a) Draw the network diagram for this project b) Calculate for the slack time c) Find the critical path d) When is the project completion time
Q: A plumber has decided to use the techniques of project management in order to plan a job. He knew…
A: The critical path method in project management is the longest set of activities that must be…
Q: The following table provides the information necessary to construct a project network diagram and…
A: Project crashing is a process which reduces the total duration using additional costs. Here, we can…
Q: Q2: For the activities shown below determine: . The duration of project . The critical path by using…
A: ANSWER IS AS BELOW:
Q: Consider the following information for a project to add a drive-through window at Crestview Bank.a.…
A:
Q: A. Construct a network for the project outlined below and determine the critical path time B.…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: a. Draw a project network. b. What is the critical path? c. What is the normal project cost? d.…
A: Find the Slope calculations below:
Q: a. Construct a CPM network for the design project. b. Compute the EF, LF, and slack for each…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: a. Draw a project network. b. Identify the critical path. e Develop the activity schedule for the…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: 1. Draw the network diagram. 2. Calculate the expected duration and variance of each activity. 3.…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Consider the following information for a project to add a drive-through window at Crestview Bank. a.…
A: b. The critical path is B-E-G-H. c. Slack for the activities A and D are 8 each.
Q: The figure shows the network diagram of a project along with the activity durations (T). In this…
A: A project schedule network diagram shows the sequential and analytical connection between tasks in a…
Q: a. Construct the network diagram for this project. b. Determine the earliest and latest start times…
A: Below is the solution:-
Q: a. Construct the network. b. How long will it take to finish the project? c.. What is the critical…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: league baseball team. Draw a project network given the information in the table that follows.…
A: Find the answers below: Given Details: Given details: ID Description Predecessor Time…
Q: (1) Find the Early Start / Early Finish Time of Each Activity (2) Find the Late Start / Late Finish…
A:
Q: Draw the project PDM. b. Determine the critical path. c. Calculate the total slack time. а.
A: In this question, I would first determine the expected activity time for each activity, based on the…
Q: A project's activities must be completed in the sequence indicated below. Activity Immediately…
A: Here, It is CPM or critical path method problem, for this problem, I have following data like…
Q: (c) Compute the earliest start, earliest finish, latest start and latest finish time and the slack…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: 1. Draw a project network given the following information. 2. Complete the forward and backward pass…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Solve the following project by hand and submit your notes: Activity Normal Time Crash Time Normal…
A: Please find the attached network diagram below-
Q: (2) Cables By Us is bringing a new product on line to be manufactured in their current facility in…
A: The critical path method (CPM), or critical path analysis (CPA), is a calculation for booking a…
Q: (1) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical connection between tasks in a…
Q: a) Draw the network diagram. What is the project completion time? What is the critical path? b)…
A: The network diagram is a graphical representation of the project and is made up of a series of…
Q: The following CPM network has estimates of the normal time in weeks listed for the activities: (в(2)…
A: Since you have posted a question with multiple subparts, as per guidelines we need to answer for the…
Q: The following information has been gathered for a project to install a new machine lathe at Diamond…
A: Given Information:
Q: a) Draw an AON diagram of the project, including activity durations. b) Define the critical path,…
A: In project management, there are two types of networks. One is AON and the second is AOA. AON…
Q: 1. Activity Preceding activity Activity duration A - 6 B - 3 C B 1 D A, C 2 E…
A: Given Information:
Q: 1. Determine the amount of slack in each of a project's activities (presented below), and identify…
A: We’ll answer the first question since the exact one wasn’t specified. Please submit a new question…
Q: A project manager has compiled a list of major activities that will be required to install a…
A: The Time estimate can be calculated using formula = (Optimistic+4*Most Likely+Pessimistic)/6 Std Dev…
Q: Table 1 Activities Immediate Predecessors Time (In Days) A 9. -- В A C A 9. B,C 6. E В, С 7 F 10 G E…
A:
Q: . CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL…
A: Activity-on-node is a therm related to project management. It directs to a precedence diagramming…
Q: 1. Draw the network diagram. 2. Calculate the expected duration and variance of each activity. 3.…
A: The project network is the diagram that shows the order of completion of project network activities…
Q: (a) Construct a project network. (b) Determine the expected times and variances for each activity.…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: The Industrial and Systems Engineering Department at Sun University is moving from its old building…
A: Project management is the management in which different kinds of skills, techniques, processes, and…
Q: 1. Construct the PERT network for this project 2. Compute for the Earliest Start Time and Latest…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(1, 2,…
Q: a Draw the Network diagram on your own paper. b. How many paths are there in the network? c. What is…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: (a). Draw the Activity on Node (AoN) network diagram. (b). Find the critical path and write that…
A: Below is the solution:-
Q: a) Construct a network for this project b) Find a project schedule to minimize the completion time…
A: Given data is
Q: REQUIRED: a. Calculate t,(expected time) for each activity. For each activity, the estimates are to,…
A: Answer is as below
Q: From the following information, develop an AON project network. Complete the forward and backward…
A: Given Information:
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A:
Q: Consider the following project activities: | Duration Activity Predecessor (DAY) 4 A A 3 A 5 D E C F…
A: Activity Predecessor Duration A - 4 B A 3 C A 3 D B 5 E C 2 F C 1 G D, E 6 H F, G 5
Q: The fo llowing is a table of activities associated with a project at Rafay lshfaq's software firm in…
A: Note: As per the Bartleby guidelines only the first three parts have been answered. AOA ( Arrow to…
Q: a) Draw the project network using AON. b) Identify the critical path. c) What is the expected…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Questions 1. Organize the information above in an activity precedence table showing the activity,…
A: Answer of all pats are below:-
Q: Activity Preceding Time A 8 -- B 3 -- A 7 D А, В 3 E C 4 F 6 a. Draw the network diagram. b.…
A: given, Activity Preceding Time A - 8 B - 3 C A 7 D A,B 3 E C 4 F D 6
Q: a. Calculate the expected time and variance for each activity. . Calculate the activity slacks and…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Draw the project network diagram. 1. What is the total time required to complete the project if no…
A: Network analysis (NA) could be a set of integrated techniques to depict relations among actors and…
Q: a. Construct the project network b. Determine the critical path c. Find the completion time of the…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Help me anwser the questions. Thank you in advanced.
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
- #3) Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and no task by be crashed to more than half its original duration and tasks A and N cannot be crashed at all? Task Predecessors Most Likely Duration A - 8 B A 12 C A 6 D A 12 E B 10 F E 7 G C 18 H C 13 I G 10 J H 13 K D 10 L K 11 M L 7 N F, I, J, M 4 Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.Construct an activity network diagram using Table 3a. Activity A B C D E F G Predecessors - - A A,B D C,E E Expected Time(WKS) 7 9 12 8 9 6 5 Table 3a Activity Durations and relationship Conduct a forward and backwards pass for the activity network diagram that you have constructed and identify the critical path and its duration. Calculate the slack on all of the activities, and proceed to analyze how knowing the slacks can help to manage schedule risk the a project 3b. Assuming that there is the risk of exceeding the project schedule baseline for 7 weeks, critically evaluates the options available that could be used to bring the project on trackThe following represents a project with known activity times. All times are in weeks.Activity ImmediatePredecessor TimeA - 4B - 3C - 1D B 2E A 3F C, E 5G D 3H F 2I G, H 3J I 6K I 4L J 21) Create a CPM Network. 2) What is the total project time? 3) What activities are on the critical path?4) Compute the slack time for all non-critical activities. 5) What is the latest possible start time for activity D? Please show all work in excel and how you did it, Thank you!
- A project has these activities, precedence relationships, and activity durations: Activity Immediate Predecessor Activity Activity Duration (Week)a * 3b * 4c * 3d c 12e b 5f a 7g e,f 3 a. Draw a CPM network for the project. b. Provide an overview for the project by computing the duration for each path. c. What is the critical path? What is the project's estimated duration?To be able to meet delivery dates, a project consultant intimates that a project should be analyzed with activities as follows: ACTIVITY IMMEDIATE PREDECESSOR EXPECT DURATION (WEEKS) A. Initial discussion none 3 B. product design none 5 C. Market survey B 3 D. market evaluation A,C 4 E. product costing D 8 F. sales plan C 2 G. product pricing F 4 H. prototype F 2 I. master inform B 5 J.prototype testing HEG 3 (i) Draw a network to represent the various activities of the project.(ii) Draw up a table showing for each activity, the earliest and latest start and finish times and total float/slack.(iii) Determine the critical path and project duration.(iv) As a management science student, advise the management about the effect on the project completion time If the start time of activity A is delayed by 3weeks, activity G is delayed by 8 weeksUsing the information in Table-1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Task Description Duration (WorkingDays) Predecessor/s A Requirement Analysis 5 B Systems Design 15 A C Programming 25 B D telecoms 15 B E Hardware Installation 30 B F Integration 10 C, D G System Testing 10 E, F H Training/Support 5 G I Handover and Go-Live 5 H (i) Determine the critical path of the project (ii) Calculate the planned duration of the project in weeks (iii) Identify any non-critical tasks and the float (free slack) on each.
- a) Explain the purposes of a dummy activity in a network diagram. (b) Table 1 shows the activities of a project and their durations. Table 1Activity Preceding Activity Duration (Days)A – 9B – 3C A 8D A 2E A 3F C 2G C 6H C 1J B,D 4K F,J 1L E,H,G,K 2M E,H 3N L,M 4 i. Draw the project network.ii. Determine its critical path and completion time.iii. Calculate the total float for the non-critical chains. 2. a) Outline FOUR different types of stockholding casts. b) i) Explain the periodic review system of inventory control.ii) State TWO disadvantages of the periodic review system. c) Explain FOUR major functions of an office. d) A common trend in the office management in many large manufacturing organizations today is to set up an ‘organization and method’ (O&M) team, which is normally directly answerable to the Chief Executive Officer. Highlight FOUR responsibilities of such a team. 3. a) State FOUR objectives of maintenance in a manufacturing plant. b) Explain the purpose of the…To design a new app, a project manager has gathered the time information foreach activity as shown in the following table:Activity Predecessors Optimistic Most Likely PessimisticA / 1 4 7B / 2 6 10C B 3 3 9D A 6 13 14E A, C 4 6 14F B 6 8 16G D,E,F 2 5 8Identify the critical path. How much slack time is associated with each noncritical activity?Suppose you wanted to have 99% confidence in the project finishing on time. How manyweeks in total would your project team need to achieve this 99% likelihood?Q: (a) How value engineering can reduce overall project duration? Can you give any practical example? (b) What will be the difference in duration of dummy activity for simple and complex arrow networks? (c) Draw arrow network for the following given project. Picture of table is attached at the end.
- Please assist in detailed explanation on the following question in Project Scheduling: 1) - A company decides to plan a project, with activities, precedence and deterministic durations given in the following table: Activity i Duration (days) Immediate Predecessors A 32 none B 21 none C 30 none D 45 A E 26 A, B F 28 C G 20 E, F Questions: 1.1) What method should be used? Using only one pseudo-activity, draw the project network, with arcs labeled by the activity name and duration. 1.2) Compute and display in a table the earliest and latest starting and finishing times, as well as slack, for each activity, and identify the critical path(s). 1.3) Draw a Gantt chart of the schedule, based on earliest starting times 1.4) Which activities must be completed by day 60 to ensure that the project is not delayed?Given the following information, a. Draw a project network. b. Complete the forward and backward pass, compute activity slack, and identify the critical path. c. How sensitive is the network schedule? Briefly justify your answer? d. Which activities have free slack? Activity Predecessor Duration (days) A None 10 B None 20 C A 10 D A 30 E B 10 F C 30 G C, D 20 H D, E 10 I F, G, H 20Draw a network representation of the project (nodes = activities, arrows = precedence constraints). Provide early start/early finish as well as late start/late finish times for all activities. What is the duration of the project, and which tasks are on the critical path? Task Description Duration Predecessors A Project Planning 16 days - B Evaluation Existing Apps 20 days - C Define Value Proposition 12 days B D Define User Interface 18 days B E Define Technology Requirements 22 days C and D F Document Requirements 14 days E G Develop Architecture 35 days A and F H Creation Code Design 18 days G I Roadmap Feature Development 12 days G J User Interface Development 74 days H and I K Code Development 92 days H and I L Release Testing 32 days J and K M Get User Feedback 22 days L N Bug Fixing 28 days L O Marketing Plan 54 days E P Release Product 5 days M, N and O