Quiz 4 1.
The work breakdown structure subdivides the project into smaller pieces called work items.
Answer: True
2.
An activity does not necessarily require the expenditure of effort by people.
Answer: True
3.
Certain activities in a network diagram have to be done in serial sequence.
Answer: True
4.
The customer may make unannounced visits to the contactor’s facility or work
Answer: True
5.
The project manager should involve every project member in developing the WBS to have special expertise, knowledge, or experience that will help develop a more comprehensive and complete WBS.
Answer: False
6.
All branches of the WBS have to be broken down to the same level.
Answer: False
7.
The project quality plan should state which tools and techniques to use and when.
Answer: True
8.
The quality plan may also state that suppliers must provide documentation certifying that the materials they supply meet certain required specifications.
Answer: True
9.
For large or complex projects, it may be difficult to determine all the work elements to include in
the work breakdown structure.
Answer: True
10.
The deliverables in the project scope document will be used as the basis for creating a more detailed WBS in the next step of the planning process
Answer: False
11.
A clear description of the acceptance criteria with quantitative measures will help to avoid understanding
Answer: False
12.
Some activities in a network diagram may be done concurrently
Answer: True
13.
Using the work breakdown structure, the individual or team responsible for each work package must next define all the specific activities that need to be performed to produce the end item or deliverable for the work package
Answer: True
14.
The description of an activity in a network diagram usually starts with a _____
Answer: verb
15.
Arrows linking the activity boxes in a network diagram show the _____ of the dependent relationship:
Answer: direction
16.
The project objective must be clearly defined and agreed upon by the
Answer: sponsor or customer and the project team or contractor that will perform the project
17.
The _____ shows all the individuals associated with each work item in the work breakdown structure, as well as all the work items associated with each individual
Answer: responsibility assignment matrix
18.
Each box for an activity in a network diagram is assigned
Answer: a unique activity number
19.
_____ contains a small number of higher-level activities rather than a large number of detailed activities
Answer: A summary network
20.
It is common to progressively elaborate the network diagram Answer: as the project progresses and more information is known or becomes clear
21.
_____ in a network diagram will allow the project to be completed in the shortest possible time while making the best use of available resources.
Answer: Laddering
22.
A network diagram is a tool for arranging the specific activities in the _____ and defining their _____
Answer: appropriate sequence, dependent relationships
23.
In preparing a network diagram, drawing activities in a _____ is not acceptable because it portrays a path of activity that perpetually repeat itself.
Answer: loop
24.
Activities in a network diagram have __________ that is, they are linked in a logical sequence to show which activities must be finished before others can start
Answer: a dependent relationship
25.
To draw a _______ start by drawing the activities in their logical sequence and connecting them with arrows o show the required dependent relationship
Answer: network diagram
26.
An activity in a network diagram cannot start until
Answer: all of the preceding activities that are linked to it by arrow are finished
27.
The ______ is a roadmap that displays how all the specific activities fit together to accomplish the project work scope
Answer: network diagram
28.
The responsibility assignment matrix may use a P to designated _____ responsibility and an S to indicate _____ responsibility for a specific work item
Answer: primary, support
29.
Each activity in a network diagram is represented by a box in the ____ and the ___ of the activity is written the box
Answer: project scoop document, responsible organization
30.
The ______ is a communication tool for the project team because it show who is responsible for each activity and how each person ‘s work fits into the overall project
Answer: network diagram
31.
In the network diagram for the following list, what activity immediately follows activity E?
Answer: G
32.
In the network diagram for the following list, what activity immediately follows activity D?
Answer: F
33.
The project scope is all the work that must be done to do all of the following except.
Answer: meet with every stakeholder
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
A project may be better comprehended by sketching its map with and
without its underlying architecture. Bearing in mind the influence of the end
product.
arrow_forward
Both architectural and non-architectural maps of a project should be created for maximum comprehension.what effect it will have on the final result.
arrow_forward
Suppose you are the project manager for the following project: First,draw a network diagram for the project. Determine the critical path andslack times for all of the tasks. This completes your plan for the projectschedule. During project execution, you become aware of the need tochange the duration of Task 4 to five days.Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, ifany, effects do these changes have on your project? What would have happened if you had notbeen monitoring the status of the project?
arrow_forward
a) A network diagram is an important scheduling tool that graphically portrays the
logical relationship and sequencing of activities and events on a project.
Task
Immediately Preceding Activity
A
B
с
D
A
E
B
F
B
G
C
H
D
I
G
J
F, H, I
Based on the information in the table above, draw an Activity-on-Arrow network
diagram to depict the logical relationships among the activities of the project.
b) One of the logical rules on a network diagram states that "No two activities may
share the same 'head' and 'tail' events". Explain why this is the case and STATE
any TWO implications for the project if this rule is disregarded.
arrow_forward
A project should be mapped both with and without architecture in order to better understand it.how the ultimate product will be affected by it
arrow_forward
> For each component in the project, draw (not necessarily by a tool):
o the DFD Context diagram: to show input/output of the component as one
process
o the DFD level 0 diagram: to show input/output of sub-processes in the
component
arrow_forward
Take a project into consideration and map it both with and without architecture. how it will impact the result.
arrow_forward
writeLiterature reviewLiterature review must start with a background for Design and implementation of the exterior and interior decoration design system for interior design offices , the relevant literature must be identified and give reviews of background reading. Students are expected to review/evaluate the literature in comparison with their project tasks. The literature review must include a clear statement of approach to be taken to solve the problem with reference to the background reading.
arrow_forward
Your task for this assignment is to create a network diagram for two projects. The activity,
immediate predecessor and duration are given. You are to layout-long-hand or using some
software-a network diagram for each project. For each diagram conduct a forward and
backward pass, calculate the slack, and identify the critical path. When noting your early start,
early finish, late start, late finish and slack, please use the format provided.
Project 1
Activity
Immediate Predecessor
Duration
A
none
3
В
A
4
none
6
D
none
2
D
5
F
В, С, Е
2
Project 2
Activity
Immediate Predecessor
Duration
A
none
6
B
none
3
A
9
B
E
в
4
D
2
G
E
8.
*Note: please use this format.
Early
Start
Duration Early
Finish
Activity
Float
Late
Start
Late
Finish
arrow_forward
Drawing the project map with and without the architecture may help. Possible global effects.
arrow_forward
Is a project sponsor's job the same throughout the whole SDLC?
arrow_forward
Project Communication Plan Diagram - communication plans during development for Attendance fingerprint system
arrow_forward
As a project manager of a Software project, you have received given data about the different type of Issues identified in the project: –
Issue 1 – 85 occurrences; Issue 2 – 125 occurrences; Issue 3 – 28 occurrences; Issue 4 – 395 occurrences; Issue 5 – 185 occurrences; Issue 6 – 128 occurrences; Issue 7 – 85 occurrences; Issue 8 – 169 occurrences; Issue 9 – 148 occurrences; Issue 10 – 209 occurrences.
Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Related Questions
- A project may be better comprehended by sketching its map with and without its underlying architecture. Bearing in mind the influence of the end product.arrow_forwardBoth architectural and non-architectural maps of a project should be created for maximum comprehension.what effect it will have on the final result.arrow_forwardSuppose you are the project manager for the following project: First,draw a network diagram for the project. Determine the critical path andslack times for all of the tasks. This completes your plan for the projectschedule. During project execution, you become aware of the need tochange the duration of Task 4 to five days.Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, ifany, effects do these changes have on your project? What would have happened if you had notbeen monitoring the status of the project?arrow_forward
- a) A network diagram is an important scheduling tool that graphically portrays the logical relationship and sequencing of activities and events on a project. Task Immediately Preceding Activity A B с D A E B F B G C H D I G J F, H, I Based on the information in the table above, draw an Activity-on-Arrow network diagram to depict the logical relationships among the activities of the project. b) One of the logical rules on a network diagram states that "No two activities may share the same 'head' and 'tail' events". Explain why this is the case and STATE any TWO implications for the project if this rule is disregarded.arrow_forwardA project should be mapped both with and without architecture in order to better understand it.how the ultimate product will be affected by itarrow_forward> For each component in the project, draw (not necessarily by a tool): o the DFD Context diagram: to show input/output of the component as one process o the DFD level 0 diagram: to show input/output of sub-processes in the componentarrow_forward
- Take a project into consideration and map it both with and without architecture. how it will impact the result.arrow_forwardwriteLiterature reviewLiterature review must start with a background for Design and implementation of the exterior and interior decoration design system for interior design offices , the relevant literature must be identified and give reviews of background reading. Students are expected to review/evaluate the literature in comparison with their project tasks. The literature review must include a clear statement of approach to be taken to solve the problem with reference to the background reading.arrow_forwardYour task for this assignment is to create a network diagram for two projects. The activity, immediate predecessor and duration are given. You are to layout-long-hand or using some software-a network diagram for each project. For each diagram conduct a forward and backward pass, calculate the slack, and identify the critical path. When noting your early start, early finish, late start, late finish and slack, please use the format provided. Project 1 Activity Immediate Predecessor Duration A none 3 В A 4 none 6 D none 2 D 5 F В, С, Е 2 Project 2 Activity Immediate Predecessor Duration A none 6 B none 3 A 9 B E в 4 D 2 G E 8. *Note: please use this format. Early Start Duration Early Finish Activity Float Late Start Late Finisharrow_forward
- Drawing the project map with and without the architecture may help. Possible global effects.arrow_forwardIs a project sponsor's job the same throughout the whole SDLC?arrow_forwardProject Communication Plan Diagram - communication plans during development for Attendance fingerprint systemarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning