Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($72 million) Below average 0.20 (24 million) Average 0.50 12 million Above average 0.20 14 million Вoom 0.05 38 million Calculate the project's expected NPV, standard deviation, and coefficient of variation. Enter your answers for the project's expected NPV and standard deviation in millions. For example, an answer of $13,000,000 should be entered as 13. Do not round intermediate calculations. Round your answers to two decimal places. E(NPV): million ONPV: million CV:

College Algebra
1st Edition
ISBN:9781938168383
Author:Jay Abramson
Publisher:Jay Abramson
Chapter9: Sequences, Probability And Counting Theory
Section9.7: Probability
Problem 1SE: What term is used to express the likelihood of an event occurring? Are there restrictions on its...
icon
Related questions
Question
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average."
However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results:
Economic Scenario Probability of Outcome
NPV
Recession
0.05
($72 million)
Below average
0.20
(24 million)
Average
0.50
12 million
Above average
0.20
14 million
Boom
0.05
38 million
Calculate the project's expected NPV, standard deviation, and coefficient of variation. Enter your answers for the project's expected NPV and standard
deviation in millions. For example, an answer of $13,000,000 should be entered as 13. Do not round intermediate calculations. Round your answers to two
decimal places.
E(NPV):
million
ONPV:
million
CV:
Transcribed Image Text:Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($72 million) Below average 0.20 (24 million) Average 0.50 12 million Above average 0.20 14 million Boom 0.05 38 million Calculate the project's expected NPV, standard deviation, and coefficient of variation. Enter your answers for the project's expected NPV and standard deviation in millions. For example, an answer of $13,000,000 should be entered as 13. Do not round intermediate calculations. Round your answers to two decimal places. E(NPV): million ONPV: million CV:
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Tree
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, statistics and related others by exploring similar questions and additional content below.
Recommended textbooks for you
College Algebra
College Algebra
Algebra
ISBN:
9781938168383
Author:
Jay Abramson
Publisher:
OpenStax