Calculate the total operation time for this construction activity if the volume of soil to be removed is 8 cu.m. (considered 33% for bulking of materials.) The speed of dumptruck is 30 kph and travel distance (round trip) from the source to disposal area vice-versa is 6 km. The bucket size of excavator is 0.50 cu.m at 0.50 min loading time, tipping time is 4 mins. a. 15.18 minutes b. 22.02 minutes c. 25.32 minutes d. 30.00 minutes
A contractor is to excavate an area of 350′ × 150′ to a depth of 9′ and haul it by dump truck to a site where it is to be used for fill. The soil will then be fully compacted. If the swell factor is 25 percent and the shrinkage factor is 18 percent. Estimate the total bare cost for the job (excavation only) using a 2½ CY front-end loader, track mounted. Consider average nation price. Use the crew below.
Describe two (2) expected impacts to the physical environment for each stage of a quarry operation e.g. (Development, (Production/Operation) & Decommissioning).
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,