CFIN
CFIN
5th Edition
ISBN: 9781305661639
Author: Scott Besley, Eugene Brigham
Publisher: Cengage Learning
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 10, Problem 17PROB
Summary Introduction

Scenario Analysis is a technique used to identify the project’s risk and compare the bad and good circumstances with the base case scenario. It considers both the 1) sensitivity of the project’s NPV to its key variables and 2) the change in values of these variables considering their probability distribution.

To carry out the scenario analysis, it is required to calculate the NPV of worst case, best case and base case, followed by the calculation of its standard deviation and co-efficient of variation. If the co-efficient of variation is higher than the average project of the company, the project should be rejected.

Expected NPV, Standard deviation of NPVs and co-efficient of variation of NPVs are calculated as below:

Expected NPV=i=1nPri(NPVi)             σNPV=i=1nPri(NPViExpected NPV)2  CVNPV=σNPVExpected NPV

Here,

Probabilities of the occurrence is “Pri

NPV for each probability is “NPVi

Standard deviation of NPVs is “σNPV

Co-efficient of Variation of NPVs is “CVNPV

After conducting a scenario analysis, it is estimated, that the NPV of the project for all the three scenarios is as follows. Determine whether the project should be accepted or rejected if the maximum allowable co-efficient of variation is 0.8.

Scenario Probability NPV
Best Case 20% $31,500
Base Case 70% $19,800
Worst Case 10% -$20,100

Blurred answer
Students have asked these similar questions
Huang Industries is considering a proposed project whose estimatedNPV is $12 million. This estimate assumes that economic conditions will be “average.”However, the CFO realizes that conditions could be better or worse, so she performed ascenario analysis and obtained these results: Calculate the project’s expected NPV, standard deviation, and coefficient of variation.
Desai Industries is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price should increase with inflation. Fixed costs will also be constant, but variable costs should rise with inflation. The project should last for 3 years, it will be depreciated on a straight-line basis, and there will be no salvage value. No change in net operating working capital would be required. This is just one of many projects for the firm, so any losses on this project can be used to offset gains on other firm projects. What is the project's expected NPV? 10.0% $200,000 39,000 $25.00 WACC Net investment cost (depreciable basis) Units sold Average price per unit, Year 1 Fixed op. costs excl. depr. (constant) Variable op. cost/unit, Year 1 Annual depreciation rate Expected inflation rate per year Tax rate Oa. -$64.886 Ob. -$66,833 Oc. -$72,673 O d. -$73,970 O e. -$60,993 $150,000 $20.20 33.333% 5.00% 40.0%
Adam Andler Corp is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price should increase with inflation. Fixed costs will also be constant, but variable costs should rise with inflation. The project should last for 3 years. This is just one of many projects for the firm, so any losses on this project can be used to offset gains on other firm projects. What is the project's expected NPV? Do not round the intermediate calculations and round the final answer to the nearest whole number. WACC or cost of capital Net investment cost (depreciable basis) The salvage value of its equipment No other fixed assets will be acquired for following years The company will require an increase in net working capital at the $10,000 beginning The company will liquidate all working capital at the end of the project -10,000 Units sold (constant through years) 60,000 $30.00 $50,000 $17.00 Average price per unit, Year 1 Fixed operating…
Knowledge Booster
Background pattern image
Finance
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Text book image
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Financial Risks - Part 1; Author: KnowledgEquity - Support for CPA;https://www.youtube.com/watch?v=mFjSYlBS-VE;License: Standard youtube license