Question
Using the activity table below, construct a CPM/PERT network noting the activity numbers and durations. Identify the critical path through the network, determine the project completion time, and determine the earliest and latest end dates for each node.
Activity |
Predecessor |
Time (months) |
1 |
- |
10 |
2 |
- |
1 |
3 |
- |
6 |
4 |
2 |
3 |
5 |
1,3,4 |
5 |
6 |
3 |
8 |
7 |
5,6 |
2 |
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 3 steps with 35 images

Knowledge Booster
Similar questions
- 21. Recently, you were assigned to manage a project to remodel the seminar room for your company. You have constructed a network diagram depicting the various activities in the project (Figure 7.130). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table. Activity A B с D E Optimistic Start 5 4 5 2 4 Figure 7.13 Network Diagram for Problem 21 B D TIME ESTIMATES (DAYS) Most Likely 8 8 6 4 7 Finish Pessimistic 11 11 7 6 10 a. What is the expected completion time of the project? b. What is the probability of completing the project in 21 days or less? c. What is the probability of completing the project in 17 days or less?arrow_forward7arrow_forwardA project has activities, durations, costs, and precedence relationships as shown in the following table. Accelerated Duration (Weeks) Immediate Predecessor Path A-C-E A-D-H-I B-F-H-I Activity B-G-I A B с D E F GJ H I Present Duration (Weeks) Project is reduced from Activity Crashed (1 week) Additional Cost for Crashing 8 13 8 18 13 15 10 7 5 $ to B B 7 I 11 4 16 8 13 8 6 4 $14,000 Develop a time-cost trade-off analysis. Detail the steps that you would use to accelerate or crash the project to its minimum duration at the lowest cost. Determine each step's cost and the duration of the project. Length of Path (weeks) H D, F A weeks at an additional cost (in $) of $ A U B B D, F G, H Present Cost D, F $11,000 $20,000 $9,000 $25,000 $20,000 $20,000 $15,000 $12,000 $10,000 Accelerated Cost $16,000 $26,000 $21,000 $29,000 $34,000 $31,000 $24,000 $17,000arrow_forward
- EX6-6 (Algo) From the following information, develop... From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? ID A Survey site B Description C Excavate site Install power lines. D Install drainage E Pour foundation The project will take The critical path is The late start on Activity C is The slack on Activity C is The slack on Activity D is The early start on Activity E is Predecessor None A B B C, D. Time 4 5 4 3 days. days. days. days, days.arrow_forwardPerform the exercise in Microsoft Project Construct the Project network.arrow_forwardPlease give me correct solution.arrow_forward
- 6. Given the following network, with activity times in months, determine the earliest and latest activ- ity times and slack for each activity. Indicate the critical path and the project duration.arrow_forwardGiven the following network and activity time estimates, determine: The expected time and variance for each activity Complete the chart showing bout the EF and LFarrow_forwardGiven the following network and probabilistic activity timeestimates, determine the expected time and variance foreach activity and indicate the critical path:arrow_forward
- Charlie Cook was able to determine the activity times for constructing his chemical contaminant tracking machine. Cook would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Q Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A B C D 7 8 2 1 Charlie's earliest start (ES) and earliest finish (EF) are: A A Activity A EFGH ES EF 7 5 7 11 8 B B C, E D, Farrow_forwardYou have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 30 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 30 working days. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical activities. Time (days) 6 ID ABCDEFGHHDM А с I J к Description Prepare site Pour foundation Erect frame Roof Windows Doors Electrical Rough-in frame Door opener Paint Cleanup The project will take The critical activities are The early start on Activity D is The late start on Activity E is The slack on Activity E is The slack on Activity F is Predecessor None ABCCUU А В с с с с D, E, F, G F, G H, I J UNHUNONN ана 1 2 days. days. days. days. days.arrow_forwardUse the following information in a table about the activities of an information technology project of ABC Bank and solve the given questions. Activity Activity Predecessors Time Estimate/Duration (days) ES EF LS LF Slack time A B C D E F -- A A B B, C D, E 4 5 6 5 3 7 Draw a network diagram. List all the paths and their durations Find the critical path. Calculate early start, early finish, late start and late finish Calculate the slack time of each activityarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,

Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning

Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.