Task-2 A radial feeder is shown in Figure 1. -3-Phase Transmission Line Bus-A Bus-B Bus-C Bus-D CB, CT CB, CTB CB.CTC 个 G .... 30MVA RA Re 11 kV Load-A Load-B Load-C Load-D 3MVA 7.5MVA 5.5MVA 6MVA Figure 1 Radial Feeder Time graded overcurrent protection scheme is to be designed for this feeder using Inverse Definite Minimum Time (IDMT) relays at all busses. The maximum fault current of 10000 Ampere and a minimum fault current of 4000 Ampere is expected to flow for three-phase fault and single line to ground fault, respectively, between bus C and D. IDMT relays located at all buses can be assumed to be of 1 Ampere OR 5 Ampere rating with 100% plug setting. Circuit breakers at bus B and C take 0.6 S to operate. Relay located at bus A has an overshoot time of 0.08 S while relay at bus B has an overshoot time of 0.1 S. The Time Setting Multiplier (TSM) QEAD- Template A Rev: 04_ ver 02 Date: 014 October 2018 Page 2 of 6 F/QAP/021/001 for the fastest relay is to be set to 0.5. Neglect the voltage drop in the line sections for the calculations. ASsume the Overload capacity of this feeder in the range of 20-35%. (i) Design appropriate CT ratios for CTA, CTB, and CTc. [06] (ii) Estimate time of Operation for all three relays for maximum value of fault current to maintain the selectivity. [06] (ii) Determine TSM for relays at bus A and B for maximum fault current. (Use the standard formula for IDMT relays for these calculations.) [06]

Power System Analysis and Design (MindTap Course List)
6th Edition
ISBN:9781305632134
Author:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Chapter5: Transmission Lines: Steady-state Operation
Section: Chapter Questions
Problem 5.30P
icon
Related questions
Question
100%
Please I need step by step solution.
Task-2
A radial feeder is shown in Figure 1.
-3-Phase Transmission Line
Bus-A
Bus-B
Bus-C
Bus-D
Zs
св, ст
CB, CTB
CB. CT.
G
30MVA
Ra
R.
11 kV
Load-C
Load-D
Load-A
3MVA
Load-B
7.5MVA
5.5MVA
6MVA
Figure 1 Radial Feeder
Time graded overcurrent protection scheme is to be designed for this feeder using Inverse
Definite Minimum Time (IDMT) relays at all busses. The maximum fault current of 10000
Ampere and a minimum fault current of 4000 Ampere is expected to flow for three-phase fault
and single line to ground fault, respectively, between bus C and D. IDMT relays located at all
buses can be assumed to be of 1 Ampere OR 5 Ampere rating with 100% plug setting. Circuit
breakers at bus B and C take 0.6 S to operate. Relay located at bus A has an overshoot time of
0.08 S while relay at bus B has an overshoot time of 0.1 S. The Time Setting Multiplier (TSM)
QEAD- Template A
Rev: 04_ ver 02
Date: 01 October 2018
Page 2 of 6
F/QAP/021/001
for the fastest relay is to be set to 0.5. Neglect the voltage drop in the line sections for the
calculations. Assume the Overload capacity of this feeder in the range of 20-35%.
(1)
Design appropriate CT ratios for CTA, CTB, and CTc.
[06]
(ii)
Estimate time of Operation for all three relays for maximum value of fault current to
maintain the selectivity.
[06]
(iii)
Determine TSM for relays at bus A and B for maximum fault current. (Use the
standard formula for IDMT relays for these calculations.)
[06]
Transcribed Image Text:Task-2 A radial feeder is shown in Figure 1. -3-Phase Transmission Line Bus-A Bus-B Bus-C Bus-D Zs св, ст CB, CTB CB. CT. G 30MVA Ra R. 11 kV Load-C Load-D Load-A 3MVA Load-B 7.5MVA 5.5MVA 6MVA Figure 1 Radial Feeder Time graded overcurrent protection scheme is to be designed for this feeder using Inverse Definite Minimum Time (IDMT) relays at all busses. The maximum fault current of 10000 Ampere and a minimum fault current of 4000 Ampere is expected to flow for three-phase fault and single line to ground fault, respectively, between bus C and D. IDMT relays located at all buses can be assumed to be of 1 Ampere OR 5 Ampere rating with 100% plug setting. Circuit breakers at bus B and C take 0.6 S to operate. Relay located at bus A has an overshoot time of 0.08 S while relay at bus B has an overshoot time of 0.1 S. The Time Setting Multiplier (TSM) QEAD- Template A Rev: 04_ ver 02 Date: 01 October 2018 Page 2 of 6 F/QAP/021/001 for the fastest relay is to be set to 0.5. Neglect the voltage drop in the line sections for the calculations. Assume the Overload capacity of this feeder in the range of 20-35%. (1) Design appropriate CT ratios for CTA, CTB, and CTc. [06] (ii) Estimate time of Operation for all three relays for maximum value of fault current to maintain the selectivity. [06] (iii) Determine TSM for relays at bus A and B for maximum fault current. (Use the standard formula for IDMT relays for these calculations.) [06]
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Knowledge Booster
State Variable Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Power System Analysis and Design (MindTap Course …
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning