Quiz 9

.pdf

School

University of Texas, Dallas *

*We aren’t endorsed by this school

Course

6362

Subject

Accounting

Date

Feb 20, 2024

Type

pdf

Pages

15

Uploaded by DeanHeatOkapi4

Report
QUESTION 1 1 points To develop the budget, the project manager O a.starts by aggregating all the costs @ b.all of the above O c.determines how much money is required for reserve funds (O d.must understand cash flow both in terms of funding and requirements to meet costs for activities on a day-to-day basis. QUESTION 2 1 points The amount of project budget reserved for unforeseen project work that addresses the “unknown unknowns” that can affect a project is the O a.project buffer. O b. funding limit. @(c. contingency reserve. ® d.management reserve.
QUESTION 3 1points |t is the approved version of the project budget, including how much money is expected to be spent and when; the cost baseline will be compared to actual project results for monitoring and controlling purposes. O a.Contingency reserve O b.empirical estimating @ c. Cost performance baseline O d.Cash flow
QUESTION 4 1 points For the given System Integration Project, the overall duration to complete the project is 14 days, and there are 5 activities as shown in the timeline. The effort for each activity and cost per day is given. Also, the incurred cost and actual % of work completion at the end of 8 days are given. what does SPI of the project indicates at the end of 8 days? 1 2 3 45 6 78 9 1011 12 13 14 Planned Values Actual Values per End of day 8 #_|Activity Days _|Costperday |Planned cost # [Activity Days _[Incurred cost|Actual % completion Detine Requkements 1 |Define Requirements 3 500 1 |Define Requirements| 3 1500 100% o 2_|Purchase Software 2 900 2 |Purchase Software 2 1600 100% ol Sotware 3 [Install Software 2 600 3 |Install Software 2 1800 50% Prepare TestPlan 4_|Prepare Test Plan a 700 4__|Prepare TestPlan a 700 25% TostSystom 5 [TestSystem 3 800 5 [TestSystem 3 0 0% [TotalBudget | ] @ a.SPlis < 1 and project is performing behind the schedule O b.SPlis > 1 and project is performing ahead of schedule O c.SPlis 1 and project is performing on schedule O d.SPl is 2 and the project has performed twice the work it was supposed to at this point.
QUESTION 5 1 points |2 S-L] Jason, a project manager, is working with his team to estimate the total cost of developing a web-based CRM system. After reviewing the planned scope of work with Jason, his sponsor suggests that Jason use the budget from a previous, similar project as the basis for his project budget. The estimating process that Jason’s sponsor is using is called . O a.three-point estimating. O b. parametric estimating. @ c.analogous estimating. O d.single-point estimating. QUESTION 6 1 points The documentation of a project cost estimate generally requires substantial supporting detail to include all of these EXCEPT: a.management reserve needs O b.assumptions and constraints. O c.the estimating methods and a range of possible outcomes. O d.a description of scope.
QUESTION 7 1 points The “process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs” is referred to as . O a.determine budget. O b.estimate costs. O c.control costs. @ d.plan cost management. QUESTION 8 1 points The is the approved budget, usually in a time distribution format, that is used to estimate, monitor, and control the overall cost performance of the project. O a.control account O b.management baseline. O c.cost benchmark @ d. cost baseline.
QUESTION 9 1 points For the given System Integration Project, the overall duration to complete the project is 14 days, and there are 5 activities as shown in the timeline. The effort for each activity and cost per day is given. Also, the incurred cost and actual % of work completion at the end of 8 days are given. what does CV and SV of the project indicates at the end of 8 days? 1 2 3 45 6 78 9 1011 12 13 14 Planned Values Actual Values per End of day 8 #_|Activity Days _|Cost perday |Planned cost # [Activity Days _[Incurred cost|Actual % completion Deine Requrements 1 |Define Requirements | 3 500 1 [Define Requirements| 3 1500 100% - 2_|Purchase Software 2 900 2 |Purchase Software 2 1600 100% ol Softwace 3 [Install Software 2 600 3 [install Software 2 1800 50% Propare TextPlan 4_|Prepare Test Plan 2 700 4 |Prepare TestPlan 2 700 25% TestSpstem 5 [TestSystem 3 800 5 [TestSystem 3 0 0% [TotalBudget | ] O a.Project is performing on budget and on schedule O b.Project is performing under the budget and on schedule @ c.Project is performing over the budget and over the schedule O d.Project is performing under the budget and under the schedule
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help