Analyze power system as shown in Fig. 3 subject to (a) Line to Ground bolted fault (b) Line to Line Bolted Fault occurred at bus 2. Compare values of symmetrical and unsymmetrical values of fault currents and fault voltage at fault bus under (a) Line to Ground Bolted Fault (b) Line to Line Bolted Fault. Pre-fault voltages can be assumed as 1+ 0j =1< 0° per unit. Transformers T1 and T2 have 345 Y / 20 A KV Transformation Ratio. Power Plant – I Power Plant – II (2) 3) Generator Generator Transmission Line 1

Power System Analysis and Design (MindTap Course List)
6th Edition
ISBN:9781305632134
Author:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Chapter7: Symmetrical Faults
Section: Chapter Questions
Problem 7.15P
icon
Related questions
icon
Concept explainers
Question
Analyze power system as shown in Fig. 3 subject to (a) Line to Ground bolted fault (b) Line to Line Bolted
Fault occurred at bus 2. Compare values of symmetrical and unsymmetrical values of fault currents and
fault voltage at fault bus under (a) Line to Ground Bolted Fault (b) Line to Line Bolted Fault. Pre-fault
voltages can be assumed as 1+ 0j = 1 < 0° per unit. Transformers Tị and T2 have 345 Y / 20 A KV
Transformation Ratio.
Power Plant – I
(2
(3)
Power Plant – II
Generator
Generator
Transmission Line
1
Transformer 1
Transformer 2
Fig.3: Single Line Diagram for Faults at Bus 2.
Positive, Negative and Zero sequence Z-buses are given as:
[j0.19
jo.08 jo.08
jo.08 j0.58
0 0
[j0.1437 jo.1211 j0.0789 jo.0563]
jo.1211 j0.1696 j0.1104 j0.0789
jo.0789 j0.1104 j0.1696 j0.1211
Ljo.o563 jo.0789 j0.01211 j0.1437]
z
(o)-
bus
z(1 = z2)
bus
bus
jo.19]
Transcribed Image Text:Analyze power system as shown in Fig. 3 subject to (a) Line to Ground bolted fault (b) Line to Line Bolted Fault occurred at bus 2. Compare values of symmetrical and unsymmetrical values of fault currents and fault voltage at fault bus under (a) Line to Ground Bolted Fault (b) Line to Line Bolted Fault. Pre-fault voltages can be assumed as 1+ 0j = 1 < 0° per unit. Transformers Tị and T2 have 345 Y / 20 A KV Transformation Ratio. Power Plant – I (2 (3) Power Plant – II Generator Generator Transmission Line 1 Transformer 1 Transformer 2 Fig.3: Single Line Diagram for Faults at Bus 2. Positive, Negative and Zero sequence Z-buses are given as: [j0.19 jo.08 jo.08 jo.08 j0.58 0 0 [j0.1437 jo.1211 j0.0789 jo.0563] jo.1211 j0.1696 j0.1104 j0.0789 jo.0789 j0.1104 j0.1696 j0.1211 Ljo.o563 jo.0789 j0.01211 j0.1437] z (o)- bus z(1 = z2) bus bus jo.19]
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 7 images

Blurred answer
Knowledge Booster
Fault analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Power System Analysis and Design (MindTap Course …
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning