Summary Introduction

To determine: The time for each line at each of the cashier windows.

a)

Expert Solution
Check Mark

Explanation of Solution

Determine the arrival and service rate using waiting line approximation:

X¯a=4Sa=4X¯s=7Ss=3S=2

Determine interarrival time:

Ca=SaX¯a=44=1

Determine service time:

Cs=SsX¯s=37=0.4286

Determine arrival and service time:

λ=1X¯a=14=0.25

μ=1X¯s=17=0.1429

ρ=λSμ=0.252(0.1429)=0.875

Determine the time for each line at each of the cashier windows:

Lq=ρ2(S+1)1ρ×Ca2+Cs22=0.87502(2+1)10.8750×12+0.428622=0.72100.125×1.1842=3.4147

Hence, the time for each line at each of the cashier windows is 3.4147.

b)

Summary Introduction

To determine: The time spent by the customer in the bank.

b)

Expert Solution
Check Mark

Explanation of Solution

Determine the arrival and service rate using waiting line approximation:

X¯a=4Sa=4X¯s=7Ss=3S=2

Determine interarrival time:

Ca=SaX¯a=44=1

Determine service time:

Cs=SsX¯s=37=0.4286

Determine arrival and service time:

λ=1X¯a=14=0.25

μ=1X¯s=17=0.1429

ρ=λSμ=0.252(0.1429)=0.875

Determine the time spent by the customer in the bank:

Lq=ρ2(S+1)1ρ×Ca2+Cs22=0.87502(2+1)10.8750×12+0.428622=0.72100.125×1.1842=3.4147

Ls=Lq+Sρ=3.4147+(2)(0.8750)=3.4147+1.75=5.1647

Ws=Lsλ=5.16470.25=20.6588

Hence, the time spent by the customer in the bank is 20.6588.

c)

Summary Introduction

To determine: The term for the given information.

c)

Expert Solution
Check Mark

Explanation of Solution

Determine the term for the given information:

Whenever the cashier spends idle, the amount of time stays the same and it would not increase or decrease.

d)

Summary Introduction

To determine: The term for the given information.

d)

Expert Solution
Check Mark

Explanation of Solution

Determine the term for the given information:

There would be a decrease in the average amount of time a customer spends in the bank.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.