will manage the design, construction and commissioning of the Alpha Machine Shop. Project Manager will hand over Operations of the Alpha Machine Shop to the operations management team prior to the official opening. Alpha Consulting Board of Directors will retain approval authority for all critical design, marketing and financial decisions throughout the project. Project team resources include the Project Manager, Project Leader (Design & Construction), Team Leader (Financial), Team Leader (Procurement), Team Leader (Human Resources) as well as a Marketing Manager. A contracted firm, overseen by the Project Manager, will carry out construction & commissioning activities.
The Work Breakdown Structure (WBS) describes the high level activities and schedule for the project. Subsequent planning activities will break high level activities down further into tasks. Level three schedule will be prepared which will break down the lengthy tasks into subordinate tasks. The schedule also identifies the “critical path” of activities and milestones, which must be met to achieve the target opening date of January 1st 2018.
Project duration is from September 2016 to December 2017, a period of 16 months. The total project cost is $5,329,700, based on a Class B estimate, with a range of +25% to -10%. The project risk is low for Phases 1 (preconstruction), 2 (construction), Phase 3 (Post construction) and Operations. Risk management and mitigation are dealt with at length in the
PROJ 592 All Discussions Week 1 - 7 Purchase here http://devrycourse.com/proj-592-all-discussions-week-1-7 Product Description PROJ 592 Week 1 DQ 1 WBS Construction PROJ 592 Week 1 DQ 2 Project Cost Estimates and Assumptions PROJ 592 Week 2 DQ 1 Cost Components PROJ 592 Week 2 DQ 2 Estimating Processes PROJ 592 Week 3 DQ 1 Project Schedules PROJ 592 Week 3 DQ 2 Sensitivity Analysis PROJ 592
A project has been estimated to take six weeks and cost $130,000. Cost and percent complete data are provided in the table below through 3 weeks of the project. % scheduled data can be obtained from the Gantt chart following the table.
Work breakdown structure (WBS) showing discrete work tasks and grouped hierarchically that helps to organize and define the total work scope of the project
A project has been estimated to take six weeks and cost $130,000. Cost and percent complete data are provided in the table below through 3 weeks of the project. % scheduled data can be obtained from the Gantt chart following the table.
Phase 1 and 2, construction expenses, will cost around $1,138,223. Phase 3 and 4, operation expenses, will cost $499,306 on average. In summary, our project is estimated to reach a total of $1,637,529. Half of the cost which is $818,764.50 will be funded by Manhattan Construction Company. We are requesting the Dallas Chambers of Commerce to be our sponsor and support our fund by providing the other half of our budget.
As Russell Menere, I recommend the management of Boeing Australia Limited to follow the footsteps of Boeing Seattle to adopt and implement cost effective e-Procurement system, which can be interfaced with the legacy information system as we have IT infrastructure in place that is our core strength.
Activities A, B, and C are the starting tasks, while activities I and J are the end activities of the project. Dummy activities Start and Finish with duration 0 are added in the network diagram to make the calculation of critical paths simpler (You can remove these dummy variables if you want). Following duration for each activities are provided:
This will be a perfect project to accept due to life span stay between 2 to 3 years. This will be within company’s policy.
Work Breakdown Structure (WBS) is a tool that is used to define the work elements of a project and identify its entire scope. It is the map of the project which identifies all elements of the project and allows managers to keep track and control of it. It is made of a hierarchy which facilitates the evaluation of cost, time and performance at all levels of the project life-cycle and organization. The structure illustrates the smaller units and allows for adaptation and quick communication if there a problems which need to be addressed. Definitions of each task should be clear and avoid overlapping in
So we will set up milestones that show deadlines the date, mean by finish a task which a milestone is a task with zero duration. We think that a milestone is most important in a log cabin project as it show important dates on the project plan and often key events, but it does not affect any of the Gantt chart calculations. Overall, the work breakdown structure (WBS) to make complex a log cabin project more management while the WBS is designed to help breakdown this project into manageable chunk that can be effectively estimated. Also a WBS helps to explain a log cabin project scope to the stakeholder, supplier and labor.
essful project completion. The project has a low risk of failure with a high potential of success that will mean high profits and the potential for future projects in this housing market.
At the Second Level of the WBS the level one task are decomposed. The second levels of the WBS consist of the major task needed complete each phase of the level one task. As a result the first level task of gathering and implementing requirements is made up of the smaller task such as Architecture review, systems requirements, integration and deployment. Each of these task need to be completed to deliver the level one task.
A work breakdown structure (WBS) will develop for this project and the WBS is based on the project charter, scope statement, and other relevant information. Gantt chart and network diagram also will be well prepared for this project. While preceding the planning stage, the resource usage cash flow report will showing the hours each person is assigned to work on each task each week. Furthermore, the probability/ impact matrix and list of prioritized risks for the project will be included in the project
The work breakdown structure (WBS), even for the project of PCB, should allow for the leadership team to view an evaluate the the plan with ease. Objectives are organized under categories that allow for specific tasks to be broken into sub-tasks, processes, or other levels of detail, making it uncomplicated for team members to identify time and resources needed (CSU-Global, 2013). To ensure that no steps are missing, a WBS is outlined from the start of the project for phototool testing, to include the initiation.
During the construction project following factors can be effect the cost of the complete project and these factors will be helpful during the estimation of the complete project. Choice of management varies, dependant on size, complexity and duration of project.