List seven factors, specific to masonry work, which influence the level of productivity of crews performing masonry work.
In addition to carpenters and laborers, what crafts may be involved with concrete system construction?
Group of answer choices (multiple choice)
-Iron workers for rebar
-OE for concrete pump
-Cement Masons
Visit buildings under construction when floor finishing crews are at work. Observe the tools and procedures used?
Knowledge Booster
Similar questions
- Find the duration in days for a masonry job that has 24,000 bricks with a crew of five masons and three laborers. The work day is 10 hours. The productivity of the crew is 0.103 man hour per unit (9.7087 unit/man-hour).arrow_forwardWhy is it also preferable to measure the concrete and all other work associated with an item before going on to measure the concrete in another item?arrow_forwardexplain and suggest the fastest construction method for each structurearrow_forward
- You are the Field Engineer and Cost Engineer for a residential project that you are managing. In three (3) days, your endeavor will begin Masonry Works. In accordance with this, you must calculate (ahead of time) the total number of CHB sections required for the road-facing exterior walls. To ensure you have sufficient materials, you added an allowance for eight percent (8%) breakage. Determine the quantity of CHB to be ordered. Round your answer to the nearest integer.Student Number is the Total Contract Price (TCP) of the Undertaking. If the project's operating expenses are 35% of the total budget, how much will be left if the price of CHB is 13 pesos and 16 pesos, respectively? use 123456 as the TCP. Below are specifics: NEED ASAP 30 MINSarrow_forwardDescribe any Five major construction methods which are advance, innovative and sustainable process or techniques to be involved in during the construction stage (covers site investigation, site planning and development, earthwork and excavation, temporary works, concrete handling and curing, lightweight materials in construction, etc.).arrow_forwardwhat do you mean by building maintenance and repairing of reinforced concrete structurearrow_forward
- Discuss the standards to being used when estimating concrete for a construction project, include tables.arrow_forwardConcrete estimatearrow_forwardPrepare an organizational chart depicting the construction process. Identify the parties involved, their functions, responsibilities, and connections with each other. Why must builder/contractor understand materials? Make a list of the kinds of materials used in (a) a water distribution system, (b) a city street pavement, (c) a sewage collection system, and (d) a roofing system. Discuss at least three sustainable construction methods or materials used in the Philippines today. Cite some examples.arrow_forward
- Describe the four types of information documented in the daily construction report?arrow_forwardWhat are the several uses of a tirfor machine?arrow_forwardA method statement for each of the following aspects of the construction: Excavations and foundations Structural Frame Access road(s) Road and building drainage Pondarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,