Q1:- The timetable for one of the projects was as in Table No. (1), answer the following: 1- Draw the sagittal wireframe of the project 2- Find the late start time for the event numbered (5). 3- The time limit for the early end of the activity No. (9) 4-Project completion time 5- select the critical path
Q: A plumber has decided to use the techniques of project management in order to plan a job. He knew…
A: The critical path method in project management is the longest set of activities that must be…
Q: Q1) The project schedule has the following characteristics: Activity Time (weeks) Activity…
A: Given information, Activity Predecessors Durations A 10 B 7 C B 5 D B 6 E A 9…
Q: A2 A4 A5 A3 Task Duration (days) 3 A1 3 A2 A3 1 A4 A5 days What is the late finish time for activity…
A: Using the Forward Path Early Start of the activity = Early Finish of predecessor activity Early…
Q: For the small project with the relationships shown below. Activity IPA's Duration (Day) A 5 B 7 4 D…
A: An activity-on-node diagram is a visual representation of the network of an entire project schedule.…
Q: Q1: For the project listed below, find the following items: 1- Total project finishing time 2-…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: Q1: For activities shown in table below, find the new time of project after updating, if the project…
A: Given data is
Q: (b) By referring to information in Table 1, determine the critical path, non-critical paths, and…
A: A Small Introduction about Critical path In project management, a critical path is the succession…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Note: - As we can answer only three subparts, the first three(a, b, and c) will be answered. If…
Q: SESSION 2– Individual exercise (for marks) Given the following activity precedence table, please…
A: The question is related to Critical Path Analysis. The details are given.
Q: 1. Draw the network diagram. 2. Calculate the expected duration and variance of each activity. 3.…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A:
Q: 01) The utility data for a network are given below: Activity Duration (Days) 0-1 1-2 8 1 -3 10 2-4…
A: Note: - Since we can answer only up to 3 subparts we will answer subparts 1, 2, and 3 for your…
Q: CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT…
A: Project management is described as a process through which a project, the resources of a project are…
Q: I need a project scope management plan and not a list of what should be included in the plan
A: A Project Scope Management Plan outlines the processes involved in executing your project and serve…
Q: Q1- The schedule for one of the projects was as in Table No. (1), answer the following- 1- Draw the…
A: Below is the solution:-
Q: ID Immediate Time (weeks) Predecessor A 6 B. 4 3. D. A, B, C 7 4. F D 2 H. ID Cost by week (in…
A:
Q: Give data of a project. Project manager checks the project at the end of week 10th Manpowers/ weeks…
A: Cost Variance (CV = EV - AC) Cost Performance Index (CPI = EV/AC) Schedule Variance (SV = EV -…
Q: The activities necessary for the completion of this project are listed in the following table:…
A: Since you have posted a question with multiple sub-parts, we will solve the subparts asked by you.…
Q: CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT…
A: Project management: It illustrates the method of managing the whole project work to accomplish some…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Hi, we are supposed to answer three subparts at a time. Since you have not mentioned which subpart…
Q: A2 A4 A5 Task Duration (days) 3 A1 A2 A3 3 Aa A5 days What is the late finish time for activity A,?
A: Using the Forward path, Early Start of the activity = Early Finish of predecessor activity Early…
Q: Ql: For activities shown in table below, find the new time of project after updating, if the project…
A:
Q: Table 7.8 contains data for the installation of new equipment in a manufacturing process at Excello…
A:
Q: The first question: The part of a construction project whose activities are shown in Table No. 1…
A:
Q: В- using the table below, Activity Predecessor Duration A A A D E 1 В E,C F D,B 1- How many paths…
A: The project network diagram is the visual representation of project tasks and their duration to…
Q: An activity, A, has two succeeding activities, B and C. Given the following information, determine…
A: Option C - 33
Q: Create the project management plan, project charter, enterprise environmental factors (EEFs), and…
A: Disclaimer: Since you have asked multiple question, so we will solve the first question for you. If…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: The critical path method is used to calculate the duration of the project by sequentially arranging…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (x) = 40 weeksDesired completion time (μ) = 40 weeks or…
Q: A project has the following activities, with specified precedents and expected durations (in hours).…
A: A network diagram is a diagram that shows the visual form of the project activities and their…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (μ)= 40 weeksDesired completion time (x) = 46 weeks or…
Q: Enrichment Exercise 7.2 Promoter of championship boxing match must perform the task shown in the…
A: An approach is a better way of looking at teaching and learning concepts. An approach gives rise to…
Q: 5. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each…
A: The project network is the visual representation of the project activities and their durations to…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: The critical path method is based on mathematical calculations to calculate the duration of the…
Q: 1) Build a quality management plan.
A: A Small Introduction to Quality Management Quality management is the demonstration of supervising…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Mean (x) = 40 weeks Desired completion time (μ) = 40 weeks Variance (σ2) = 9 weeks
Q: Q4: - The network diagram of one of the projects and its data as in Table No. (4), so if want to…
A: Below is the solution:-
Q: Q3: Draw the network diagram and determine the critical path for the following project: Activity…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: What would a project manager have to do to crash an activity? 2. Describe the meaning of slack, and…
A: Project management is a process of coordinating all processes related with a project. A crashing…
Q: CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT…
A: The success of any project is dependent on careful planning and the collaboration of a project…
Q: NORMAL CRASH TIME NORMAL CRASH COST TIME IMMEDIATE ACTIVITY (WEEKS) (WEEKS) COST PREDECESSOR(S) A 4…
A: Answer: we can see that for the mentioned project there are seven activities A, B, C, D, E, F, G. In…
Q: What is the slack time for activity A? 7 5 3 0
A: Formula:
Q: Predecessors C, F 9. Activity A B. H, I None (Start) B, J D D. C. H. G\ Construct a CPM network for…
A: Edge Node1 → Node2 D 1→2 C 2→3 F 2→4 d 3→4 G 3→6 H 3→7 A 4→5 J 5→8 I 6→7 B 7→8…
Q: Immediate Activity Predecessor Time (days) 8 в 20 33 18 D E 20 F B B.C 10 H D EF G, H, I 4 (End) a)…
A: A network diagram is a visual representation of a project which helps to identify the project…
Q: Question 2…
A: We know in Project Management, Variance may be a measure of a deviation from the projected value.…
Q: Q2. Consider the following data summarizing the details of a project involving 12 activities.…
A:
Q: Q2,A project network diagram with activities and their durations (days) is given below. A H 2 10…
A: In assembly line balancing, each task is assigned to a workstation in order to meet the specified…
Q: What is the slack time for Activity F and the late start for Activity H?
A: Below is the solution:-
Q: Draw the project network diagram. 1. What is the total time required to complete the project if no…
A: Network analysis (NA) could be a set of integrated techniques to depict relations among actors and…
Q: Q1: A project consisting of the following activities: ML KTJIH GFE D CB A K J HE GF D.C D.C D.C A BB…
A:
Step by step
Solved in 2 steps with 1 images
- As the pandemic waned, an educational institution was faced with the imperative of refurbishingand retrofitting its premises to facilitate reopening for blended modality in learning. Essential tasksincluded expanding certain spaces, fitting canteen tables with partitions and acquiring andinstalling equipment. A project manager was engaged to ensure readiness in three weeks.Information compiled on the project scope, such as activity times and relationships, is presentedbelow: Activity Immediate Predecessor Time (Days) A - 2 B A 5 C A 2 D A 6 E B 6 F C, D 3 G D…Ans c. The earliest starting time for activity H is 15 days Ans d. The latest start time for activity J is 25 days. Ans e. The critical path is A-B-H-I-L-M with the minimum duration of the project as 28 days This is a follow up question please do f and gACTIVITY Immediate Predecessor Normal Duration (wks) Minimum Duration (wks) Crash Costs ($/wk) A --- 4 4 --- B --- 3 2 100 C A, B 5 3 200 D C 4 4 --- E C 2 1 300 F C 1 1 --- G D 3 2 200 H E 1 1 --- I F 1 1 --- J H, I 3 1 100 What is the slack time for Activity F and the late start for Activity H? Group of answer choices 2 weeks, 11 weeks 1 weeks, 11 weeks 3 weeks, 10 weeks 2 weeks, 12 weeks None of the above are correct.
- 2. a) The activity shown in Table Q2 (a) are processes carried out in a mechatronic company. Based on the table provided, (i) Determine the Critical Path and Project Duration to complete the process. ii. Activity F cannot start immediately after activity C. The delay is expected to be 7 days. Determine by stating the possible problem, Critical Path and Project Duration to complete the process.Project 1-3: Creating a Project Schedule for Hiring a New EmployeeIn this project, you will create a project schedule for the process of hiring a new employee for your department. GET READY. OPEN a new blank project schedule. Set the project start date to be October 21, 2019.Enter the following tasks and durations:Task DurationWrite job description 2dNotify departmental recruiter 1dPost job internally 5dPost job externally 5dCollect résumés 10dReview résumés 5dSet up interviews 3dConduct interviews 8dSelect candidate 1dMake offer milestoneAssign a finish-to-start relationship to all the tasks.Change the relationship between tasks 3 and 4 to a start-to-start relationship.Auto-fit all the columns and rows.Change all tasks to the Automatically Scheduled mode.Use the statistics button on the Project Information dialog box to determine the current project duration.SAVE the project schedule in the solutions folder for this lesson as Hiring Employee xxd where…In a traditional project, the project manager saves the project schedule as a baseline plan in project management software. During the course of the project, the variance reports are created to show the difference between planned and actual activities. Project monitoring and control is different in agile projects than traditional projects. In an agile project, different tools and techniques are used to monitor and control project schedules. How does it help a project manager to monitor cost and schedule in a traditional project? There are different techniques for monitoring schedule performance in a traditional project. One method is a schedule variance report. How is a schedule variance report different from schedule variance in earned value? Does the role of the project manager change when monitoring and controlling agile projects?
- Which one is NOT a basic output of a PM network analysis? Select one: a. Identification of the critical path(s) b. Immediate predecessors c. Determination of the earliest and latest start times d. Estimated project durationWeek 6 Status Report When reporting on the progress and status of a project, your Stakeholders want to know what potential pitfalls or obstacles you have identified, and what your plan is for dealing with them. Toward that end, this week, you are to add an additional section to your Status report. The new section should look as follows: Open Risk Probability Impact Response Type Response Plan Identify at least two "risks" that could impact your ability to complete this week's assignments, and complete the table. These are NOT risks pertaining to the Running Case - they should be things which might impact YOU this week and cause your work to be late. (You can make some up if you honestly don't have any...) Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.What is the relationship between the earliest start time (EST) of an activity and the earliest completion time (ECT) of the activity? a. EST + Activity time = ECT b. EST × Activity time = ECTc. EST = ECT d. None of these statements is correct.
- 1. CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL PATH AND ITS DURATION (in weeks)4. CREATE A GANTT CHART STARTING JANUARY 1, 2021. NO DAY-OFFS5. WHEN WILL THE PROJECT BE COMPLETED? (Write in week)CPMGT 300 week 3 discussion question 1Week Three Discussion Topic One1 The Statement of Work and the Requirements Document of the project planning process are two components of delivering a product or service. Define these components and their relevance to the planning process. What might these two planning components have in common? What are their differences? Explain your answer. ………….Answer Preview………….Three Discussion Topic OneStatements of work (SOW) is referred to as a formal document that defines and capture the work activities timelines and deliverables a vendor need to execute in performance of a particular job for a client. The statement includes various detailed pricing and requirement together with a standard regulatory as well as terms and conditions of government. Requirement document is defined as………APA155 Words Added to cartDevelopment of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 44 33 $ 2 comma 100$2,100 $ 2 comma 700$2,700 long dash— B 22 11 $ 2 comma 200$2,200 $ 2 comma 900$2,900 long dash— C 33 33 $ 500$500 $ 500$500 long dash— D 88 44 $ 2 comma 500$2,500 $ 2 comma 820$2,820 A E 66 33 $ 1 comma 000$1,000 $ 1 comma 300$1,300 B F 33 22 $ 3 comma 400$3,400 $ 4 comma 800$4,800 C G 44 22 $ 1 comma 500$1,500 $ 2 comma 000$2,000 D, E Part 2 a) Based on the given information…