A Project ACTIVITY 2-3 has 3-5 4-5 4-6 5-7 6-7 7-8 7-9 8-10 9-10 the Construct find the find the OPTIMISTIC 1 1 1 3 3 4 6 2 following characteristics: 5 1 3 the PESSIMISTIC 3 network 5 5 24 7 6 8 6 8 MI 3 7 MOST LIKELY TIME 7 3 F 44 3 5 4 6 2 5 Critical path and Variance for each Event project duration at 95% probability.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter10: Introduction To Simulation Modeling
Section: Chapter Questions
Problem 55P
icon
Related questions
Question
A
Project
ACTIVITY
2-3
2-4
3-5
4-5
4-6
S
Lo
6
hus
7
7-8
7-9
8-10
9-10
Ⓒfind
Construct
find the
the following Chorracteristics:
OPTIMISTIC
the
1
1
3
3
4
6
2
5
1
3
the
PESSIMISTIC
network
5
5
4+
7
6
6
8
3
7
MOST LIKELY
3
44
3
5
4
6
5
Critical path and Variance for each Event
at 95% probability
duration
Project
Transcribed Image Text:A Project ACTIVITY 2-3 2-4 3-5 4-5 4-6 S Lo 6 hus 7 7-8 7-9 8-10 9-10 Ⓒfind Construct find the the following Chorracteristics: OPTIMISTIC the 1 1 3 3 4 6 2 5 1 3 the PESSIMISTIC network 5 5 4+ 7 6 6 8 3 7 MOST LIKELY 3 44 3 5 4 6 5 Critical path and Variance for each Event at 95% probability duration Project
Expert Solution
steps

Step by step

Solved in 4 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,