The levelized cost of energy (LCOE) for coal-fired electricity is about $0.09/kWh. Suppose the capital cost of the plant is $600 million and it operates for 40 years with a capacity factor of 95%. What is the contribution of CAPEX to LCOE? Given the difference you (hopefully) find, what contributes the remaining costs?
Problem T3 If the shaft power is 82kw and the cost of the electricity is $0.10 kwh; estimate the cost of the electricity for one hour. Answer $8.2
Installed capacity of the plant 200 MW Capital cost = Rs 400 crores Rate of interest and depreciation= 12% Annual cost of fuel, salaries and taxation = Rs 5 crores Load factor = 50% Also estimate the saving in cost per kWh if the annual load factor is raised to 60%. calculate the cost of generation per kwh for a power station.

Chapter 10 Solutions

Bundle: Sustainable Energy, 2nd + Mindtap Engineering, 1 Term (6 Months) Printed Access Card

Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Sustainable Energy
    Civil Engineering
    ISBN:9781337551663
    Author:DUNLAP, Richard A.
    Publisher:Cengage,
Text book image
Sustainable Energy
Civil Engineering
ISBN:9781337551663
Author:DUNLAP, Richard A.
Publisher:Cengage,