![Intermediate Accounting, Student Value Edition Plus MyLab Accounting with Pearson eText -- Access Card Package (2nd Edition)](https://www.bartleby.com/isbn_cover_images/9780134833118/9780134833118_largeCoverImage.gif)
Intermediate Accounting, Student Value Edition Plus MyLab Accounting with Pearson eText -- Access Card Package (2nd Edition)
2nd Edition
ISBN: 9780134833118
Author: Elizabeth A. Gordon, Jana S. Raedy, Alexander J. Sannella
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Question
Chapter 11, Problem 11.2P
a.
To determine
The amount of the interest to be capitalized.
b.
To determine
To prepare: The required journal entries.
c.
To determine
The Final valuation of the power plant
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
(Capitalization of Borrowing Costs) In early February 2023, Huey Corp. began construction of
an addition to its head office building that is expected to take 18 months to complete. The
following 2023 expenditures relate to the addition: Feb. 1
120,000 Mar. 1
Payment to architect
24,000 July 1
Payment #1 to contractor $
Payment #2 to contractor
60,000 Dec. 1
Payment #3 to contractor
180, 000 Dec. 31 Asset carrying amount
$384,000 On February 1, Huey issued a $100,000, three-year note payable at a rate of 12%
to finance most of the initial payment to the contractor. No other asset-specific debt was
entered into. Details of other interest-bearing debt during the period are provided in the
table below: Other Debt Instruments Outstanding-2023
bonds, issued May 1, 2008, matured May 1, 2023
Principal Amount 9%, 15-year
$300,000 7%, 10-year bonds, issued
June 15, 2017 $500,000 6%, 12-year bonds, issued May 1, 2023
$300,000 Instructions
What amount of interest should be capitalized for the…
Required information
[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Revenue
Gross profit (loss)
2021
2022
$2,610,000 $3,162,000
6,390,000 2,028,000
2,100,000
1,850,000
2021
2022
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate
calculations. Loss amounts should be indicated with a minus sign.)
2023
$2,230,800
2023
0
3,672,000 4,228,000
5,150,000
3,000,000
At the beginning of 2021, Florida Road Construction entered into a contract to build a road for the government. Construction will take four
years. The following information as of December 31, 2021 is available:
Revenue according to contract
10,000,000
Total expected cost
8,000,000
Cost incurred during 2021
1,200,000
Cost incurred during 2022
2,400,000
Cost incurred during 2023
Cost incurred during 2024
1,600,000
2,800,000
Compute for the reported Gross Profit of Florida using:
Year
2021
2022
2023
2024
Completed Contract Method
Zero Profit Method
Percentage of Completion Method
Chapter 11 Solutions
Intermediate Accounting, Student Value Edition Plus MyLab Accounting with Pearson eText -- Access Card Package (2nd Edition)
Ch. 11 - Stephen J. Cosgrove is the Former Vice President....Ch. 11 - Prob. 11.2QCh. 11 - Prob. 11.3QCh. 11 - Prob. 11.4QCh. 11 - Will the expense/capitalization choice impact...Ch. 11 - Prob. 11.6QCh. 11 - Prob. 11.7QCh. 11 - For a long-lived operating asset acquired by...Ch. 11 - Prob. 11.9QCh. 11 - Prob. 11.10Q
Ch. 11 - Prob. 11.11QCh. 11 - What is the maximum amount of interest to be...Ch. 11 - Prob. 11.13QCh. 11 - Prob. 11.14QCh. 11 - Prob. 11.15QCh. 11 - Do firms expense all costs incurred after the...Ch. 11 - Prob. 11.17QCh. 11 - Prob. 11.18QCh. 11 - When using the double-declining balance...Ch. 11 - Prob. 11.20QCh. 11 - Will a firm recognize a loss on the income...Ch. 11 - Prob. 11.22QCh. 11 - Prob. 11.23QCh. 11 - Prob. 11.24QCh. 11 - Prob. 11.25QCh. 11 - Differentiate between a leasehold and a leasehold...Ch. 11 - Prob. 11.27QCh. 11 - Prob. 11.28QCh. 11 - Prob. 11.29QCh. 11 - Prob. 11.30QCh. 11 - Prob. 11.31QCh. 11 - Prob. 11.32QCh. 11 - Prob. 11.33QCh. 11 - Prob. 11.34QCh. 11 - Prob. 11.35QCh. 11 - Prob. 11.36QCh. 11 - Prob. 11.37QCh. 11 - Prob. 11.38QCh. 11 - Prob. 11.39QCh. 11 - Prob. 11.40QCh. 11 - In a nonmonetary exchange does a firm record the...Ch. 11 - Prob. 11.42QCh. 11 - Prob. 11.43QCh. 11 - Prob. 11.44QCh. 11 - Prob. 11.45QCh. 11 - Prob. 11.1MCCh. 11 - On January 1, Year 1, Bluebird Inc. borrowed 10...Ch. 11 - Prob. 11.3MCCh. 11 - Prob. 11.4MCCh. 11 - Prob. 11.5MCCh. 11 - Prob. 11.6MCCh. 11 - Prob. 11.7MCCh. 11 - Prob. 11.8MCCh. 11 - Determining Acquisition Cost. Haply, Inc. incurred...Ch. 11 - Determining Acquisition Cost. Tarpley, Inc....Ch. 11 - Prob. 11.3BECh. 11 - Prob. 11.4BECh. 11 - Prob. 11.5BECh. 11 - Prob. 11.6BECh. 11 - Prob. 11.7BECh. 11 - Prob. 11.8BECh. 11 - Depreciation, Straight-Line Method. Hermit...Ch. 11 - Prob. 11.10BECh. 11 - Prob. 11.11BECh. 11 - Prob. 11.12BECh. 11 - Prob. 11.13BECh. 11 - Derecognition Due to Abandonment. Greene Corp....Ch. 11 - Prob. 11.15BECh. 11 - Prob. 11.16BECh. 11 - Prob. 11.17BECh. 11 - Prob. 11.18BECh. 11 - Prob. 11.19BECh. 11 - Prob. 11.20BECh. 11 - Leasehold Improvements. At the beginning of its...Ch. 11 - Determining Acquisition Cost. St Charles Flooring...Ch. 11 - Prob. 11.2ECh. 11 - Prob. 11.3ECh. 11 - Acquiring an Asset with a Note Payable (Deferred...Ch. 11 - Prob. 11.5ECh. 11 - Prob. 11.6ECh. 11 - Capitalization of Interest, Specific and General...Ch. 11 - Prob. 11.8ECh. 11 - Prob. 11.9ECh. 11 - Capitalization of Interest, Specific and General...Ch. 11 - Prob. 11.11ECh. 11 - Expensing versus Capitalizing ExpendituresAnalysis...Ch. 11 - Depreciation Methods, Disposal. Kurtis Koal...Ch. 11 - Prob. 11.14ECh. 11 - Depreciation Methods, Partial-Year Depreciation....Ch. 11 - Prob. 11.16ECh. 11 - Depreciation Methods. Ace Manufacturing, Inc....Ch. 11 - Prob. 11.18ECh. 11 - Depreciation Methods, Partial-Year Depreciation,...Ch. 11 - Prob. 11.20ECh. 11 - Partial-Year Depreciation, Sale of Property,...Ch. 11 - Prob. 11.22ECh. 11 - Disclosure of Property, Plant, and Equipment. Use...Ch. 11 - Disclosure of Property, Plant, and Equipment,...Ch. 11 - Prob. 11.25ECh. 11 - Research and Development Activities. During the...Ch. 11 - Prob. 11.27ECh. 11 - Goodwill Computation, Acquisition of Intangibles,...Ch. 11 - Prob. 11.29ECh. 11 - Prob. 11.30ECh. 11 - Prob. 11.31ECh. 11 - Prob. 11.32ECh. 11 - Prob. 11.33ECh. 11 - Prob. 11.34ECh. 11 - Prob. 11.35ECh. 11 - Prob. 11.36ECh. 11 - Prob. 11.37ECh. 11 - Exchanges Lacking Commercial Substance, Cash...Ch. 11 - Prob. 11.39ECh. 11 - Prob. 11.41ECh. 11 - Prob. 11.42ECh. 11 - Note Payable Exchanged for a Plant Asset (Deferred...Ch. 11 - Prob. 11.2PCh. 11 - Prob. 11.3PCh. 11 - Depreciation Methods and Depreciation Schedules....Ch. 11 - Prob. 11.5PCh. 11 - Disposals of Long-Term Operating AssetsAnalysis,...Ch. 11 - Goodwill and Bargain Purchase Computations. The...Ch. 11 - Prob. 11.8PCh. 11 - Prob. 11.9PCh. 11 - Prob. 11.10PCh. 11 - Prob. 11.11PCh. 11 - Judgment Case 1: Property, Plant, and Equipment:...Ch. 11 - Prob. 2JCCh. 11 - Financial Statement Analysis Case Financial...Ch. 11 - Surfing the Standards Cases Surfing the Standards...Ch. 11 - Prob. 2SSCCh. 11 - Surfing the Standards Case 3: Involuntary...Ch. 11 - Prob. 4SSCCh. 11 - Prob. 5SSCCh. 11 - Prob. 1BCCCh. 11 - Prob. 2BCC
Knowledge Booster
Similar questions
- GinebraCorporation recognizes construction revenue and cost using the percentage of completion method. During 2021, a single long-term project was begun which continued through 2021. Information on the project follows: 2021. 2022 Partial billing on contract 1,000,000. 4,200,000 Accounts receivable 1,000,000 3,000,000 Construction cost 1,050,000 1,920,000 Construction in progress 1,220,000 3,640,000 What is the gross profit recognized from this long-term construction contract in year 2021 and 2022, respectively? 2021 2022 A.220,000. 2,280,000 B.170,000. 500,000 C.220,000. 1,000,000 D.170,000. 1,280,000arrow_forwardRequired information [The following information applies to the questions displayed below] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,100,000 2022 $3,150,000 2023 $2,475,000 5,400,000 2,150,000 2,250,000 3,100,000 8 1,875,000 3,100,000 4,750,000 5,025,000 Westgate recognizes revenue over time according to percentage of completion. 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) Balance Sheet (Partial) Current assets Current liabilities: 2021 2022 0 0arrow_forwardAssume Avaya contracted to provide a customer with Internet infrastructure for $2,200,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming Avaya recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time according to percentage of completion. 4. Prepare a partial balance sheet to show how the information related to this contract would be presented at…arrow_forward
- Assume Avaya contracted to provide a customer with Internet infrastructure for $2,200,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming Avaya recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time according to percentage of completion. 4. Prepare a partial balance sheet to show how the information related to this contract would be presented at…arrow_forwardAssume Avaya contracted to provide a customer with Internet infrastructure for $2,200,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming Avaya recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time according to percentage of completion. 4. Prepare a partial balance sheet to show how the information related to this contract would be presented at…arrow_forwardSandhill Construction, which follows ASPE entered into a contract to construct a bridge for a contract price of $2.8 million. Construction began in 2022 and was completed in 2024. Below are the details of the transactions related to the contract: Costs incurred during the year Estimated costs to complete Revenue Expenses $ Gross Profit $ 2022 2022 $637,000 1,489,000 $844,000 Calculate the gross profit to be recognized each year using the completed-contract method. 2023 $ $ 713,000 2024 $715,900 2023 0 $ $ 2024 SUPPORTarrow_forward
- Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,100,000 2023 $2,695,000 2022 $2,450,000 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to percentage of completion. Ø 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for…arrow_forwardIn 2024, Cupid Construction Company (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2024 (from construction progress billings) $ 37.5 Actual construction costs incurred in 2024 $ 135 Cash collected on project during 2024 $ 105 Construction in progress, 12/31/2024 $ 207 Estimated percentage of completion during 2024 60% What were the construction billings by CCC during 2024?arrow_forwardes In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 $ 3,471,000 5,429,000 2,900,000 2,700,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Cost incurred during the year Estimated costs to complete as of year-end 2025 $ 4,005,000 1,424,000 4,576,000 4,500,000 Cost incurred during the year Estimated costs to complete as of year-end Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2024 $ 2,490,000 5,690,000 2-b.…arrow_forward
- help mearrow_forwardIn 2021, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2021 (from construction progress billings) $ 37.5 Actual construction costs incurred in 2021 $ 135 Cash collected on project during 2021 $ 105 Construction in progress, 12/31/2021 $ 207 Estimated percentage of completion during 2021 60 % How much cash remains to be collected by CCC on the project?arrow_forwardnterest During Construction Alta Company is constructing a production complex that qualifies for interest capitalization. The following information is available: Capitalization period: January 1, 2019, to June 30, 2020 Expenditures on project: 2019: January 1 $ 492,000 May 1 441,000 October 1 648,000 2020: March 1 1,392,000 June 30 708,000 Amounts borrowed and outstanding: $1.7 million borrowed at 10%, specifically for the project $5 million borrowed on July 1, 2018, at 12% $12 million borrowed on January 1, 2017, at 6% Required: Note: Round all final numeric answers to two decimal places. Compute the amount of interest costs capitalized each year. Capitalized interest, 2019 $ fill in the blank 1 Capitalized interest, 2020 $ fill in the blank 2 If it is assumed that the production complex has an estimated life of 25 years and a residual value of $0, compute the straight-line depreciation in 2020. $ fill in the blank 3 Since…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337788281/9781337788281_smallCoverImage.jpg)
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning