Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended:Standard variable-overhead rate per hour: $2.50Standard fixed-overhead rate per hour: $4.00Planned activity during the period: 20,000 machine hoursActual production: 10,700 finished unitsMachine-hour standard: Two completed units per machine hourActual variable overhead: $55,440Actual total overhead: $155,900Actual machine hours worked: 23,100 Required: Did Maxwell spend more or less than anticipated for fixed overhead? How much? .Was variable overhead underapplied or overapplied during the year? By how much?
"Maxwell Company uses a
Required:
Did Maxwell spend more or less than anticipated for fixed overhead? How much?
.Was variable overhead underapplied or overapplied during the year? By how much?