A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the total completion time for the project?
- a. 3 days, because this is the minimum time
- b. 7 days, because this is the maximum time
- c. 20 days, because this is the sum of the times
- d. It is not possible to determine the total completion time from the given information.
To determine: The total completion time for the project.
Answer to Problem 1CQ
D. It is not possible to determine the total completion time from the given information.
Explanation of Solution
Given information:
Four activities of a project take 4, 3, 6 and 7 days respectively.
The given scenario lacks basic information to find the completion time of the project. Details like precedence relationship is not given which makes it impossible to find the sequence of activities in which the project must be done.
Want to see more full solutions like this?
Chapter 19 Solutions
OPERATIONS MANAGEMENT
Additional Business Textbook Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Operations and Supply Chain Management 9th edition
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Operations Management
Operations Management: Processes and Supply Chains (11th Edition)
- An email announcing the project to major stakeholders is an example of a Project Team Kickoff. Question 1 True Falsearrow_forwardWhich of the following statements is correct with respect to an AON graph of a project?a. In an AON graph, the activities are on the edges of a graph.b. In an AON graph, the activities are on the nodes of a graph.c. AON stands for the American Operations Norm.d. None of these statements is correctarrow_forwardBriefly describe 'Parkinson's Law' and 'Murphy's Law'. One sentence each. Then briefly in 3-6 sentences, please explain why these 'Laws' are relevant in project planning in regard to schedule, risk, cost, and resources (especially the 'people resource')..arrow_forward
- In reference to the attached image: Activity times with the greatest uncertainty are activities D, E, and H. Describe conceptually how you could model this uncertainty in activity times. (You do not have the necessary data to actually do this numerically.)arrow_forwardWhy do you believe that timetable conflicts are the most common source of conflict on projects? What is it about project management software that makes it tough to utilise effectively? Discuss three additional proposals for increasing the quality of IT projects that were not included in Chapter 8.arrow_forwardYou are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in the table. Your interest is in minimizing the cost of the project to the community center. a. Using the normal times for each activity, what is the earliest date you can complete the project? b. Suppose the variable overhead costs are $50 per day for your project. Also, suppose that the center must pay$40 per day for a temporary room on day 15 or beyond. Find the minimum-cost project schedule.arrow_forward
- A bar chart shows the number and type of resources you need throughoutyour project is called a _______________.A. Organizational ChartB. Resource histogramC. Resource ScheduleD. Staffing Timetable You have identified an opportunity to potentially increase the project’s value.Which of the following is an example of enhancing that opportunity?A. By taking additional actions, you increase the potential reward without reducing itsprobabilityB. By forming a partnership with another company, the project’s value will increase forboth companiesC. By taking out insurance, you can reduce potential costs to the projectD. By documenting the opportunity in the register, you can keep track of it and ensureit gets exploitedarrow_forwardFor a given activity, the: most optimistic time to complete the project is 8, the most pessimistic time to complete the activity is at 32, compute the estimated time to complete the activity if the most likely to complete is at 2arrow_forwardA contractor estimated that a project will be finished by his crew in 60 days. After the crew worked for 40 days, 38 workers stopped working. If the remaining workers will continue at the same rate, they will be delayed by 5 days. How many workers are there in the original crew?arrow_forward
- The critical path in a project is the sequence of activities that:a. has the shortest time.b. has the smallest number of activities.c. has the shortest budget.d. None of these statements is correct.arrow_forwardGiven a project with three paths and their corresponding path lengths: A-B-C: 25 days, A-D-F: 15 days, and B-C-D-E: 20 days; which of the following statements is TRUE? * Activity B has the most slack The expected duration of the project is 60 days The earliest project completion time is 15 days The critical activities are A, B and Carrow_forwardWhat is the optimal plan for expediting some activities so as to minimize the total cost of performing the project within the deadline?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.