Output Information (in hours) 4 5 7 8 Planned output Actual output 70 70 70 70 70 60 60 60 60 60 Input Information Deviation (in hours) Cumulative deviation Backlog 75 hours 4 5 6 7 8 Planned input Actual input 40 50 50 60 60 45 45 45 55 60 Deviation Cumulative deviation

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter14: Data Mining
Section14.2: Classification Methods
Problem 11P
icon
Related questions
Question

Jack, the owner and manager of Jack’s Box Company, wants
to monitor usage at Work Center 3, which is a bottleneck in the
system. He has collected data on the planned and actual input and
output. 

(a) Complete the input/output record.
(b) Describe your concerns based on the results of the
input/output analysis.

Output Information (in hours)
4
5
7
8
Planned output
Actual output
70
70
70
70
70
60
60
60
60
60
Input Information
Deviation
(in hours)
Cumulative deviation
Backlog 75 hours
4
5
6
7
8
Planned input
Actual input
40
50
50
60
60
45
45
45
55
60
Deviation
Cumulative deviation
Transcribed Image Text:Output Information (in hours) 4 5 7 8 Planned output Actual output 70 70 70 70 70 60 60 60 60 60 Input Information Deviation (in hours) Cumulative deviation Backlog 75 hours 4 5 6 7 8 Planned input Actual input 40 50 50 60 60 45 45 45 55 60 Deviation Cumulative deviation
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,