Fundamentals Of Construction Estimating
4th Edition
ISBN: 9781337399395
Author: Pratt, David J.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Question
error_outline
This textbook solution is under construction.
Students have asked these similar questions
1* Suppose you are a project manager of a power plant project and there is a penalty in your contract with the main client for every day you deliver the project late. You need to decide which sub-contractor is appropriate for your projects critical path activities. But while selecting a sub-contractor, you should take into consideration the costs and delivery dates.Sub-contractor 1 bids $250,000. You estimate that there is a 30% possibility of completing 60 days late. As per your contract with the client, you must pay a delay penalty of $5,000 per calendar day for every day you deliver late.Sub-contractor 2 bids $320,000. You estimate that there is a 10% possibility of completing 20 days late. As per your contract with the client, you must pay a delay penalty of $5,000 per calendar day for every day you deliver late.You need to determine which sub-contractor is appropriate for your projects critical path activities. Both sub-contractors promise successful delivery and high-quality…
CPM Construction plans to buy a truck for $150,000, andsell it for $15,000 at the end of five years. The annual operatingcost of the vehicle is $60,000. What is the equivalentannual cost of this truck, if the company uses a MARR of12%?
Find the effective gross hourly cost for drill press operators paid an average wage of $22/hour. No overtime is planned. Company policy allows six paid holidays and the average entitled vacation is 10 days. There is no nonchargeable time or performance subsidy. No sick leaves are included. FICA is at 6.2% and worker’s compensation is at 2% of $20,000. The company pays $400 for unemployment insurance.
Knowledge Booster
Similar questions
- A contractor has a job which should be completed in 100 days, at present he has 80 men on the job and it is estimated that they will finish the work in 130 days, if of the 80 men, 50 are paid 400/day, 25 at 500/day, and 5 at 600/day, and if for each day beyond the original 100 days, the contractor has to pay 10,000 in liquidated damages. a. How many men should the contractor add so he can complete the work on time?arrow_forwardDetermine the Average Cost if the total cost of the production is $150 and the total numbers of production unit is $100.arrow_forwardA client plans to construct a manufacturing plant that involves multiple engineering disciplines. Calculate the total engineering fees including taxes based on the following: Mechanical Works, $1,540,000 Electrical Works, $1,780,000 Earth Works, $950,000 Civil Works, $2,125,100 Environmental Works, $1,325,000 Basis B fees = 9% There are no office fees Taxes = 13%arrow_forward
- Engineer Layla purchased a dump truck worth P850,000. She added P50,000for the delivery and other expenses. The said equipment is expected to be useful for 10 years. At the end of its life, it will cost x% of the first cost. Using SLM, its book value at year 5 is P517,500. What is the value of x?arrow_forwardA client plans to construct a manufacturing plant that involves multiple engineering disciplines. Calculate the total engineering fees including taxes based on the following: Mechanical Works, $1,540,000 Electrical Works, $1,780,000 Earth Works, $950,000 Civil Works, $2,125,100 Environmental Works, $1,325,000 Basis B fees = 14% There are no office feesDo not include the Contractor payment in the engineering fees. Taxes = 13%arrow_forwardAs supervisor of a facilities engineering department, you consider mobile cranes to be critical equipment. The purchase of a new, medium-sized truck-mounted crane is being evaluated. The economic estimates for the two best alternatives are shown in the following table. MARR is at 15% per year. You can use the assumption of repeatability in this case. Show that the same selection is made for the following methods: c. EUAC method Alternative A B Capital investment ALTERNATIVE A $272,000 ALTERNATIVE B $346,000 Annual expenses ALTERNATIVE A $28,800 1 ALTERNATIVE B $9,300 Useful life (years) ALTERNATIVE A =6 ALTERNATIVE B =9 Salvage value ALTERNATIVE A $ 25,000 ALTERNATIVE B $40,000 Answer letter c only. Give thee EUAC methodarrow_forward
- An ironworker works 10hr/day, 6 days/week. A base wage of OMR20.97/hr is paid for all straight-time work, 8 hr/day, 5 day/week. An overtime rate of one time and one half is paid for all hours over 8 hr/day, Saturday through Wednesday, and double time is paid for all Thursday work. The social security tax is 7.65% and the unemployment tax is 3% of actual wages. The rate for worker’s compensation insurance is OMR12.5 per OMR100 of base wage. Calculate the average hourly cost to hire the ironworker.arrow_forwardTwo installers will install the unit. Each will work the same amount of timeand will be paid $8.00 per hour. How much will each installer earn fromthis job?arrow_forward7 A consortium of international telecommunication companies contracted for the purchase and installment of a fiber optic cable linking two major cities at a total cost of US$990 million. The amount includes freight and installation charges estimated at 10% of the above contract price. If the cable shall be depreciated over a period of 16 years with zero salvage value. What is the book value after 4 years using straight line method? Express your answer in whole number.arrow_forward
- How is the extended home office overhead is computed under the Eichleay formula?arrow_forwardThere is a building that has 15 floors, a grocery store and a gym, the rent for the floors 1-5 is 3000 per month, for the floors 6-10 is 4000 per month, for the floors 11-15 is 5000 per month, for the grocery store the rent is 6000 per month, for the gym the rent is 6500 per month, the effective gross income is 12%, the operating expense is 8% and the capital expedinture is 6% and the annual market increase is 4%. Find the value of the building and the net operating income?arrow_forwardA contractor estimates that he could finish a project in 15 days if he has 20 men. At the start, he hired 10 men then after 6 days, 10 more men are added. How many days was the project delayed? A. 6 B 5 € 4 D 3 E None of the abovearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,