine the critical path for the following project: Activity…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: The diagram in Figure was developed for the project launch of Kitty Condo, a new product in the…
A:
Q: Answered all given questions as below. Value for A and B will be determined by your unique id as per…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(a, b,…
Q: b) Provide a brief explanation of the main difference between a Work Breakdown Structure and Network…
A: A project network diagram is shown as a chart with a sequence of boxes and arrows.
Q: a. Draw the network diagram b. What is the critical path? c How many dayswill it take to complete…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Below matrix shows one of the important data used in project management, identify the name of the…
A: The matrix shown in the question is named as RACI Chart or RACI Matrix. The RACI Chart or RACI…
Q: The project manager of Good Public Relations gathered the data shown in Table 7.15 for a new…
A: Critical path method is one of the effective project scheduling technique in which project can be…
Q: Crash the project until no more crash can be performed How much it would cost The new critical…
A: Proect crashing is one of the techniques used in the calculation of the duration of the critical…
Q: Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern…
A: Project Evaluation and Review Technique (PERT) may be a technique utilized in project management…
Q: Q2. Consider the following data summarizing the details of a project involving 12 activities.…
A:
Q: 4. For each of the following network diagrams, determine both the critical path and the expected…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: a. Construct the project network b. Determine the critical path c. Find the completion time of the…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 7 images
how to determine tabulate the the Late Start and Late Finish of the project ?
- quetion 1 a)What is a burn-down chart? What purpose does it serve? b)Why should a project manager be concerned with monitoring a project’s progress? c) Describe how the SPI and CPI can be used to forecast the final cost of a project?Jabez Contractors installs network routers. Using the CPM method and in reference to the table provided comment on the expected completion time of the projectand identify the activities that neeD to be prioritised by the project manager. (Nodiagram is required) TABLE- PROJECT INSTALLATION Activity Predecessor optimistic Most Likely Pessismistic Estimated time A - 4 7 10 7 B - 2 9 10 8 C A,B 2 5 8 5 D C 16 19 28 20 E C 6 9 24 11 F E 1 7 13 7 G C 4 10 28 12 H D,F 2 5 14 6 I G 5 8 17 9 J H,I 2 5 8 5Follow up to previous question: 3) A company decides to plan a project, with activities, precedences and random duration statistics given in the following table: Activity Immediate Predecessors Duration Minimum (weeks) Duration Mode (weeks) Duration Maximum (weeks) A none 2 5 9 B A 1 6 8 C A 3 5 12 D B 2 4 12 E B, C 4 6 8 F B 6 7 8 G D, E 1 2 6 H F, G 4 6 16 Questions: 1) What method should be used? Compute the mean and variances for each activity and add them to the table above. 2)Draw the project network and label the arcs with the activity name. 3) Assuming that the critical path is AàBàP1àEàGàH, compute the probability that this path duration is between 28 weeks and 32 weeks. 4) Assuming that the critical path is AàBàP1àEàGàH, compute the number of weeks within which the project will be completed with probability 0.95.
- 3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: a) DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team. b) Find the critical path. c) What is the project completion time? • • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede: ACTIVITY DURATION (WEEKS) PRECEDES A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 — ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A — 2 B — 5 C — 1 D B…Draw a network diagram showing the linkage between these activities from start to finish. For the diagram, each activity should be labelled alphabetically ie. A, B, C… etc. PERT Formula: TE = (O + 4T + P) / 6 TE = Pert Expected Time Duration, O = Optimistic estimate, P = Pessimistic estimate, T = Most Likely (Typical) estimate Activity Predecessor Optimistic Most Likely Pessimistic Duration Duration in Weeks A — 2 3 4 B — 4 5 7 C B 1 2 3 D C & E 0.5 1 1.5 E B 0.5 1 1.5 F C 2 3 4 G F 2 3 4The project described in the following table has just begun. It is scheduled to be completed in 11 weeks.Use Table B1 and Table B2. Activity Estimated Time(weeks) Standard Deviation(wks.) 1-2 4 0.70 2-4 6 0.90 1-3 3 0.62 3-4 9 1.90 a. If you were the manager of this project, would you be concerned? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) because the probability of finishing on schedule is only about . b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) Probability Have worked this with various formulas and all come back wrong. Where am I making a mistake
- Critically assess and comment on the success of the project from the followingviewpoints aline with a project To enhance Sports development by providing assistance to sports clubs and teams in St. Catherine North Central by providing them with the necessary gears and equipment for whichever Sporting disciple that they may part-take in. a. Level or degree of alignment of end results and outcomes to the organization’sstrategic goals.b. Level of success in the management of the triple constraints of time, cost, andscope.I want answer with explanation... I'll upvote you... Only typed answer I want... The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Activity optimistic time most likely time pessimistic time Activity Predecessor A 1 4 7 -- B 2 6 7 -- C 3 3 6 B D 6 13 14 A E 3 6 12 A, C F 6 8 16 B G 1 5 6 E, F Table 1 Reference: Ref 1 Using Table 1, the probability that the project could be completed in 23 weeks or less is approximately A. 0.94 B. 0.87 C. 0.91 D. 0.89To be able to meet delivery dates, a project consultant intimates that a project should be analyzed with activities as follows: ACTIVITY IMMEDIATE PREDECESSOR EXPECT DURATION (WEEKS) A. Initial discussion none 3 B. product design none 5 C. Market survey B 3 D. market evaluation A,C 4 E. product costing D 8 F. sales plan C 2 G. product pricing F 4 H. prototype F 2 I. master inform B 5 J.prototype testing HEG 3 (i) Draw a network to represent the various activities of the project.(ii) Draw up a table showing for each activity, the earliest and latest start and finish times and total float/slack.(iii) Determine the critical path and project duration.(iv) As a management science student, advise the management about the effect on the project completion time If the start time of activity A is delayed by 3weeks, activity G is delayed by 8 weeks
- This project has the following activities that need to be completed (see Table below) a) Draw the AOA and AON diagrams b) Find the critical path in AOA and AON Diagrams. Show calculations and table. c) Find the completion time. Show calculations d) Find the duration of each activity. Show calculations e) Show the predecessors in a table format. Activity TE AB 1 AC 3 AD 3 DC 4 CB 3 DE 8 CF 2 BF 4 IJ 2 CE 6 EF 5 FG 10 FH 11 EH 1 GH 9 EJ 3 GI 8 HJ 6 .This was a three part question. Bartelby helped me get A and B. The picture for Part A is the network diagram and Part B's answer is below for the critical path. My question I need to answer is Part C which is in the second picture. Part B There are the following paths in the project network. A –> B –> D –> G –> J = 2 + 4 + 2 + 3 + 7 = 18 A –> B –> E –> G – >J = 2 + 4 + 1 + 3 + 7 = 17 A –> B –> F –> H –> J = 2 + 4 + 8 + 5 + 7 = 25 A –> C –> F –> H –> J = 2 + 5 + 8 + 5 + 7 = 27 A –> C –> F –> I –> J = 2 + 5 + 8 + 4 + 7 = 26 The longest path in all the possible paths of the project network is A –> C –> F –> H –> J with the longest time. Therefore, the project duration is 27 days.Following are the activities of a project: Activity time in weeks Immediate Most Most MostActivity Precedence Optimistic Likely PessimisticA None 4 7 13B A 6 9 11C A 5 7 09D B 3 5 07E C 7 8 10F D 2 3 05G E 6 7 08H F&G…