Green Vehicle Inc., manufactures electric cars and small delivery trucks. It has just opened a new factory where the C1 car and the To make either vehicle, processing in the assembly shop and in the paint shop are required. It takes 1/30 of a day and 1/75 of a day to paint a truck of type T1 and a car of type C1 in the paint shop, respectively. It takes 1/45 of a day to assemble either type of vehicle in the assembly shop. AT1 truck and a C1 car yield profits of $325 and $250, respectively, per vehicle sold The aim of the objective function for Green Vehicle Inc. should be to Maximize the objective value. The optimum solution is: Number of trucks to be produced per day (round your response to two decimal places).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question

11

Green Vehicle Inc., manufactures electric cars and small delivery trucks. It has just opened a new factory where the C1 car and the T1 truck can both be manufactured
To make either vehicle, processing in the assembly shop and in the paint shop are required. It takes 1/30 of a day and 1/75 of a day to paint a truck of type T1 and a
car of type C1 in the paint shop, respectively. It takes 1/45 of a day to assemble either type of vehicle in the assembly shop.
AT1 truck and a C1 car yield profits of $325 and $250, respectively, per vehicle sold
The aim of the objective function for Green Vehicle Inc. should be to Maximize the objective value.
The optimum solution is:
Number of trucks to be produced per day (round your response to two decimal places).
=
Transcribed Image Text:Green Vehicle Inc., manufactures electric cars and small delivery trucks. It has just opened a new factory where the C1 car and the T1 truck can both be manufactured To make either vehicle, processing in the assembly shop and in the paint shop are required. It takes 1/30 of a day and 1/75 of a day to paint a truck of type T1 and a car of type C1 in the paint shop, respectively. It takes 1/45 of a day to assemble either type of vehicle in the assembly shop. AT1 truck and a C1 car yield profits of $325 and $250, respectively, per vehicle sold The aim of the objective function for Green Vehicle Inc. should be to Maximize the objective value. The optimum solution is: Number of trucks to be produced per day (round your response to two decimal places). =
Expert Solution
steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,