Assume that, as a part of its economic development program, your governmental agency has committed to provide access to a new regional industrial park. This project must fund the construction of an on/off-interchange from an adjacent highway, a 2-mile length of 4-lane divided roadway, and a bridge that will cross a 500-foot wide river. The entire project is estimated to require 2 years to complete following planning & design.a. The interchange is projected to cost $50 million. It will need to begin construction in 18 months. Rights-of-way acquisition, surveying, and permitting have already been completed and paid for by the program. There will be 2 additional project phases: 1) planning & design, 2) construction. Each will require payment at the end of the phase. The projected cost of the 1st phase of the project is $2.5 million. The 1st phase is expected to need the entire 18 months prior to the start of construction and must be completed before construction can begin. The 2nd phase is projected to cost the remaining $47.5 million. It is expected to be completed at the end of the 2-year period following planning & design.b. The roadway to be constructed is projected to cost $125,000 per lane mile. It will need to begin construction 12 months prior to the project’s estimated completion date. Your government controls the permitting process for the roadway and has already issued the necessary permits. The total roadway project will be paid for at its completion.c. At the same time as the interchange is being constructed, the bridge project must also be underway. The bridge is projected to cost $48 million. It will also need to begin construction in 18 months. Rights-of-way acquisition, surveying, and permitting have already been completed and paid for by the program. There will be 2 additional project phases: 1) planning & design, 2) construction. Each will require payment at the end of the phase. The projected cost of the 1st phase of the project is $5.5 million. The 1st phase is expected to need the entire 18 months prior to the start of construction and must be completed before construction can begin. The 2nd phase is projected to cost the remaining $42.5 million. Its construction is also expected to be completed at the end of the 2-year period following planning & design. Unlike the roadway, there will need to be a payout of 30% of the cost of construction at the end of the 1st year of the construction project. The remaining 70% will be paid at the completion of the project.Assuming a discount rate of 4.25% and monthly compounding, what amount will need to be funded today to meet the complete project’s funding requirements on the payment due dates.

Century 21 Accounting Multicolumn Journal
11th Edition
ISBN:9781337679503
Author:Gilbertson
Publisher:Gilbertson
Chapter18: Acquiring Capital For Growth And Development
Section: Chapter Questions
Problem 1CP
icon
Related questions
Question

Assume that, as a part of its economic development program, your governmental agency has committed to provide access to a new regional industrial park. This project must fund the construction of an on/off-interchange from an adjacent highway, a 2-mile length of 4-lane divided roadway, and a bridge that will cross a 500-foot wide river. The entire project is estimated to require 2 years to complete following planning & design.
a. The interchange is projected to cost $50 million. It will need to begin construction in 18 months. Rights-of-way acquisition, surveying, and permitting have already been completed and paid for by the program. There will be 2 additional project phases: 1) planning & design, 2) construction. Each will require payment at the end of the phase. The projected cost of the 1st phase of the project is $2.5 million. The 1st phase is expected to need the entire 18 months prior to the start of construction and must be completed before construction can begin. The 2nd phase is projected to cost the remaining $47.5 million. It is expected to be completed at the end of the 2-year period following planning & design.
b. The roadway to be constructed is projected to cost $125,000 per lane mile. It will need to begin construction 12 months prior to the project’s estimated completion date. Your government controls the permitting process for the roadway and has already issued the necessary permits. The total roadway project will be paid for at its completion.
c. At the same time as the interchange is being constructed, the bridge project must also be underway. The bridge is projected to cost $48 million. It will also need to begin construction in 18 months. Rights-of-way acquisition, surveying, and permitting have already been completed and paid for by the program. There will be 2 additional project phases: 1) planning & design, 2) construction. Each will require payment at the end of the phase. The projected cost of the 1st phase of the project is $5.5 million. The 1st phase is expected to need the entire 18 months prior to the start of construction and must be completed before construction can begin. The 2nd phase is projected to cost the remaining $42.5 million. Its construction is also expected to be completed at the end of the 2-year period following planning & design. Unlike the roadway, there will need to be a payout of 30% of the cost of construction at the end of the 1st year of the construction project. The remaining 70% will be paid at the completion of the project.

Assuming a discount rate of 4.25% and monthly compounding, what amount will need to be funded today to meet the complete project’s funding requirements on the payment due dates.

Expert Solution
steps

Step by step

Solved in 1 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Century 21 Accounting Multicolumn Journal
Century 21 Accounting Multicolumn Journal
Accounting
ISBN:
9781337679503
Author:
Gilbertson
Publisher:
Cengage
Century 21 Accounting General Journal
Century 21 Accounting General Journal
Accounting
ISBN:
9781337680059
Author:
Gilbertson
Publisher:
Cengage
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L