Work center 100 200 300 Adjust all answers to one decimal point using the Decrease Decimal Function. 568-98 Work center 100 Weekly capacity requirements (in hours) WEEK 200 300 1 2 15 30 "For the two scheduled receipts, assume that the setup is complete, and that in each case they are half complete". Using the "cover" as an example, this means that the setup (of 2 hours) is already complete, and half (25 of the 50) covers have already been made. (So 25- the other half-still must be processed) Hint: It is useful to prepare a table like the one below, before you calculate the weekly capacity req.'s. You must fill out the data for WCs 100 and 300. Planned Order Releases and Scheduled Receipts 1 2 3 30 3 4 30 4 5 30 5 6 0 6 0 Problem 7: An office supply company makes notebooks with the following product structure: Pad Notebook Gross requirements Scheduled receipts Projected available balance Planned order releases The company uses an MRP system, and has the following records for these three items: Week Q-L4L, LT-1, 55-0. Pad Gross requirements Scheduled receipts Projected available balance Planned order releases Q-M.LT=1.55-0. Notebook 30 10 Cover Gross requirements Scheduled receipts Projected available balance 10 Planned order releases Cover 1 2 25 25 S 20 S 30 0 25 1 2 20 25 15 10 30 3 4 5 25 25 25 0 25 3 25 15 30 1 2 20 25 25 50 40 15 50 0 3 40 50 0 25 4 25 20 30 4 ܘܟ ܠ ܕ ܕ 0 25 5 25 25 0 5 25 25 6 25 0 9 0 6 0 25 0 6 0 40 40 00 The notebooks are fabricated in the following work centers, listed with accompanying time requirements. Operation Notebook assembly Pad production Cover production Work Center 100 200 300 Setup Time 2 hours 3 hours 2 hours Run Time 10 minutes 5 minutes 9 minutes Determine the weekly capacity requirements in each of the work centers. For the two scheduled receipts, assume that the setup is complete, and that in each case they are half complete.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
Work
center
100
200
300
Adjust all answers to one decimal point using the Decrease Decimal Function
8-98
Work
center
100
Weekly capacity requirements (in hours)
WEEK
200
300
1
2
15
30
"For the two scheduled receipts, assume that the setup.
is complete, and that in each case they are half complete".
Using the "cover" as an example, this means that the
setup (of 2 hours) is already complete, and half (25 of the 50)
covers have already been made. (So 25- the other half-still
must be processed)
Hint: It is useful to prepare a table like the one below, before you calculate
the weekly capacity req.'s. You must fill out the data for WCs 100 and 300.
Planned Order Releases and Scheduled Receipts
1
2
3
3
30
4
30
4
5
30
5
6
0
6
0
Problem 7: An office supply company makes notebooks with the following product structure:
Pad
Notebook
Gross requirements
Scheduled receipts
Projected available balance
Planned order releases
The company uses an MRP system, and has the following records for these three items:
Week
Cover
Gross requirements
Scheduled receipts
Projected available balance
Planned order releases
Q-50, LT-2, S5-0
Notebook
Q-L4L, LT-1, SS=0.
Pad
Gross requirements
Scheduled receipts
Projected available balance 10
Planned order releases
Q-30, LT-1, 55-0
cont'd on the right.
30
10
1
25
1
Cover
-
5
0
0
20 25 25
20
15
30
2
25
1
20
50
40
50
2
25
10
30
2
25
3
25
15
0
3
25
15
30
3
25
4
25
0
0
25 25
4
25
20
30
4
25
5
25
40 15
50
0
5
25
25
0
5
25
40
0
6
25
0
0
6
0
25
0
6
0
40
0
The notebooks are fabricated in the following work centers, listed with accompanying time.
requirements.
Operation
Notebook assembly
Pad production
Cover production
Work Center
100
200
300
Setup Time
2 hours
3 hours
2 hours
Run Time
10 minutes
5 minutes
9 minutes
Determine the weekly capacity requirements in each of the work centers. For the two scheduled
receipts, assume that the setup is complete, and that in each case they are half complete.
Transcribed Image Text:Work center 100 200 300 Adjust all answers to one decimal point using the Decrease Decimal Function 8-98 Work center 100 Weekly capacity requirements (in hours) WEEK 200 300 1 2 15 30 "For the two scheduled receipts, assume that the setup. is complete, and that in each case they are half complete". Using the "cover" as an example, this means that the setup (of 2 hours) is already complete, and half (25 of the 50) covers have already been made. (So 25- the other half-still must be processed) Hint: It is useful to prepare a table like the one below, before you calculate the weekly capacity req.'s. You must fill out the data for WCs 100 and 300. Planned Order Releases and Scheduled Receipts 1 2 3 3 30 4 30 4 5 30 5 6 0 6 0 Problem 7: An office supply company makes notebooks with the following product structure: Pad Notebook Gross requirements Scheduled receipts Projected available balance Planned order releases The company uses an MRP system, and has the following records for these three items: Week Cover Gross requirements Scheduled receipts Projected available balance Planned order releases Q-50, LT-2, S5-0 Notebook Q-L4L, LT-1, SS=0. Pad Gross requirements Scheduled receipts Projected available balance 10 Planned order releases Q-30, LT-1, 55-0 cont'd on the right. 30 10 1 25 1 Cover - 5 0 0 20 25 25 20 15 30 2 25 1 20 50 40 50 2 25 10 30 2 25 3 25 15 0 3 25 15 30 3 25 4 25 0 0 25 25 4 25 20 30 4 25 5 25 40 15 50 0 5 25 25 0 5 25 40 0 6 25 0 0 6 0 25 0 6 0 40 0 The notebooks are fabricated in the following work centers, listed with accompanying time. requirements. Operation Notebook assembly Pad production Cover production Work Center 100 200 300 Setup Time 2 hours 3 hours 2 hours Run Time 10 minutes 5 minutes 9 minutes Determine the weekly capacity requirements in each of the work centers. For the two scheduled receipts, assume that the setup is complete, and that in each case they are half complete.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,