Klassen Toy Company, Inc., assembles two parts(parts I and 2): Part I is first processed at workstation A for15 minutes per unit and then processed at workstation B for330 PART 2 DESIGNING OPERATIONS10 minutes per unit. Part 2 is simultaneously processed at workstationC for 20 minutes per unit. Workstations B and C feed theparts to an assembler at workstation D, where the two parts areassembled. The time at workstation Dis 15 minutes.a) What is the bottleneck of this process?b) What is the hourly capacity of the process?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
Klassen Toy Company, Inc., assembles two parts
(parts I and 2): Part I is first processed at workstation A for
15 minutes per unit and then processed at workstation B for
330 PART 2 DESIGNING OPERATIONS
10 minutes per unit. Part 2 is simultaneously processed at workstation
C for 20 minutes per unit. Workstations B and C feed the
parts to an assembler at workstation D, where the two parts are
assembled. The time at workstation Dis 15 minutes.
a) What is the bottleneck of this process?
b) What is the hourly capacity of the process?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,