Fill in the Blank
1 project schedule 2 link
3 phases
4 calendar
5 template
6 note
7 exceptionis
8 predecessor
9 milestone
10 tasks
True/False
1 F
2 F
3 F
4 T
5 F
6 F
7 T
8 F
9 F
10 T
Fill in the Blank
1 assignment
2 cost or material
3 work
4 Duration
5 over allocated.
6 units / unit work
7 work formula
8 resources
9 material resources
10 40
Multiple Choice
1 over allocated
2 Actions tag list
3 an assignment
4 It decreases.
5 in the Assign Resources dialog box when the cost resource is assigned.
6 24 hours
7 Ctrl
8 You can see if the resource assignment affects task duration.
9 variable
rate
‐
10 Resource Sheet
Multiple Choice
1 3 - SD card
2 2 - work the night shift
3 1 - material resources
4 4 - Resource Sheet view
5 3 - adding a resource note
6 1 - material
7 4 - 200%
8 3 - The base calendar gives the basic days/hours for the resource, but the resource's calendar can have exceptions to those days/hours.
9 3 - Change Working Time
10 1 - The information is often confidential.
1.
column headings.
2.
A way to reorder task or resource information in a table and to display summary values according to various criteria you can choose is called a(n) .
3.
The dialog box shows you all of the predefined filters that are available to you for tasks or resources.
4.
A(n) is a way of ordering task or resource information in a view by the criteria you specify.
5.
When you apply a filter, you may see gaps in the order of the .
6.
When you sort data in your project, the sort applies to the active , no matter which table is displayed.
7.
A tool that enables you to see or highlight in a table only the task or resource information that meets criteria you choose is a(n) .
EXPLANATION AROUND THE BREACH:
1. Manipulation of Emissions Tests:
VW installed a "defeat device" in diesel cars, which could detect when the vehicle was undergoing emissions testing.
During tests, the device activated emission control systems, ensuring compliance with regulatory standards.
In real-world driving conditions, however, the emissions control systems were deactivated, leading to higher levels of nitrogen oxide (NOx) emissions.
2. Concealing Actual Emission Levels:
VW marketed their diesel vehicles as "clean diesel," emphasizing lower emissions.
The intentional manipulation of emissions tests allowed VW to circumvent regulations and present a false image of environmental responsibility.
Multiple Choice
Select the best response for the following statements.
1.
Microsoft Project uses _ to determine which tasks can be delayed in order to resolve periods of resource overallocation.
1.
load balancing
2.
random selection
3.
task priorities
4.
task deadlines
2.
Which of the following is the numeric ranking range for task priority? 1.
1 to 100
2. 0 to 100
3. 1 to 500
4. 0 to 1000
3.
Entering a deadline date has no effect on the scheduling of a summary
or subtask, except when the task involves which of the following?
1.
slack
2.
the critical path
3.
relationships
4.
a priority equal to 0
4.
Which of the following is not a semi‐flexible constraint?
1.
Start No Earlier Than
Project 5-4: Establishing Deadline Dates for an Office Remodel
You would like to keep a closer eye on some of the tasks for the lunchroom office remodel project you are managing. You decide it is a good idea to add some deadline dates to several tasks. You know that Microsoft Project will alert you when a task's finish date moves beyond the deadline.
The Office Remodel 5
‐
4 project schedule is available on the book companion website.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
17 The entical path method (CPM) calculates the theoretical early start and fish
dates, and late start and finish dates. The difference between the late and early
start of a task is called
A Free float
B. Feeding buffer
C Danger zone
D Total float
18 Which of the following is NOT a characteristic of a project?
A Ongoing nature
B Uniqueness
C Clear objectives
D Integration of interrelated tasks and resources
19. Which of the following is NOT managed by the project manager?
A. Time, cost and scope
B. The project team
C. The project sponsor
D Expectations of the stakeholders
20 When writing the roles and responsibilities for team members, you should
document the role, authority, responsibility and competency for each team
member. Where must this information be documented?
-A Human resource management plan
B RACI chart
C Resource calendar
D Resource Breakdown Structure (RBS)
21. Which of these is not a component of the scope baseline that is contained in
the project management plan?
A Work…
arrow_forward
Software engineering
arrow_forward
Task
Effort (person-days)
Duration(days)
Dependencies
T1
5
5
T2
11
24
T1
T3
5
10
T4
15
5
T2
T5
10
10
T3
What is the total effort ?What will be the shortest duration of the project, if you can have multiple people working on it ?
a. Effort: 44, Duration: 34
b. Effort: 34, Duration: 34
c. Effort:46, Duration: 46
d. Effort: 46, Duration: 34
e. Effort: 45, Duration: 34
arrow_forward
Figure 23.14 sets out a number of tasks, their durations, and their dependencies. Draw a bar chart showing the project schedule.
arrow_forward
As a project manager of a Software project, you have received given data about the
different type of Issues identified in the project: -
Issue 1 85 occurrences; Issue 2 - 125 occurrences; Issue 3 - 28 occurrences; Issue 4
- 395 occurrences; Issue 5 - 185 occurrences; Issue 6- 128 occurrences; Issue 7 – 85
occurrences; Issue 8 169 occurrences; Issue 9 - 148 occurrences; Issue 10
209
occurrences.
-
-
Which diagram you will use to prioritize the Issues? Generate the diagram using any
tool and paste it here.
arrow_forward
10 Which of the following is a classic organizational structure?
A Functional
B Projectized
C Composite
D Matrix
11 Defining a new project or a new phase of an existing project relates
to
A Initiating process.
B. Planning process
C Scope management process
D. Control process
12 If you are developing a Project Management Plan, how should you determine
the level of detail to be included in the plan?
A Always only provide a summary or high level plan
B Include only the details your manager specifically requested
C Always provide the maximum level of detail possible
D. Provide the level of detail based on the project complexity and application area
13 Midway through a project, a project manager determined that the project was
running way behind schedule. If the project manager needs to shorten the project
schedule, without changing the project scope, which of the following schedule
compression techniques could be applied?
A. Crashing
B. Reserve Analysis
C. Forecasting
D. Last Tracking
14.…
arrow_forward
As a project manager of a Software project, you have received given data about the different type of Issues identified in the project: –
Issue 1 – 85 occurrences; Issue 2 – 125 occurrences; Issue 3 – 28 occurrences; Issue 4 – 395 occurrences; Issue 5 – 185 occurrences; Issue 6 – 128 occurrences; Issue 7 – 85 occurrences; Issue 8 – 169 occurrences; Issue 9 – 148 occurrences; Issue 10 – 209 occurrences.
Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.
arrow_forward
Generate a schedule of project in Gantt chart to observe the task timeline and progress.
arrow_forward
ded
The network dlagram and task times for a project are shown below.
Task
A₁
A₂
A₁
A2
Late start time
A3
A4
00
As
Duration (days)
65926
A3
A4
A5
What is the late start time for activity A3 ?
4x days
arrow_forward
SYSTEM ANALYSIS AND DESIGN ( COMPUTER
SCIENCE)
Instruction:
As a system analyst, you are required to analyze and propose a system
design for your client company to help in their daily business process.
Choose ONE (1) of the following system and discuss the development
process in detail.
Online Tuition Center
- Online Babysitter
- Online Cleaning Service
Online Event Management
- Online Emergency Management
- Online Personal Shopper
Question 1
a) Identify the appropriate system development method and explain
why it is suitable for the system.
b) List all the possible functions applicable to the system.
c) Create a Gantt chart for the system analysis and design proposal. You
may use the outline provided as a guideline for your Gantt Chart
Outline for Gantt chart
System Investigation
- Introduction
- System Request Form
- Project Proposal
- Feasibility Studies
- Fact Finding Techniques Used
- List of End-user Requirement
System Analysis
- Proposed Actors & Use cases
- Proposed Use case…
arrow_forward
Which of the following statements is false?
A work breakdown structure is a hierarchical structure that identifies the project’s resources by category and type.
Duration and effort are not synonymous terms.
A three-point estimate includes an optimistic, most likely, and pessimistic estimate.
A Gantt chart is a common tool for displaying project schedule information.
arrow_forward
Q2/You are given the following data about *
the project tasks, network, and crash
times/costs. Calculate the cost of the
project at all time durations until you can
no longer crash the project.
Time in weeks
Cost in $.
Activity
Normal Crash
Normal Crash
A
16
11
$36,000 $38,000
B
26
18 $27,000
$33,000
C
26
21
$8,000
$8,900
D
30
23
$135,000 $138,570
E
28
20
$20,000 $22,400
F
27
23
$12,000 $13,700
G
18
12
$35,000 $36,500
Total
$273,000 $291,070
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Related Questions
- 17 The entical path method (CPM) calculates the theoretical early start and fish dates, and late start and finish dates. The difference between the late and early start of a task is called A Free float B. Feeding buffer C Danger zone D Total float 18 Which of the following is NOT a characteristic of a project? A Ongoing nature B Uniqueness C Clear objectives D Integration of interrelated tasks and resources 19. Which of the following is NOT managed by the project manager? A. Time, cost and scope B. The project team C. The project sponsor D Expectations of the stakeholders 20 When writing the roles and responsibilities for team members, you should document the role, authority, responsibility and competency for each team member. Where must this information be documented? -A Human resource management plan B RACI chart C Resource calendar D Resource Breakdown Structure (RBS) 21. Which of these is not a component of the scope baseline that is contained in the project management plan? A Work…arrow_forwardSoftware engineeringarrow_forwardTask Effort (person-days) Duration(days) Dependencies T1 5 5 T2 11 24 T1 T3 5 10 T4 15 5 T2 T5 10 10 T3 What is the total effort ?What will be the shortest duration of the project, if you can have multiple people working on it ? a. Effort: 44, Duration: 34 b. Effort: 34, Duration: 34 c. Effort:46, Duration: 46 d. Effort: 46, Duration: 34 e. Effort: 45, Duration: 34arrow_forward
- Figure 23.14 sets out a number of tasks, their durations, and their dependencies. Draw a bar chart showing the project schedule.arrow_forwardAs a project manager of a Software project, you have received given data about the different type of Issues identified in the project: - Issue 1 85 occurrences; Issue 2 - 125 occurrences; Issue 3 - 28 occurrences; Issue 4 - 395 occurrences; Issue 5 - 185 occurrences; Issue 6- 128 occurrences; Issue 7 – 85 occurrences; Issue 8 169 occurrences; Issue 9 - 148 occurrences; Issue 10 209 occurrences. - - Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.arrow_forward10 Which of the following is a classic organizational structure? A Functional B Projectized C Composite D Matrix 11 Defining a new project or a new phase of an existing project relates to A Initiating process. B. Planning process C Scope management process D. Control process 12 If you are developing a Project Management Plan, how should you determine the level of detail to be included in the plan? A Always only provide a summary or high level plan B Include only the details your manager specifically requested C Always provide the maximum level of detail possible D. Provide the level of detail based on the project complexity and application area 13 Midway through a project, a project manager determined that the project was running way behind schedule. If the project manager needs to shorten the project schedule, without changing the project scope, which of the following schedule compression techniques could be applied? A. Crashing B. Reserve Analysis C. Forecasting D. Last Tracking 14.…arrow_forward
- As a project manager of a Software project, you have received given data about the different type of Issues identified in the project: – Issue 1 – 85 occurrences; Issue 2 – 125 occurrences; Issue 3 – 28 occurrences; Issue 4 – 395 occurrences; Issue 5 – 185 occurrences; Issue 6 – 128 occurrences; Issue 7 – 85 occurrences; Issue 8 – 169 occurrences; Issue 9 – 148 occurrences; Issue 10 – 209 occurrences. Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.arrow_forwardGenerate a schedule of project in Gantt chart to observe the task timeline and progress.arrow_forwardded The network dlagram and task times for a project are shown below. Task A₁ A₂ A₁ A2 Late start time A3 A4 00 As Duration (days) 65926 A3 A4 A5 What is the late start time for activity A3 ? 4x daysarrow_forward
- SYSTEM ANALYSIS AND DESIGN ( COMPUTER SCIENCE) Instruction: As a system analyst, you are required to analyze and propose a system design for your client company to help in their daily business process. Choose ONE (1) of the following system and discuss the development process in detail. Online Tuition Center - Online Babysitter - Online Cleaning Service Online Event Management - Online Emergency Management - Online Personal Shopper Question 1 a) Identify the appropriate system development method and explain why it is suitable for the system. b) List all the possible functions applicable to the system. c) Create a Gantt chart for the system analysis and design proposal. You may use the outline provided as a guideline for your Gantt Chart Outline for Gantt chart System Investigation - Introduction - System Request Form - Project Proposal - Feasibility Studies - Fact Finding Techniques Used - List of End-user Requirement System Analysis - Proposed Actors & Use cases - Proposed Use case…arrow_forwardWhich of the following statements is false? A work breakdown structure is a hierarchical structure that identifies the project’s resources by category and type. Duration and effort are not synonymous terms. A three-point estimate includes an optimistic, most likely, and pessimistic estimate. A Gantt chart is a common tool for displaying project schedule information.arrow_forwardQ2/You are given the following data about * the project tasks, network, and crash times/costs. Calculate the cost of the project at all time durations until you can no longer crash the project. Time in weeks Cost in $. Activity Normal Crash Normal Crash A 16 11 $36,000 $38,000 B 26 18 $27,000 $33,000 C 26 21 $8,000 $8,900 D 30 23 $135,000 $138,570 E 28 20 $20,000 $22,400 F 27 23 $12,000 $13,700 G 18 12 $35,000 $36,500 Total $273,000 $291,070arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning