A project has the following activities, with specified precedents and expected durations (in days). How much slack does Activity E have? Answer: Activity PrecedentDuration A B C D E F G H . A A B B C DE 3 3.9 6 6 4.1 4 6.2 8
Q: Please explain why it is necessary to have a project manager for complicated projects.
A: A project manager is crucial to the accomplishment of a challenging project. Given the numerous…
Q: Graph the region determined by the constraints.Then find the maximum value of the given objective…
A: Objective : 2x+3yConstraint i: x≥0 , y≥0Constraint ii : x+y≤8Constraint iii: 3x+2y≥6
Q: The United States is a rapidly changing, diverse, immigrant nation. Discuss this with respect to the…
A: Immigrants are people who come to a new country to live permanently or temporarily. There are…
Q: What did you learn from this example? Questions you have?
A: Through the development of a large-scale COVID testing facility, the Lighthouse Labs initiative…
Q: .Explain quality management standards 2.Outline the principles of “Total quality Management’’ TQM.…
A: Quality management is the systematic processes, activities, and techniques executed by an…
Q: A value proportion defines the product or service that an enterprise is producing with the aims at…
A: A small GPS tracking device that may be connected to priceless items is what Brenco, a security and…
Q: Discuss the many financial aspects of the project. There is a possibility that using project…
A: To guarantee that a project achieves its goals effectively and efficiently, operations management…
Q: discuss importance of project resource planning and its impact on project success
A: Planning and organizing resources is a tried-and-true method for maximizing resource utilization…
Q: 3.1Identify five common underlying causes of resistance to change. 3.2Explain how you can…
A: 1) Fear of the unknown = People has a fear because they are unsure of how a change would affect…
Q: 4. The table shows projected cost for all possible combinations of four workers and job waiting…
A: Ans) Problem is balanced, 4 jobs 4 workers. Each job should be assigned to 1 worker and minimize the…
Q: Many firms have made significant strides in reducing their inventories. Which of the following would…
A: Absorption costing, also referred to as full costing or traditional costing, is a widely utilized…
Q: Is it possible for projects to derive multiple advantages from the Internet? What sets apart these…
A: The Internet has become an indispensable tool for all sorts and sizes of businesses and…
Q: Operations could be considered as a sub-system of an organization". Explain this statement…
A: Operations management is function that designs, manages, and controls the production of goods and…
Q: What are some of the goals that should be accomplished by using a control system?
A: A control system is a set of processes, procedures, and mechanisms put in place to monitor, measure,…
Q: In relation of structural approach based on comparison of the time horizon, what remain unchanged in…
A: An analytical framework or perspective known as the structural approach focuses on the underlying…
Q: In order to promote the College of Engineering, IT and Environment, the college asks you to organize…
A: To promote the institution, the Institution of Engineering, IT, and Environment has asked for an…
Q: Which of the following is a match between the type of supply chain and the type of product? Group…
A: Supply chain management is all about managing supply chain activities effectively. All the…
Q: Design a brief research proposal with a topic of your choice derived from your area of study.…
A: Business research is the systematic as well as objective investigation of business-related topics,…
Q: Describe the key elements of project management and the skills required for successful project…
A: Project management is about planning and organizing the resources of the company. These resources…
Q: office complex is to be renovated. Before the job can be completed, various tradespeople and skilled…
A: Basic Formulas and Structure: Diagram: a)
Q: In this M2M example, the advantages of a loT-based solution are shown with the help of a current…
A: IoT (Internet of Things) and M2M (Machine-to-Machine) communication are two concepts that have…
Q: What were the factors that led to the project’s success? what techniques were used
A: The project's success is a result that meets the clients, customers, or various stakeholders, such…
Q: Given the following activity network: (3 activities A1, A2, & A3; arrows point from A1 to A2 & A1 to…
A: Find the Given details below: Activities Predecessor Duration A1 - 5 A2 A1 7 A3 A1 (4*50%)…
Q: The new Fore and Aft Marina is to be located on the Ohio River near Madison, Indiana. Assume that…
A: Find the Calculation methods below: Single server: Multiple servers: Total cost: Total cost = Cw*L…
Q: Question 34 Consider the processing times and priorities for four jobs: Job Processing time…
A: Processing time refers to the amount of time required to complete a specific task or job. In the…
Q: Why is Lyft cheap than Uber? Explain
A: Lyft is often perceived as cheaper than Uber due to various factors. Below are few of those factors:
Q: Business case: an architecture construction and interior design company with our own retail line. •…
A: The architecture, construction, and interior design industry is highly competitive, demanding…
Q: Given the following activity network: (3 activities - A1, A2 & A3; arrows point from A1 to A2 and A1…
A: A network diagram shows the link of each task with the duration taken by each activity with respect…
Q: How can companies compare the performance of divisions operating in different countries? What are…
A: Comparing performance of divisions operating in different countries is essential for multinational…
Q: C&A sells 600 bottles of a dietary supplement per week at $100 per bottle. The supplement is ordered…
A: Total ordering and holding cost can be calculated using the average inventory and number of orders…
Q: Describe the obstacles that governments and businesses encounter when trying to improve…
A: It is crucial that transport networks continue their digital transformation, using state-of-the-art…
Q: The following information is available: Direct labour hours taken to manufacture the first two…
A: Hours for the first unit: 60 Hours for the second unit: 48 The learning curve formula is given by:…
Q: The schedular at ZamTech uses MPS time-phased records for planning and item production. The planner…
A: Find the Given details below: Weeks 1 2 3 4 5 6 7 8 Forecast 130 130 130 140 140 140 145 145…
Q: 2.7 Which of the following help explain how the Reorder Point (ROP) works in conjunction with the…
A: Here, we know that Reorder point or ROP works in conjunction with the economic order quantity, the…
Q: we have seen various methods to set control limits for control charts. Which method would you prefer…
A: There are several methods to set control limits for control charts, these methods are Variable…
Q: what forces of business are involved in the podcast What Skills Are You Missing as an Entrepreneur…
A: Entrepreneurship is the process of identifying, creating, and pursuing opportunities to establish a…
Q: Identify the range of output for which each alternative is superior(has the lowest cost) 2. If the…
A: A crossing point is a inventory level which specify the same total costs for two method. The…
Q: To complete an assembly line in a factory, the major steps and seven activities involved are shown…
A: The calculations for the given project network is given below:
Q: What is the overall duration of the project (in weeks)? 28 weeks What is the earliest week you could…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: A successful public relations campaign begins ends with research. * Why is research important in…
A: NOTE: We are allowed to do one question only at a time. Research is the systematic process of…
Q: a). If he uses the maximin criterion, which size bus will he decide to purchase? b). If he uses the…
A: Here, for each option, I have been given three demand states, and I would apply each specific…
Q: When compared to the idea of "quality improvement," what is the difference between benchmarking and…
A: Benchmarking is a process of measuring an organization's performance against the best practices of…
Q: If carrying costs are $2 per year for each stone, find the order quantity that will minimize total…
A: Here, given that the usage rate is 25 stones per day, The annual demand =usage rate×200 The annual…
Q: Discuss your thoughts on the value of developing case diagrams. Do you believe case diagrams will…
A: A process refers to a series of steps or actions performed in a systematic manner to achieve a…
Q: Advise Mr. Kingo Meliki a small scale manufacture of soft drinks in your city on the usefulness of…
A: Break Even Analysis is a financial tool used to determine the point at which a business generates…
Q: What mean by structural change? a) Bad Publicity b) Layoff c) Weakened Engagement Should Yes or no ?…
A: Significant changes in an organization's fundamental structure, procedures, or systems are referred…
Q: Case Analysis: Report Cites Procurement Flaws in Districts A study was conducted in Uganda and…
A: Creating a specification document for the distribution of electronics, furnishings, and home…
Q: Visakha steel a company that supplies steel bundles to a construction company is having 250-day…
A: Answer) To determine the optimal number of steel bundles to obtain per order, we need to calculate…
Q: Make sure to include a concise description of the training and certification requirements, in…
A: Operational management is a critical function in any organisation, ensuring that business processes…
Q: Using just a few phrases, please explain how the management of a plant may significantly boost EVA…
A: Economic Value Added (EVA) is a financial performance metric that measures the difference between a…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
- g. Which activities can be delayed? h. If activity B were delayed by 2 days, how long can activity G be delayed without delaying the whole project?You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…
- Construct the DATA SHEETS with ES, EF, LS, LF, TF, FF, AND INDF. What is the duration of the project? Identify the critical path. How many days can ACTIVITY C be delayed without extending the duration of the whole project?Which project management approach follows a deterministic approach and assumes the activity duration is a known certainty? a) PERT b) CPM c) Network Diagram d) JIT e) ABCWhat is/are the consequence(s) of positive slack or negative slack in execution of projects? How can they be prevented or encouraged? Give examples in support of your statements.
- The project manager must make trade-offs between project progress and process. Conceptually, this involves trade-offs between the __________ functions. a. schedule and cost b. technical and managerial c. cost and performance d. performance and scheduleA) What is the variance activity B? 2 decimal places B) What is the variance of activity F? 2 decimal places C) what is the probability the project can be completed? 4 decimals places only D) what is the probability the project will be 3 weeks late from the expected completion time ? 4 decimal places only.Which activity should be crashed to reduce the project completion time by one day? -Activity E -Activity A -Activity C -Activity B
- Use the following project status information to calculate each of the requested EVM numbers below (a-i).The project status is reported at the end of week 13. Task Budget Cost Budget Duration Status as of Week 13 A $5,000 2 Weeks 100 percent complete $5,000B $8,500 3 Weeks 100 percent complete $9,000C $15,000 4 Weeks 75 percent complete $14,000D $10,000 4 Weeks 50 percent complete $9,000 E $12,000 4 Weeks Not startedF $15,000 5 Weeks Not started a. Planned Valuedb. Actual costc. Cost varianced. Schedule variancee. Cost performance indexf. Schedule performance indexg. Budget at completionh. Estimation to completei. Estimation at completionYou may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…